AI summaryCabinet noted Aylesbury regeneration progress, NHHT demolitions and phased Phase 4 notices, with a one year purchase scheme, £69m remaining budget and further capital reporting [D] [P18] [P32] [P55].
Written from the decision and the officer reportPDF Pro
OutcomeAgreedDemolition and phased notice principles noted [D]
Money£69m remaining budget [P55]Approved total budget is £76.7m [P48]
What happens nextFurther Cabinet capital reports [P18]ERP funding checks and budget changes remain outstanding [P18]
Who it affectsAylesbury tenants and leaseholders [P39]Rehousing options and support continue [P41] [P42] [P43]
What was decided
Cabinet noted the NHHT planning application positions, rehousing progress, 57-76 Northchurch moving into Phase 2, the one year purchase programme, community facility design, Affordable Homes Programme funding and the ERP application [D]. The planning work comprises a detailed application for the First Development Site and an outline application for Phases 2, 3 and 4 [D].
NHHT will undertake demolition of existing buildings at the First Development Site, Plot 18 and in Phase 2 under the DPA [D] [P22]. Report P22
The director of housing and community services will serve phased demolition notices on Phase 4 blocks as the programme comes forward [D] [P32] [P70]. Report P32, P70
Why
NHHT sought additional funding that could reduce the programme's effect on council finances over its lifetime [P4]. Report P4
Procuring demolition through NHHT followed advice on VAT and was expected to improve redevelopment efficiency and secure competitive demolition prices [P22] [P23]. Report P22, P23
Phased demolition notices were intended to reduce the effect of Right to Buy activity on property acquisition costs [P26] [P29] [P32]. Report P26, P29, P32
What happens next
Exact demolition costs will be subject to a competitive tender and further reports to Cabinet [D] [P24]. Report P24
ERP funding checks will be completed by the Homes and Communities Agency, then the final funding and interest rate will be confirmed, spending across years revised and the position reported to Cabinet [P18] [P54] [P56] [P65]. Report P18, P54, P56, P65
Once the revised programme is approved, the director will serve Phase 4 demolition notices as blocks enter the seven year period [D] [P32]. Report P32
The money
approximately £150m Estimated cost of acquiring all property interests, including vacant possession and above ground demolition [P1] [P59] Report P1, P59
£76.7m Approved total Aylesbury regeneration capital budget [P48] Report P48
£27,452,000 Affordable Homes Programme social housing grant allocation secured by NHHT [P6] Report P6
up to £46.1m Potential Estate Regeneration Programme loan funding following shortlisting [P9] Report P9
£9.2m Demolition costs included for Phase 1 [P13] Report P13
£13m Demolition costs included for Phase 2 [P13] Report P13
£53.7m Variation to the Aylesbury capital budget [P48] Report P48
£69m Remaining capital budget for 2014/15 to 2021/22 [P55] Report P55
Options considered
Rejected: Council directly procures above ground demolition. VAT advice led to use of the DPA option for NHHT to procure the work [P21] [P22]. Report P21, P22
Chosen: NHHT procures above ground demolition at the First Development Site, Plot 18 and in Phase 2. This was expected to improve redevelopment efficiency and secure competitive demolition prices [D] [P22] [P23]. Report P22, P23
Chosen: One year purchase programme for non council owned homes in non active phases. Existing resources can contain the scheme. Homes are bought at market value with vacant possession, a home loss payment and reasonable disturbance costs [P49] [P82] [P83] [P85] [P86]. Report P49, P82, P83, P85, P86
Chosen: Secure Affordable Homes Programme grant support. The grant could reduce the effect on council finances and support bringing affordable homes forward [P4] [P6] [P7]. Report P4, P6, P7
Chosen: Apply for Estate Regeneration Programme loan funding. The bid sought time limited funding to bring the regeneration programme forward [P9] [P12]. Report P9, P12
Chosen: Serve Phase 4 demolition notices in phases. Phasing follows the DPA programme and the statutory seven year period [P30] [P31] [P32]. Report P30, P31, P32
Chosen: Negotiate voluntary lease surrender or repurchase. Enhanced rehousing and financial support are offered to secure voluntary agreements [P42]. Report P42
Chosen: Offer shared equity without a rental component. The product supports qualifying leaseholders who are reluctant to accept voluntary repurchase [P43]. Report P43
Implications
Financial: If ERP funding is secured, NHHT would initially pay leaseholder acquisition and demolition costs, with council repayment starting in 2021/22 [P15] [P16]. Report P15, P16
Financial: Costs are expected within the current £69m allocation, but budgets and the timing of spending must be revised [P55] [P56] [P64]. Report P55, P56, P64
Financial: Moving demolition costs to NHHT is expected to reduce future land payments received by the council [P51]. Report P51
Legal: Demolition notices suspend Right to Buy claims for seven years, and Phase 4 notices depend on the intended demolition timetable [P26] [P30] [P32]. Report P26, P30, P32
Legal: The council must seek Secretary of State approval to extend the April 2010 demolition notice on certain Phase 2 blocks [P72]. Report P72
Risk: The programme presents significant financial risk, requiring regular and robust monitoring of the Housing Investment Capital Programme [P65]. Report P65
Equalities: An updated equalities analysis was prepared for planning, and NHHT consulted a wide range of individuals and groups [P37] [P38]. Report P37, P38
Other: Existing tenants and leaseholders must be rehoused, a process the report describes as difficult and often stressful [P39]. Report P39
Who and where
Aylesbury tenants and leaseholders Report P39
Phase 4 tenants and Right to Buy applicants Report P70, P71
Council tenants needing rehousing Report P41
Qualifying leaseholders needing alternative accommodation Report P42, P43
People needing temporary accommodation Report P69
People seeking housing at target rent Report P41
Local supply chains and labour Report P46
The council's Housing Revenue Account Report P73
Timeline
April 2014: The council and NHHT entered the Aylesbury DPA [D] [P1]. Report P1
September 2014: NHHT submitted the ERP funding application [P9]. Report P9
December 2014: The Autumn Statement confirmed Aylesbury shortlisting for an ERP loan award [P9]. Report P9
17 February 2015: An individual member decision brought 57-76 Northchurch into Phase 2 [D].
2015/16: The one year early purchase programme runs without rehousing assistance [D] [P49]. Report P49
April 2016: The first Phase 4 demolition notice could be served under the current programme [P32]. Report P32
December 2016: The April 2010 demolition notice on certain Phase 2 blocks expires [P72]. Report P72
2021/22: Council repayment to NHHT could begin if ERP funding is secured [P16]. Report P16
Plain English for the jargon
DPA: The council and NHHT agreement for delivering the Aylesbury regeneration [D] [P34].
NHHT: Notting Hill Housing Trust, the council's development partner [D] [P62].
ERP: The Government's Estate Regeneration Programme, established in the Budget 2014 [P9].
AAAP: The Aylesbury Area Action Plan, part of the planning policy framework [P35].
HCA: The Homes and Communities Agency, which is to complete ERP funding checks [P18].
Right to Buy: The statutory scheme whose applications and completions affected the regeneration programme and led to demolition notices being served [P26] [P28].
Shared equity: An ownership product with no rental component, available to qualifying leaseholders [P43].
Affordable Homes Programme: The funding programme from which NHHT secured social housing grant support [P6].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12
Resolved
That the update progress report of the work carried out under the Aylesbury Development Partnership Agreement (DPA), entered into in April 2014 by the council and its development partner Notting Hill Housing Trust (NHHT), as set out below be noted: · The position of the planning applications submitted by NHHT; these comprise a detailed planning application for the First Development Site and an outline application for the remainder of the estate masterplan (Phases 2, 3 and 4). · The progress update on the rehousing of tenants and leaseholders on the First Development Site and on Phase 2. · That 57-76 Northchurch has been brought forward into Phase 2 of the regeneration programme, by individual decision by member (IDM) dated 17 February 2015. · The one year programme to purchase non-council owned residential properties in non-active phases as set out in paragraphs 26 – 31 of this report. · The update on the design of the key community facilities to be delivered early as part of the council’s commitment to supporting the community. · The additional funding that has been secured from the Affordable Homes Programme for the regeneration of the Aylesbury by NHHT. · The application for funding for the Aylesbury made by NHHT to the Government’s Estate Regeneration Programme. · That NHHT will now undertake demolition of the existing buildings on the First Development Site, on Plot 18 and in Phase 2, as provision is made for within the DPA. · The principle of the director of housing and community services serving phased demolition notices on blocks within Phase 4 of the Aylesbury regeneration as the development comes forward and in accordance with the programme agreed through the DPA with NHHT.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Cabinet Member: Councillor Mark Williams, Regeneration, Planning and Transport
FOREWORD – COUNCILLOR MARK WILLIAMS, CABINET MEMBER FOR REGENERATION, PLANNING AND TRANSPORT
This report represents an important milestone in building a better future for the residents of the Aylesbury Estate. We are making great progress with the regeneration of the estate, this project will create new high quality affordable homes, new open space, much improved conditions for cyclists and pedestrians and better community facilities. Our development partner, Notting Hill Housing Trust, have submitted an outline planning application for the entire estate and a detailed application for the first development phase (Bradenham, Arklow, Chartridge and Chiltern Houses), this is expected to be considered by planning committee in April.
We are working with the remaining residents in the first phase and those in the second phase (Wendover, Winslow, Padbury, Foxcote and Ravenstone) to find them new homes as the project moves forward. We continue to work with the Creation Trust in providing additional assistance to more vulnerable residents to make sure they receive the support they need. We will continue to offer leaseholders shared equity homes so that those on low and fixed incomes can stay in the area.
This report sets out our plans to have a one year programme to buy-back leasehold properties in the third and fourth development phases, this will help those leaseholders in these later phases to better plan their futures. Despite our advanced plans for the redevelopment of the Aylesbury Estate some tenants are still able to exercise their right to buy, we will therefore move to place a demolition notice on all blocks in the later phases as soon as they fall within the prescribed timeframe to exclude them from Right to Buy. We believe this is essential and represents good value for money for the taxpayer, as public subsidy is used to allow tenants to buy their council home, we will then have to buy the same property back and cover all legal fees. In addition many former council properties are rented out privately, many of which are subsidised again through housing benefit.
We will also ensure that local residents on the Aylesbury and across the borough can take advantage of the construction jobs that will be available on this and other sites. We are working to create a Construction Skills Academy which will be located at the Elephant and Castle so that our residents, including those on the Aylesbury, can get the skills they need to take advantage of these opportunities. RECOMMENDATIONS
1. That the cabinet notes the update progress report of the work carried out under the Aylesbury Development Partnership Agreement (DPA), entered into in April 2014 by the council and its development partner Notting Hill Housing Trust (NHHT), as set out below:
• The position of the planning applications submitted by NHHT; these comprise a detailed planning application for the First Development Site and an outline application for the remainder of the estate masterplan (Phases 2, 3 and 4).
• The progress update on the rehousing of tenants and leaseholders on the First Development Site and on Phase 2.
• That 57-76 Northchurch has been brought forward into Phase 2 of the regeneration programme, by IDM dated 17 February 2015.
• The one year programme to purchase non-council owned residential properties in non-active phases as set out in paragraphs 26 – 31 of this report.
• The update on the design of the key community facilities to be delivered early as part of the council’s commitment to supporting the community.
• The additional funding that has been secured from the Affordable Homes Programme for the regeneration of the Aylesbury by NHHT.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.