Gateway 2: Contract Award Approval Heating and Water Contracts
ApprovedExecutive1 paper
AI summarySouthwark Cabinet awarded the north heating and water contract to OCO Ltd and the south contract to Smith and Byford Ltd. [D] The contracts cost an estimated £7.2m and £6.6m per annum and run for 5 years from 1 April 2016. [D]
Written from the decision and the officer reportPDF Pro
OutcomeApprovedNorth: OCO Ltd. South: Smith and Byford Ltd. [D]
Money£7.2m, £6.6m annually [D]Total estimates: £72m and £66m. [P2][P3]
What happens nextContract start 1 April 2016 [P14]Mobilisation and monitoring are planned. [P57][P68]
Who it affectsResidents and leaseholders [P7][P79]Heating, water, safety and maintenance services are covered. [P7][P17]
What was decided
Contract A for the north of the borough was awarded to OCO Ltd for an estimated £7.2m per annum for 5 years from 1 April 2016, with an option to extend up to 5 years and a total estimated contract value of £72m. Report P2
Contract B for the south of the borough was awarded to Smith and Byford Ltd for an estimated £6.6m per annum for 5 years from 1 April 2016, with an option to extend up to 5 years and a total estimated contract value of £66m. Report P3
OCO Ltd and Smith and Byford Ltd may act as each other's backup using their own tendered rates when required. Report P4
Why
Tenders were assessed under a 40:60 price and quality model, and the two highest scoring tenders were each allocated a contract. Report P41, P42, P43, P53
Two geographical contracts were considered better for logistical service coverage, and a single contractor for all the services was not considered appropriate. Report P8
The contracts maintain housing assets, deliver repairs and maintenance, and support the council's landlord safety duties. They also cover energy management systems and dry and wet risers. Report P17, P18, P22
What happens next
After award, weekly mobilisation meetings and site visits were planned, and the council's TUPE process was to be started and monitored. Report P56, P57
A standstill of a minimum of 10 calendar days must run between notifying successful contractors and awarding the contracts, and the award notice must then be posted in OJEU within 30 days. Report P126, P127
Daily joint inspections, independent quality auditing, monthly progress meetings and a bi-monthly core group were planned for monitoring. Report P59, P68
The money
£7.2m per annum Estimated annual sum for Contract A Report P2
£72m Total estimated contract value for Contract A Report P2
£6.6m per annum Estimated annual sum for Contract B Report P3
£66m Total estimated contract value for Contract B Report P3
£69m Total estimated five year value stated in the financial implications Report P104
£13.8m Annual contract value covering revenue repairs, maintenance and capital works Report P104
£1m each Anticipated efficiency savings for revenue and capital budgets from April 2016 Report P104
£15.8m Anticipated 2016/17 total budget Report P105
Options considered
Chosen: Award Contract A to OCO Ltd. OCO Ltd ranked first and was recommended for Contract A after the MEAT evaluation. Report P52, P53
Chosen: Award Contract B to Smith and Byford Ltd. Smith and Byford Ltd ranked second and was recommended for Contract B after the MEAT evaluation. Report P52, P53
Chosen: Use two geographically split contracts. The split was considered better for logistical service coverage. Report P8
Rejected: Appoint a single contractor for all services. The appointment of a single contractor was not considered appropriate. Report P8
Chosen: Let both contractors act as each other's backup. The arrangement provides mutual backup and supports contract risk mitigation. Report P8, P19, P72
Implications
Financial: Each contract includes a General Maintenance Index adjustment due each April after the first year. Starting in April 2016, the contracts also depend on budget decisions, with £1m each assumed in revenue and capital savings. Report P9, P104
Financial: The financial implications state £69m over five years, while the award recommendations state £72m for Contract A and £66m for Contract B. Report P2, P3, P104
Financial: Specified work is above the statutory consultation limit, so annual service charges will be passed to leaseholders. Report P79, P80, P134
Legal: The awards are subject to Public Contract Regulations 2015 and an EU procurement process. The OJEU award notice must be posted within 30 days, a minimum standstill of 10 calendar days applies, and each contract can be terminated without consideration of loss or expense. Report P20, P125, P126, P127
Risk: Mutual backup, a performance bond and a payment retention are controls for contractor failure. A 12 month defects period applies, but no parent company guarantees will be obtained. Report P72, P73
Staffing: There is no impact on council staff. Existing officers will continue ordering and monitoring the work under the new contracts. Report P101
Equalities: The council requires London Living Wage where appropriate, and both contractors exceed that requirement. Both operate equal opportunity policies and offer apprenticeships and work experience. Report P83, P88, P91, P92
Climate: New boilers and plant will meet and exceed minimum energy efficiency requirements. Maintaining building energy management systems at optimum performance is intended to reduce CO2 emissions and fuel use. Report P94, P95
Who and where
OCO Ltd
Smith and Byford Ltd
Residents in council housing Report P17, P23
Leaseholders Report P79, P134
Council engineering and compliance staff Report P102
CFM non housing stock Report P19
Local schools and residents offered work experience Report P83, P88
Unsuccessful tenderers Report P127
Timeline
3 October 2014: The OJEU advertisement was placed and 23 expressions of interest were received. Report P26
14 April 2015: Revised tender closing date after a three week extension. Report P37
11 June 2015: Completion of the tender evaluation. Report P14
15 September 2015: Planned approval of the Gateway 2 contract award report. Report P14
7 October 2015: Planned contract award. Report P14
1 April 2016: Scheduled contract start. Report P14
31 March 2021: Scheduled contract completion date. Report P14
31 March 2026: Contract completion date if the extension options are exercised. Report P14
Plain English for the jargon
M.E.A.T.: Most economically advantageous tender, scored with 40% price and 60% quality. [P43]
General Maintenance Index (GMI): Annual index adjustment due each April after the first year. [P9]
TUPE: Process to be commenced and monitored by the council's gas contract manager after award. [P57]
OJEU: Journal used for publication of the contract award notice. [P14][P126]
Key Performance Indicators (KPIs): Measures used to monitor contract quality, compliance and performance. [P59][P60]
Building energy management systems (BEMS): Systems maintained so plant and equipment work at optimum performance. [P18][P95]
Waste Electrical and Electronic Equipment Regulations (WEEE): Rules for disposing of replaced components and equipment. [P96]
London Living Wage (LLW): Minimum pay commitment for contractor staff where appropriate. [P91]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item18
Resolved
That the award of Contract A (north of the borough) Heating and Water Contract to OCO Ltd for the estimated sum of £7.2m per annum for a period of 5 years from 1 April 2016 with the option to extend up to 5 years (3+2 years) making a total estimated contract value of £72m be approved. 2. That the award of Contract B (south of the borough) Heating and Water Contract to Smith and Byford Ltd for the estimated sum of £6.6m per annum for a period of 5 years from 1 April 2016 with the option to extend up to 5 years (3+2 years), making a total estimated contract value of £66m be approved. 3. That OCO Ltd and Smith and Byford Ltd to act as back up contractor to each other on their own tendered rates when required be approved.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 14 pages
Recommendations
That cabinet:
1. Approves the award of Contract A (north of the borough) Heating and Water Contract to OCO Ltd for the estimated sum of £7.2m per annum for a period of 5 years from 1 April 2016 with the option to extend up to 5 years (3+2 years) making a total estimated contract value of £72m.
2. Approves the award of Contract B (south of the borough) Heating and Water Contract to Smith and Byford Ltd for the estimated sum of £6.6m per annum for a period of 5 years from 1 April 2016 with the option to extend up to 5 years (3+2 years), making a total estimated contract value of £66m.
3. Approves OCO Ltd and Smith and Byford Ltd to act as back up contractor to each other on their own tendered rates when required. BACKGROUND INFORMATION
4. The current ten contracts for the whole of the borough were due to expire on 30 September 2013. A Gateway 3 report was approved on 11 September 2013 utilising the extension facility of twenty four months to extend the contracts to 30 September 2015. A combined Gateway 1&2 report was approved in June 2014 to extend the existing ten contracts for six months to enable these two new heating and water contracts to be mobilised over the winter and commence on 1 April 2016 at the end of the heating season. The current ten contracts are due to expire on 31 March 2016.
5. The planned procurement strategy was the subject of a Gateway 1 report approved by cabinet on 22 July 2014. The approved EU restrictive procedure procurement strategy was followed.
6. The scope of these new contracts (Contracts A and B) will encompass the following work streams: • Gas landlord’s safety inspections; • Responsive repairs, installations and maintenance for gas and heating installations to individual and district heated properties; • Potable water testing, treatment and installations; • Responsive repairs and maintenance for laundry and sewage plant; • Testing and maintenance of dry/ wet riser installations; • Maintenance of building energy management systems; and • Emergency response that covers a 24/7, 52 weeks a year period.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.