Aylesbury Regeneration: Amersham Site (Plot 18) Redevelopment

Noted Executive 2 papers

AI summarySouthwark Cabinet agreed to seek planning consent for a new library, community facilities and approximately 120 homes at Aylesbury's Amersham site, with £12m existing funding identified and other sources under review. [D] [P3] [P62]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNew library, community facilities and approximately 120 homes planned. [P3]
Money£12m existing funding identified [P62]Other funding sources are under review. [P62]
What happens nextPlanning submission: November 2015 [P42]Detailed consent anticipated in early 2016. [P21]
Who it affectsExisting and future residents [P18]Early facilities will serve the estate and surrounding areas. [P18]

What was decided

Cabinet agreed to proceed with a planning application for a new library, a health centre and pharmacy, an early years facility, community space and public open space at Amersham site (Plot 18), with approximately 120 residential units. The facility brief included a health centre of approximately 3,100m², an early years facility of approximately 1,000m², community space of approximately 950m² and retail space of approximately 350m². Report P3, P19

Cabinet noted that detailed planning consent for the First Development Site and outline planning consent for the Masterplan covering Phases 2, 3 and 4 had been granted. The associated section 106 agreement had been signed, and internal demolition of vacant buildings had commenced in August 2015. Report P2

Cabinet noted that the funding implications were under review and would be reported through capital monitoring. It also noted the proposed Westmoreland Road improvement works. Report P4, P5

Why

The council committed in 2009 to deliver new community facilities early, and the Aylesbury Area Action Plan identified Amersham as the optimum location. Report P17

The scheme would support existing and future residents, surrounding areas and the relocation of existing facilities from Taplow in line with the Phase 3 rehousing timetable. Report P18

The proposals align with the Aylesbury Area Action Plan and Core Strategy, while the equalities assessment found some beneficial impact on protected groups. Report P29, P36

What happens next

Notting Hill Housing Trust was scheduled to submit the Reserved Matters Planning application in November 2015, with detailed planning consent anticipated in early 2016. After submission, there would be further statutory public consultation on the detailed designs. Report P21, P42, P49

Further assessment of the capital funding impact was to be reported to Cabinet through the capital monitoring process. Report P43

Westmoreland Road works were presented for approval to proceed to detailed design and, subject to statutory consultation, implementation, with commencement anticipated in March 2016 and completion in July. Report P27

The money

  • £12m Total existing funding identified, with remaining sources under review. Report P62
  • £1.1m Council share of design fees and surveys required for planning submission. Report P43
  • £9m NHHT infrastructure fee, payable in stages linked to the start of First Development Site work. Report P41
  • £3,082,784.40 Existing section 106 funding approved for the new health centre, library and open space on the Amersham Site. Report P41
  • £76.7m Allocation approved in November 2013 for Aylesbury regeneration up to 2019/20. Report P40
  • £150m Estimated ultimate council cost over the 20 year programme under the DPA. Report P40

Options considered

  • Chosen: Submit a planning application for Amersham site redevelopment. The application would provide key community facilities early in the regeneration programme and include approximately 120 residential units. Report P3, P18
  • Chosen: Note funding implications and report through capital monitoring. The precise capital funding impact of the proposed community facilities was still being assessed. Report P4, P43
  • Chosen: Note proposed Westmoreland Road improvement works. The road is a key gateway. The proposal adds three street trees, granite footway paving, a raised pedestrian crossing table and extended footways. Report P5, P25, P26

Implications

  • Financial: The council is to fund community facilities and public open space within Plot 18, with shared professional fees apportioned under the DPA. Running costs for the new facilities are being built into future budget assumptions, and commercial leases for the GP practice and community health facility will provide council revenue. Report P41, P44
  • Financial: The capital funding impact is under review, while the council's £1.1m share of design fees and surveys is funded through committed section 106 funds. Report P43
  • Financial: At least half of the new homes on the site will be affordable in tenure. All new social rented homes will be let at target formula rents, as required by the section 106 agreement. Report P20
  • Risk: Commencement of Plot 18 development depends on NHHT demonstrating the viability of the wider Phase 2. Report P42
  • Legal: The section 106 planning agreement has been signed, and the statutory period for challenging the consents through judicial review has expired. The council has not been made aware of any judicial review application. Report P11
  • Legal: The planning application will be considered by the council's planning committee under its statutory obligations. Report P60
  • Equalities: The council concluded that the wider scheme would have some beneficial impact on protected groups. Further equalities consideration is required for Plot 18. Report P36, P38
  • Other: Early community facilities would support existing and future residents and help establish sustainable, balanced communities. The wider partnership is for a further 3,500 homes over an anticipated 19 year development period. Report P7, P18, P37

Who and where

  • Existing residents of the Aylesbury Estate Report P18
  • Future residents of the redeveloped estate Report P18
  • Residents in surrounding residential areas Report P18
  • People needing affordable homes Report P20
  • People over 55 and households whose children no longer live at home Report P20
  • Leaseholders and tenants in the rehousing programme Report P13, P15
  • People using the Aylesbury Medical Centre and community health services Report P19
  • Children and families using the early years facility Report P19

Timeline

  • 28 April 2014: The Development Partnership Agreement between the council and NHHT was signed. Report P7
  • 4 November 2014: Members approved release of £3,082,784.40 in existing section 106 funding for the Amersham Site. Report P41
  • August 2015: Planning consents were granted, the section 106 agreement was signed, and internal demolition work commenced. Report P2, P11, P12
  • November 2015: NHHT was committed to take the Plot 18 scheme to planning submission. Report P42
  • early 2016: Detailed planning consent was anticipated, and a decision on the CPO was expected from the Secretary of State. Report P14, P21
  • Spring 2016: Demolition at the Amersham site was due to commence once the remaining properties had been vacated. Report P23
  • March 2016 with completion in July: Westmoreland Road improvement works were anticipated to start and complete. Report P27
  • Quarter 3 2016/17: Plot 18 development works were anticipated, subject to the viability of the wider Phase 2. Report P42

Plain English for the jargon

  • NHHT: Notting Hill Housing Trust, the council's development partner. [P7]
  • DPA: Development Partnership Agreement between the council and NHHT. [P7]
  • AAAP: Aylesbury Area Action Plan. [P17]
  • CPO: Compulsory Purchase Order. [P14]
  • Section 106 agreement: Planning agreement signed for the estate development. [P11]
  • Reserved Matters Planning application: Application for detailed consent after outline consent for the facilities. [P21]
  • First Development Site: The initial development area within the Aylesbury Estate. [P11]
  • Target formula rents: Rents required by the section 106 agreement for all new social rented homes in the development area. [P20]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item16

Resolved

That the update progress report of the work carried out by the council and its development partner, Notting Hill Housing Trust (NHHT), in bringing forward the regeneration of the Aylesbury Estate as set out below be noted. · Detailed Planning consent for the First Development Site and outline Planning consent for the remainder of the estate Masterplan (Phases 2, 3 and 4) has been granted by the council and the associated section 106 agreement has been signed. · Demolition of vacant buildings within the FDS is now underway with the commencement of the internal soft strip contract in August 2015. 2. That it be agreed to proceed with the submission of a planning application for a new library on the Aylesbury Estate, along with a range of community facilities, including a health centre and pharmacy, early years facility, community space plus public open space and approximately 120 residential units, to be delivered through the redevelopment of the Amersham site (Plot 18), ensuring that community facilities are provided at an early stage within the Aylesbury regeneration programme. 3. That the funding implications of the proposed community facilities that are currently being reviewed be noted and that a report will come to cabinet as part of the capital monitoring report. 4. That the improvement works proposed to Westmoreland Road as a key gateway into the Aylesbury Estate be noted.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 10 pages

Recommendations

1. That the cabinet notes the update progress report of the work carried out by the council and its development partner, Notting Hill Housing Trust (NHHT), in bringing forward the regeneration of the Aylesbury Estate as set out below:

• Detailed Planning consent for the First Development Site and outline Planning consent for the remainder of the estate Masterplan (Phases 2, 3 and 4) has been granted by the Council and the associated section 106 agreement has been signed. • Demolition of vacant buildings within the FDS is now underway with the commencement of the internal soft strip contract in August 2015.

2. That the cabinet agrees to proceed with the submission of a planning application for a new Library on the Aylesbury Estate, along with a range of community facilities, including a health centre and pharmacy, early years facility, Community Space plus Public Open Space and approximately 120 residential units, to be delivered through the redevelopment of the Amersham site (Plot 18), ensuring that community facilities are provided at an early stage within the Aylesbury regeneration programme.

3. That the cabinet notes the funding implications of the proposed community facilities are currently being reviewed and will be reported back to cabinet as part of the capital monitoring report.

1 4. That the cabinet also notes the improvement works proposed to Westmoreland Road as a key gateway into the Aylesbury Estate.

BACKGROUND INFORMATION

5. Having undertaken an EU-compliant procurement process, the council appointed Notting Hill Housing Trust (NHHT) to bring forward the phased regeneration of the Aylesbury Estate, and a Development Partnership Agreement (DPA) between the Council and NHHT was signed on 28 April 2014. This partnership will see the development of a further 3,500 new homes across the Aylesbury development area, along with a number of community facilities, commercial facilities and a range of parks and open spaces and high quality public realm. In addition to the physical regeneration, the partnership provides for a number of social and economic regeneration initiatives for the duration of the anticipated 19 year development period.

6. This report sets out the progress made on the development by the council’s development partner, since the latest report to cabinet, and seeks approval to proceed with the early delivery of a range of community facilities, including a new library, at Plot 18 of the development site, as well as public realm improvement works on Westmoreland Road.

KEY ISSUES FOR CONSIDERATION

General update

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Aylesbury regenerationAppendix 1 3 pages Download
PDF
Report: Aylesbury regenerationReport 10 pages DownloadRead as text

At this meeting

Whole meeting
3Notice of Intention to conduct business in a closed meeting, and any representations receivedOn the agenda 6MinutesApproved 8Southwark School Standards Report 2015Noted 9Response to the Recommendations of the Education and Children's Services Scrutiny Sub-Committee on Narrowing the Achievement GapAgreed 10Response to Recommendations of Education and Children's Services Scrutiny Sub-Committee Review of Southwark's Adoption ServicesApproved 11Response to Recommendations from the Scrutiny of the Health of the BoroughAgreed 12Southwark Cemetery Strategy: Recommendations from Overview and Scrutiny CommitteeDecided 13Response to Overview and Scrutiny Committee recommendations on Southwark's Cemetery StrategyAgreed 14Better Placed Joint Committee with London Borough of Lambeth and London Borough of LewishamNoted 15New Southwark Plan - Preferred OptionAgreed
16Aylesbury Regeneration: Amersham Site (Plot 18) RedevelopmentThis decision
17Gateway 1: Southwark Regeneration in Partnership Programme Procurement ApprovalApproved 18Elephant and Castle Place-Making: The Next StepNoted 19Gateway 1: Asbestos Consultancy Services Contract A – Surveying and Bulk Sampling and Contract B – Air Sampling and MonitoringApproved 20Asset Management StrategyApproved 2125 Browing Street, SE17, 8 Trafaglar Avenue, SE15, 26 Hannover Park SE15 and 80 Darrell Road, London SE22 - Disposal of Freehold InterestsDecided 2266 and 68 Ambergate Street, London SE17 3RX - Disposal of Freehold InterestDecided 23Gateway 1: Procurement Strategy Approval - Commercial FleetAgreed 24Gateway 2: Contract Award Approval - Supply of Gas to all Southwark Council SitesApproved 25Gateway 2: Contract Award Approval - Supply of Electricity to All Southwark Council SitesApproved 26Former Southwark Park Nursing Home, 94 - 116 Southwark Park SE16 - Disposal of Long Leasehold InterestAgreed 27Gateway 2 Major Works Framework ContractsApproved 28Exclusion of Press and PublicOn the agenda

Who was there

10 of 12 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
SC
Councillor Stephanie CryanCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
DM
Councillor Darren MerrillCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
MS
Councillor Michael SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Aylesbury Regeneration: Amersham Site (Plot 18) RedevelopmentThis decision
  2. Amending the Rehousing Policy for Homeowners affected by the Regeneration of the Aylesbury EstateDecided
  3. Aylesbury Regeneration - Phase 1: sites 7 & 10 Revised Delivery RouteDecided
  4. Aylesbury Regeneration - Next StepsNoted
  5. Gateway 1: Procurement Strategy Approval Aylesbury Regeneration: Development PartnershipApproved
  6. Selection of a Preferred Partner to Work with the Council to Deliver the Regeneration of the Aylesbury EstateApproved

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open