Major Works Status Report incorporating Warm, Dry and Safe

Noted Executive 2 papers

AI summarySouthwark Cabinet noted the Warm, Dry and Safe housing programme, with £109.2m spent by March 2015 and a revised funding plan for Cabinet [D] [P21].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedWDS delivery and 90% decency target noted [D]
Money£109.2m WDS spend [P21]Actual spend to March 2015 [P21]
What happens nextRevised resources to Cabinet [D]Detailed affordable plan for council housing [D]
Who it affectsCouncil housing residents [D]Over 15,000 properties were receiving or had received works [D]

What was decided

Cabinet noted the status of housing investment programmes at March 2015, with particular reference to the Warm, Dry and Safe standard [D].

Cabinet noted current programme resources and that WDS investment was on course to be fully committed by the end of 2015/16. The first year of the kitchen and bathroom guarantee would run alongside the final year of WDS investment [D].

Cabinet noted the end 2015/16 target of 90% decency, against 56% in April 2010. It also noted environmental work at nearly 7,000 homes with British Gas and work at over 15,000 properties [D].

Why

The council brought forward heating funding to replace inefficient boilers with more efficient models, bringing earlier savings and tackling fuel poverty [P10]. Report P10

Fire Risk Assessment work covered substantial blocks needing urgent action and moderate blocks needing significant work to reach a tolerable level [P44] [P45]. Report P44, P45

Lift work addressed obsolete parts that were causing increasing service failures, with improved performance and reliability expected [P30]. Report P30

What happens next

Cabinet will receive revised programme resources within a detailed affordable funding plan. This will support new council homes and existing stock and include the quality kitchens and bathroom guarantee [D].

The first year of delivering the kitchen and bathroom guarantee will run alongside the final year of WDS investment [D].

Following Cabinet approval, the report will be sent to Home Owners Council and Tenant Council [D].

The money

  • £109.2m Actual spend on WDS estates and street properties to March 2015 Report P21
  • £26.6m Original Four Squares allocation, including HINE funding Report P3
  • £9m Planned contribution from disposing of void Four Squares properties Report P3
  • £18.9m Individual heating programme schedule Report P11
  • £13.2m District heating programme Report P14
  • £12.1m Minor voids capitalisation spend to March 2015 Report P36
  • £10.2m Lift programme spend to March 2015 Report P32
  • £5.5m Remaining FRA electrical works budget, later transferred to FRA budget Report P27, P61

Options considered

  • Chosen: Enhanced refurbishment at Four Squares. An options appraisal and later structural survey identified the required work and additional structural repairs [P3]. Report P3
  • Chosen: Disposal of void properties at Four Squares. It was to contribute £9m to the estate's value [P3]. Report P3
  • Chosen: Backup contractors or tendering for WDS work. Alternative arrangements were used after partnering contracts ended [P20]. Report P20
  • Chosen: Coordinated WDS and sheltered housing packages. To minimise resident disruption where the work overlapped [P81]. Report P81

Implications

  • Financial: Revised resources will be brought through a detailed affordable funding plan covering new council homes, existing stock and the kitchens and bathroom guarantee [D].
  • Risk: Four Squares surveys found falling brick slips, unstable gable ends and other structural problems, prompting extra works [P3]. Report P3
  • Risk: All substantial fire risk blocks and higher risk medium blocks were complete [P46]. Report P46
  • Equalities: Boiler replacements with more efficient models were intended to deliver earlier savings and tackle fuel poverty [P10]. Report P10
  • Climate: The British Gas partnership delivered environmental improvements to roofs, windows and insulation at nearly 7,000 homes [D].
  • Climate: Building Management Systems were used to keep heating at maximum levels of efficiency and economy [P17]. Report P17
  • Risk: Lift refurbishment aimed to improve performance and reliability as obsolete parts caused service failures [P30]. Report P30
  • Other: The target for the end of 2015/16 was 90% decency, which Southwark said would be its highest figure [D].

Who and where

  • Residents whose properties had received or were receiving works
  • Residents in nearly 7,000 homes in the British Gas partnership
  • People in new council homes and the existing housing stock
  • People living in the borough's sheltered housing units Report P81
  • Residents needing boiler replacements or district heating works Report P10, P12
  • Residents in blocks subject to Fire Risk Assessment work Report P44
  • People using lifts covered by the programme Report P30
  • People in Four Squares properties Report P3

Timeline

  • April 2010: The pre-WDS decency figure was 56% [D].
  • March 2015: Over 15,000 properties had received or were receiving works, while nearly 7,000 homes had received British Gas environmental work [D].
  • end of 2015/16: WDS investment was due to be fully committed and the decency target was 90% [D].
  • 2015/16: The first year of the kitchen and bathroom guarantee was to run alongside the final WDS year [D].
  • 2015/16: Most WDS schemes were due to commence [P66]. Report P66
  • 2015/16: Fire Risk Assessment works at Sidmouth House were due to start [P48]. Report P48
  • 2015/16: Maydew Refurbishment was expected to start late in the year [P74]. Report P74
  • 2016/17: Acorn underground mains were due to commence after the regeneration heating redesign [P59]. Report P59

Plain English for the jargon

  • Warm, Dry and Safe (WDS): The council housing improvement programme and standard [D].
  • HINE: High Investment Needs Estate funding for estates needing additional investment [P2] [P3].
  • FRA: Fire Risk Assessment covering historic blocks [P44].
  • BEMS: Building Management Systems that monitor and control services such as heating [P17].
  • ECON: The term contract used to capitalise heating works [P9].
  • FRA electrical works: Essential communal and lateral wiring and equipment replacement arising from FRA electrical tests [P26].
  • Decency: The reported housing condition percentage, targeted at 90% by the end of 2015/16 [D].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

That the status of the housing investment programmes at March 2015 with particular reference to achieving the Warm, Dry and Safe (WDS) standard be noted. 2. That it be noted that the current WDS investment is on course to be fully committed by the end of 2015/16 and that first year of delivering the kitchen and bathroom guarantee will be delivered alongside the final year of the WDS investment. 3. That the target at the end of 2015/16 is achieving 90% decency which will be the highest decency figure Southwark has achieved be noted. The pre-WDS figure was 56% in April 2010. 4. That the work that has been delivered to nearly 7,000 homes in partnership with British Gas to deliver environmental improvements including roofs, windows and insulation work at a notional cost to Southwark be noted. 5. That it be noted that over 15,000 properties had received works or were in the process of receiving works to their homes or blocks at March 2015. 6. That the current programmes resources be noted and that revised resources will be presented to cabinet as part of a detailed affordable funding plan to support housing investment in new council homes and the existing stock. This will also encapsulate the quality kitchens and bathroom guarantee. 7. That it be noted that this report will be sent to Home Owners Council and Tenant Council following cabinet approval.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 37 pages

Pictures of the programmes APPENDIX 1 APPENDIX 2 A review of the WDS programme up to March 2015.

Four Squares (New Place Estate) Status: On site Type of works: WDS plus additional funding as a High Investment Needs Estate (HINE)

Comment: Four Squares is a High Investment Needs Estate. A total of £26.6m was originally set aside to be invested including HINE funding. An options appraisal exercise to determine the scale of works required to the estate and the different approaches that could be taken was carried out. It was decided that an enhanced refurbishment scheme would be undertaken and that void properties on the estate would be disposed of to contribute to the value of £9m. Following the decision, a condition survey was undertaken, and a number of structural problems came to light, including brick slips falling from the towers and the instability of several gable ends. As a result, the Council commissioned a comprehensive structural survey of the Estate which recommended a number of structural works particularly to the south west stair towers of Layard and Marden. The funding estimate for this estate did not include these additional structural works. Additional High Investment Needs (HINE) money has been agreed to carry out the additional work indentified from the structural surveys including structural work to the stair towers and brickwork at roof level, additional concrete repairs, asphalt on balconies and extensive works to waterproof garages (major removal and reinstatement of soft landscaping and boundary walls not originally specified).

Actual spend Area to March 2015 Progress Status / Comments Four Squares Security and On site Four squares started in 2012/13 as WDS (New Place Estate) scheduled. The externals started in early (completion delayed 2014/15 following agreement of additional due to increased scope of works) funding to complete the work identified £12.9m (£13.1m through structural surveys and will be HINE) substantially completed in 2015/16. Elmington Estate (Drayton / Langland only)

Status: On site Type of works: WDS and additional works to Drayton / Langland only

Comment: This scheme has completed as outlined in the original agreed programme. The schemes budget had been revised and agreed through delegated approval to £2.1m with the additional funding coming from the contingency allowed in the programme but costs are under that budget.

Actual spend Area to March 2015 Progress Status / Comments Elmington Completed Elmington completed as scheduled starting in £1.8m 2012/13 and completing in 13/14.

Landlord Obligations (Individual Heating)

Status: Ongoing programme of boiler replacements Type of works: To support the capitalisation of heating works undertaken via the term contractors as part of the ECON contract.

Comment: Additional money was brought forward from our 2015/16 individual heating programme into 2012/13 meaning inefficient boilers were replaced with more efficient models helping to deliver earlier savings for residents and tackle fuel poverty. Over 8,000 boilers have been replaced from WDS funding. Tadworth House heating has also been completed.

Actual spend Area to March 2015 Progress Status / Comments Landlord Obligations On going This programme is ahead of the original (Individual Heating) £18.9m schedule. Landlord Obligations (District Heating)

Status: Ongoing programme of district heating works Type of works: District Heating Works

Comment: Overall the district Heating Programme is running well with the remaining schemes due to start in 2015/16..

Actual spend Area to March 2015 Progress Status / Comments Landlord Obligations On going All schemes except one planned to start by (District Heating) 2013/14 are on site or completed. The remaining schemes are due to start in 2015/16 with the exception of Acorn underground heating mains which was delayed due to the heating redesign as part £13.2m of a regeneration scheme.

Individual Scheme progress (district heating 2011/12-2014/15)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendices 1: 4: Major works status report incorporating Warm, Dry and SafeReport 37 pages DownloadRead as text
PDF
Report: Major works status report incorporating Warm, Dry and SafeReport 13 pages Download

At this meeting

Whole meeting

Who was there

12 of 12 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
SC
Councillor Stephanie CryanCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
DM
Councillor Darren MerrillCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
MS
Councillor Michael SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, present
DF
Doreen Forrester-BrownOfficer, present

On this subject at Southwark

Search all
  1. Major Works Status Report incorporating Warm, Dry and SafeThis decision
  2. Response to the Report of the Housing Scrutiny Commission:The Council's work with social landlord partners; the Fair Street/Devon Mansions, Canada and Kirby Estates QHIP major works projects; the revised resident engagement strategy; and temporary accommodation in properties awaiting demolitionNoted
  3. Report of the Housing Scrutiny Commission: The Council's work with social landlord partners; the Fair Street/Devon Mansions, Canada and Kirby Estates QHIP major works projects; the revised resident engagement strategy; and temporary accommodation in properties awaiting demolitionNoted
  4. Four Squares Estate - Major Works UpdateNoted
  5. Major Works Status Report incorporating Warm, Dry and SafeNoted
  6. Report into Major Works at Draper House (Housing, Environment, Transport and Community Safety Scrutiny Sub-Committee)Noted

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies