Revised Canada Water Area Action Plan

Approved Executive 6 papers

AI summaryCabinet agreed an additional sports facilities list modification and recommended Council Assembly adopt the revised Canada Water Area Action Plan and policies map. [D] The report identified no immediate financial implications from the modifications. [P67]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedConsider the inspector’s report and adopt the plan and map. [D]
MoneyNo immediate financial implicationsPotential additional costs would be submitted as separate reports. [P67] [P68] [P114]
What happens nextCouncil Assembly consideration and adoptionAfter adoption, publication and notification duties would apply. [P71] [P103] [P106]
Who it affectsCanada Water regeneration

What was decided

The sports facilities list on page 38, paragraph 4.4.5, was updated through an additional modification.

Cabinet recommended that Council Assembly consider the Planning Inspector’s report and adopt the revised plan and policies map. The adoption would include the inspector’s main modifications and the council’s minor modifications. Report P2, P12

Cabinet also recommended noting the sustainability appraisal, sustainability appraisal statement, equalities analysis, consultation report and appropriate assessment. Report P2

Why

Harmsworth Quays became available when the printworks moved to Essex. The plan sets planning policies to guide redevelopment of the site and nearby sites. Report P7, P28

The plan seeks a town centre combining homes, shops and business space. It also covers walking and cycling links and improvements to the Lower Road road layout. Report P29

There had already been substantial consultation, so the council did not repeat an options consultation because the plan’s vision and objectives were established. The inspector found the plan sound subject to specified modifications. Report P6, P12, P14, P77

What happens next

Council Assembly must consider the inspector’s report and decide whether to adopt the plan, policies map and supporting documents. Report P71, P72

After adoption, the council must make the plan, a formal adoption statement, the sustainability appraisal and inspection details available. Report P103, P104, P105

The council must send the adoption statement to anyone who asked for notification and to the Secretary of State. Report P106

Options considered

  • Chosen: Include all of CWAAP24 within the town centre boundary. The inspector considered the boundary should be clearer and cover the whole site. Report P35
  • Chosen: Raise the homes target from 2,500 to a minimum of 4,500, including a minimum of 1,000 affordable homes. The revised target needed to reflect planning permissions and updated capacity analysis. Report P37, P38
  • Rejected: Retain the tall building terms recessive, elegant and slender. The inspector found the terms too prescriptive and unnecessary because exemplary design was already required. Report P42
  • Chosen: Designate the space between Blick House and the City Business Centre as other open space. The inspector considered that the space met the criteria for this designation. Report P44
  • Rejected: Require large student housing developments to form part of a wider campus development. The wider campus requirement was overly onerous and unnecessary because CWAAP24 required a mix of uses. It was replaced with a requirement for good links to university campuses. Report P46
  • Chosen: Set CWAAP7 retail capacity at around 34,000sqm. This made the policy consistent with AAP policy 1. Report P50
  • Chosen: Delete AAP policy 32a on sustainability. The report said it repeated national policies and was unnecessary. Report P54
  • Chosen: Require a masterplan with the first phase of Harmsworth Quays development. The inspector considered it beneficial to state this requirement explicitly. Report P58

Implications

  • Financial: There are no immediate financial implications from the modifications and the request to the inspector. Any costs from specific proposals would come through separate reports. Report P67, P68, P114
  • Legal: Cabinet cannot approve the plan alone because approval is shared with Council Assembly. If adopted, the plan would become part of Southwark’s development plan. Report P71, P108
  • Other: The modified target is a minimum of 4,500 new homes, including a minimum of 1,000 affordable homes. It assumes schemes with planning consent are delivered as proposed and future schemes provide 35% affordable housing. Report P37, P38
  • Other: Residential and student housing at CWAAP24 should not prevent delivery of the minimum 12,000sqm of employment floorspace or the London Plan aspiration for a science cluster. Report P52
  • Equalities: The higher housing target and added open space are assessed as beneficial for people on low incomes, disabled people and all groups. No negative equalities impacts were identified. Report P64, P65
  • Climate: More homes increase the need to reduce energy and water consumption and waste. Screening found no negative impacts on protected habitats. Report P65, P66
  • Other: Road infrastructure needs to improve as retail space expands. The council says clearer policy gives greater certainty of transport improvements and can help reduce car travel. Report P40, P64
  • Legal: After publication of the adoption statement, an aggrieved party may apply to the High Court within 6 weeks, but only on specified grounds. Officers believe both the risk of a challenge and its likelihood of success are low. Report P109, P110, P111, P112

Who and where

  • People needing housing, including low income groups and disabled people Report P64
  • Future residents and users of new homes, shops and workplaces Report P29, P31
  • People needing student housing Report P46
  • People needing new education and health facilities Report P56
  • People affected by expanded retail development and transport impacts Report P40, P64
  • People affected by town centre layout, building heights and public space changes Report P29, P30
  • Developers and site owners at Harmsworth Quays and nearby sites Report P7, P28, P31
  • Planning applicants in the Canada Water area Report P5

Timeline

  • March 2012: The council adopted the Canada Water Area Action Plan. Report P4
  • 7 May until 30 July 2013: The council consulted on the draft revised plan over 12 weeks. Report P15
  • 14 January 2014: The revised plan was formally published, with representations invited through 25 February 2014. Report P16
  • 6 May 2014: The revised plan was submitted for examination. Report P10
  • 30 September 2014, 1 October 2014 and 7 October 2014: Public hearings took place. Report P10
  • 17 October 2014: The inspector sent a post hearing letter setting out proposed modifications. Report P11
  • 16 March 2015 to 14 May 2015: The council consulted on the proposed modifications. Report P17, P73
  • 19 June 2015: The inspector issued his final report and concluded that the plan could be adopted after specified modifications. Report P12

Plain English for the jargon

  • Area Action Plan: A spatial plan giving a vision, objectives and policies for managing development and growth at Canada Water. [P4] [P5]
  • Revised Canada Water Area Action Plan: The updated plan providing a planning policy framework for redevelopment at Harmsworth Quays and nearby sites. [P28]
  • Examination in public: The independent hearing where the public, developers and other stakeholders could put forward their views. [P6]
  • CWAAP24: The combined Harmsworth Quays, Site E, Mulberry Business Park and Surrey Quays Leisure Park site. [P35]
  • Main and minor modifications: Inspector changes needed for soundness, plus council factual, editorial and limited policy updates that did not alter the plan’s substance. [P11] [P12] [P60] [P61]
  • Masterplan: A plan expected to accompany the first phase of development at Harmsworth Quays. [P58]
  • Public Sector Equality Duty: The duty for public authorities to eliminate discrimination, advance equality of opportunity and foster good relations. [P84]
  • London Plan: The Mayor of London’s spatial development strategy. Local planning documents must be in general conformity with it. [P5] [P61] [P75]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

That an additional modification be made to page 38 (paragraph 4.4.5) of the Revised Canada Water Area Action Plan (appendix B of the report) to update the list of sports facilities in the area. 2. That council assembly be recommended: · To consider the Planning Inspector’s report on the Revised Canada Water Area Action Plan (Appendix A). · To adopt the revised Canada Water area action plan (Appendix B) and the revisions to the adopted policies map (Appendix C), as amended by the Inspector’s main modifications (Appendix D) and the council’s minor modifications (Appendix E). · To note the sustainability appraisal (Appendix F), sustainability appraisal statement (Appendix G), equalities analysis (Appendix H), consultation report (Appendix I) and appropriate assessment (Appendix J).
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 13 pages

Recommendations

1. That cabinet recommends that council assembly:

 considers the Planning Inspector’s report on the Revised Canada Water Area Action Plan (Appendix A).  adopts the revised Canada Water area action plan (Appendix B) and the revisions to the adopted policies map (Appendix C), as amended by the Inspector’s main modifications (Appendix D) and the council’s minor modifications (Appendix E).  notes the sustainability appraisal (Appendix F), sustainability appraisal statement (Appendix G), equalities analysis (Appendix H), consultation report (Appendix I) and appropriate assessment (Appendix J).

BACKGROUND INFORMATION

2. In March 2012, the council adopted the Canada Water Area Action Plan (“AAP”). The purpose of the AAP is to help shape the regeneration of Canada Water. Like the Core Strategy (2011) it is a spatial plan which provides a vision, objectives and

1 policies designed to help manage development and growth at Canada Water. It is a development plan and alongside the Core Strategy and saved Southwark Plan policies, it is used as the basis for determining planning applications in the area. As part of the development plan, the AAP must be consistent with the Core Strategy and in general conformity with the London Plan (2015).

3. Work on the AAP commenced in 2007 and its adoption followed four rounds of public consultation, as well as an examination-in-public (EIP) in which members of the public, developers and other stakeholders were able to set out their views to an independent planning inspector. The inspector found the AAP to be “sound”, subject to a number of amendments.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Inspector's reportAppendix A 15 pages Download
PDF
PublicationSubmission Revised AAP (final version) incorporating modsAppendix B 132 pages Download
PDF
Proposed changes to the adopted policies mapAppendix C 24 pages Download
PDF
Inspector's main modificationsAppendix D 12 pages Download
PDF
Minor modificationsAppendix E 17 pages Download
PDF
Report: Revised Canada Water area action planReport 13 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 12 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
SC
Councillor Stephanie CryanCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
DM
Councillor Darren MerrillCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
MS
Councillor Michael SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, present
DF
Doreen Forrester-BrownOfficer, present

On this subject at Southwark

Search all
  1. Revised Canada Water Area Action PlanThis decision
  2. Response to the Report of the Housing Scrutiny Commission:The Council's work with social landlord partners; the Fair Street/Devon Mansions, Canada and Kirby Estates QHIP major works projects; the revised resident engagement strategy; and temporary accommodation in properties awaiting demolitionNoted
  3. Report of the Housing Scrutiny Commission: The Council's work with social landlord partners; the Fair Street/Devon Mansions, Canada and Kirby Estates QHIP major works projects; the revised resident engagement strategy; and temporary accommodation in properties awaiting demolitionNoted
  4. Draft Revised Canada Water Area Action Plan (AAP)Approved

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies