New Homes Delivery Programme

Agreed Executive 4 papers

AI summarySouthwark Cabinet agreed in principle to work up the proposed new homes schemes and noted consultation and rehousing options. [D] [P3] [P4] [P5] The Leader delegated future approvals to the cabinet member for regeneration and new homes, with funding to be confirmed scheme by scheme. [D] [P7] [P74]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedConsultation and rehousing options were noted [P4] [P5]
MoneySeveral funding streams [P61]Sources confirmed before progress [P74]
What happens nextScheme workup and consultation [P3] [P42]Capacity studies follow architect appointments [P43]
Who it affectsResidents affected by development [P31]Decant households have rehousing support [P31] [P34]

What was decided

Cabinet agreed in principle to work up the proposed schemes under their individual recommendations and the Charter of Principles. Report P3

Cabinet noted the consultation so far and the rehousing options available to residents affected by potential development. Report P4, P5

The Leader delegated approval of future programme schemes to the cabinet member for regeneration and new homes, in consultation with the cabinet member for housing. Report P7, P47, P68

Why

Southwark has continuing need for affordable homes, with the average 2 bedroom flat being sold for £360k in 2013 and 18,547 overcrowded households recorded at the 2011 census. Report P57

The proposed sites are estimated to provide 218 homes, including 184 council rented homes, towards the 1,500 target by 2018 and the 11,000 commitment by 2043. Report P10, P26

The revised process is intended to accelerate delivery and streamline approval while retaining consultation and necessary approvals. Report P47

What happens next

A consultation strategy will be developed for each project with the T&RA, the wider community and ward councillors. Report P42

Architects and employers agents will develop capacity studies, schemes will undergo feasibility appraisal, and funding sources must be confirmed before progression. Report P43, P74

Each future site will follow local briefing and consultation, then cabinet member approval in consultation with the housing member, with Cabinet receiving updates every six months. Report P47

The money

  • £360k Average 2 bedroom flat being sold in 2013 Report P57
  • 1% yearly reduction in rents Reduction that every scheme must address in viability assessment Report P62

Options considered

  • Chosen: Work up the proposed schemes in principle. Each scheme will follow its individual recommendations and the Charter of Principles. Report P3
  • Rejected: Continue Cabinet approval for each future scheme. The revised programme approach replaces the current process to accelerate scheme delivery. Report P47
  • Chosen: Use a programme approach with delegated approval. It streamlines approval while retaining required approvals and consultation. Report P7, P47
  • Chosen: Provide advice and support to affected leaseholders and homeowners. The Charter includes rehousing options, shared ownership, shared equity and any available loss, compensation or disturbance payments. Report P35
  • Chosen: Offer options for tenants and leaseholders wanting to stay locally. The programme aims to benefit local people affected by development. Report P36
  • Chosen: Reserve at least half of remaining new council homes for affected estate tenants in housing need at first letting. This is intended to ensure affected residents receive a fair deal. Report P39
  • Chosen: Allow new council home tenants to transfer or exchange their homes. They will have the same rights as other Southwark tenants. Report P38

Implications

  • Financial: The sites are estimated to add 218 homes, with 184 let as social rent, and rental income is expected to contribute to the HRA business plan. Report P26, P60
  • Financial: Funding comes from grants, contributions, housing receipts, HRA revenue and prudential borrowing, and each source must be confirmed before schemes progress. Report P61, P74
  • Financial: All schemes must pass viability assessment and address the 1% yearly reduction in rents and any right to buy impact, which may require more outright sales. Report P62
  • Legal: Consultation must provide sufficient information and time, responses must be considered before decisions, and later proposals must follow the council's constitutional process. Report P66, P69
  • Equalities: The council must have due regard to the Public Sector Equality Duty, and consultation is designed to include all borough communities. Report P58, P67
  • Equalities: Affected residents can receive advice and rehousing support, while at least half of remaining new council homes are for estate tenants in housing need at first letting. Report P31, P35, P39
  • Risk: Significant local opposition remains a delivery risk, and most schemes are before planning, so delivery is not certain. Report P28, P29
  • Staffing: The council is procuring architects and employers agents for capacity studies, with related staffing and other costs contained in existing departmental revenue budgets. Report P43, P75

Who and where

  • Residents at Rutley Close and nearby blocks Report P16, P28
  • Salisbury Estate car park users and estate residents Report P18
  • Edmonton Court residents, including one leaseholder Report P19
  • Mayflower T&RA and users of its hall Report P20
  • Silverlock Estate residents using the ball court and garages Report P21, P22
  • Sceaux Gardens Estate residents, including leaseholders Report P23
  • Rye Hill Estate residents who rely on garages Report P24
  • Seavington House residents and nearby Champion Hill residents Report P25

Timeline

  • July 2015: Officers discussed Edmonton Court and Mayflower Hall with resident representatives and councillors. Report P19, P20
  • 15th July: Officers attended the Sceaux Gardens T&RA meeting. Report P23
  • 4 August: An update on the Salisbury Estate car park was given to the T&RA. Report P18
  • 11th August: The Rye Hill Estate T&RA meeting discussed the garage scheme. Report P24
  • following their AGM on 28 September: The first opportunity to meet the newly elected Mayflower T&RA was identified. Report P20
  • 2016/17-2017/18: The report projected the sequence of construction stages across the sites. Report P27
  • 2026-05-28: Cabinet meeting listed for the decision.
  • 1st July: Presentations were given to the Rutley Close and Silverlock Estate T&RA meetings. Report P16, P21

Plain English for the jargon

  • New Homes Delivery Programme: Council programme for delivering new homes, including rented council homes [P29] [P60]
  • Charter of Principles: Rules for scheme work, consultation and resident rehousing [P3] [P34]
  • Decanting: Moving residents to other homes so redevelopment can proceed [P31]
  • Local lettings: Share of new homes made available to local tenants in housing need [P33] [P39]
  • T&RA: Residents' association involved in consultation [P42]
  • HRA: Council housing business plan and revenue funding arrangements [P60] [P61]
  • Public Sector Equality Duty: Duty to eliminate discrimination, advance equality and foster good relations [P58]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

Decisions of the Cabinet 1. That in principle agreement be given for the schemes listed in paragraph 9 of the report to be worked up in accordance with the individually identified recommendations and in line with the Charter of Principles for inclusion in the New Homes Delivery Programme. 2. That the consultation undertaken on schemes in paragraph 9 of the report to date be noted. 3. That the rehousing options in paragraphs 14-16 of the report available to residents impacted by any potential development, as outlined in the Charter of Principles be noted. Decision of the Leader of the Council 4. That the approval of future schemes for inclusion in the New Homes Programme be delegated to the cabinet member for regeneration and new homes, as outlined in paragraph 22 of the report.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 11 pages

Recommendations

Recommendations for the Cabinet

That the cabinet

1. Agrees in principle that the schemes listed in paragraph 9 are worked up in accordance with the individually identified recommendations and in line with the Charter of Principles for inclusion in the New Homes Delivery Programme.

2. Notes the consultation undertaken on schemes in paragraph 9 to date.

3. Notes the rehousing options in paragraphs 14-16 available to residents impacted by any potential development, as outlined in the Charter of Principles.

Recommendations for the Leader of the Council 1 That the Leader

4. Agrees to delegate the approval of future schemes for inclusion in the New Homes Programme to the cabinet member for regeneration and new homes, as outlined in paragraph 22.

BACKGROUND INFORMATION

5. Improving housing in Southwark is at the centre of the council’s plans to create a Fairer Future for all, regardless of whether residents are social housing tenants, council leaseholders, private renters or homeowners. Access to appropriate, good quality, affordable homes is important not just for residents but also to the wider economy and essential to shaping a borough that all residents are proud to call home and which is truly sustainable into the future.

6. In order to deliver the council’s historic commitment to build 11,000 additional council homes by 2043, cabinet has set an interim target of the delivery of 1,500 new council homes by 2018.

7. In July 2015, cabinet received an update on progress towards achieving the 1,500 target and noted that a report would go to cabinet in September for approval of new sites. In addition, that consultation in partnership with the community engagement team had begun on those sites in line with the Charter of Principles agreed by Cabinet.

KEY ISSUES FOR CONSIDERATION

Proposed Sites

8. A number of sites have been identified as potential schemes for inclusion in the programme. At this stage only site visits and initial desktop assessments of their suitability have been made. The proposed new sites are outlined in the table in appendix 1.

9. Outlined below is a summary of the sites and the initial consultation undertaken:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed new sites for New Homes ProgrammeAppendix 1 1 pages Download
PDF
Map of schemesAppendix 2 1 pages Download
PDF
Full list of schemesAppendix 3 3 pages Download
PDF
Report: New Homes Delivery ProgrammeReport 11 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 12 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
SC
Councillor Stephanie CryanCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
DM
Councillor Darren MerrillCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
MS
Councillor Michael SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, present
DF
Doreen Forrester-BrownOfficer, present

On this subject at Southwark

Search all
  1. New Homes Delivery ProgrammeThis decision
  2. Developing Long Term Plans for the Delivery of New Council HomesNoted
  3. Next Steps on Developing Long Term Plans for the Delivery of New Council HomesNoted
  4. Update on Consultation and Plans for the Delivery of 11,000 New HomesAgreed
  5. Update on the Proposed Pipeline for the Delivery of 1,500 New Council Homes by 2018Noted
  6. Key Principles and Protocol for Developing New Council Homes in Partnership with ResidentsAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies