Gateway 2: Contract Award Approval - Supply of Electricity to All Southwark Council Sites
ApprovedExecutive1 paper
AI summarySouthwark Cabinet approved awarding the electricity supply contract for all council sites to LASER, estimated at £6.4m per annum and £25.6m over four years. Authority for management and purchasing choices is delegated to the cabinet member for environment and the public realm. [D]
Written from the decision and the officer reportPDF Pro
OutcomeApprovedRolling two year commitment starts 1 October 2016. [P7] [P15]
Money£6.4m per annum, £25.6m total [P2]Four year estimate includes LASER management fees. [P2]
What happens nextCabinet member to manage options [D]Management and purchasing choices delegated throughout the contract. [D]
Who it affectsOffices, schools, estates, street lighting [P74]Covers electricity supplies for over 3,500 council sites. [P74] [P119]
What was decided
Cabinet approved awarding the electricity supply contract for all council sites to LASER.
The contract is estimated at £6.4m per annum for four years from 1 October 2016, with a total value of £25.6m, including LASER management fees. Report P2
Authority for the management option, any change to it, and the purchasing solution is delegated to the cabinet member for environment and the public realm throughout the contract.
Why
LASER's flexible option returned a 4.9% saving against the wholesale electricity market average, the best value of the options evaluated. Report P65
LASER offered seven purchasing options and procurement only costs of £73,556.80, compared with £84,730 for Crown Commercial Services. Report P26, P58
The rolling two year LASER framework allowed exit after two years and offered continuity, avoiding the further procurement needed if the Crown Commercial Services framework for non half hourly supplies ended in 2017. Report P46, P68
What happens next
Before 31 March 2016, the Energy Management Team was to assess management options, then review them throughout the contract through six monthly performance reviews. Report P66
During the contract, the cabinet member for environment and the public realm was to approve the selected management option, consider changing it, and amend the purchasing solution.
Before the start date, officers in property and regeneration and the Modernise Programme were to be consulted to finalise the site list, and schools and leisure centre bill payers were to be notified. Report P97, P98
The money
£6.4m per annum Estimated annual value including LASER management fees Report P2
£5,250,000 HRA current estimated annual cost Report P94
£21,000,000 HRA four year cost Report P94
£750,000 General Fund current estimated annual cost Report P94
£3,000,000 General Fund four year cost Report P94
£400,000 Schools current estimated annual cost Report P94
£1,600,000 Schools four year cost Report P94
Options considered
Chosen: LASER framework agreement. It offered more purchasing options, good past performance, lower procurement only costs, service continuity and a managed service option. Report P68
Chosen: LASER rolling two year commitment. It allowed a termination notice after two years while the four year framework continued. Report P45, P46
Rejected: LASER four year commitment. Customer authorities could not issue a termination notice to exit early. Report P44
Rejected: Crown Commercial Services framework agreement. It had higher procurement only costs, fewer purchasing options and a non half hourly framework ending in 2017. Report P26, P58, P68
Implications
Financial: The award set a buying method, not fixed electricity prices. Actual billed costs will depend on market conditions and the purchasing strategy. Report P95
Financial: Any increase in electricity prices will affect tenants' service charges, and costs under the agreement will fall within leaseholders' annual service charges. Report P75, P113
Risk: Each purchasing strategy carries risk factors, and past performance is not a guarantee of future performance. Report P35, P39, P63
Risk: No performance bond is required because LASER is part of Kent County Council. If a framework supplier ceased trading, OFGEM would appoint a new supplier to protect service continuity. Report P100, P101
Legal: The procurement is subject to EU procurement regulations and Gateway 1 and Gateway 2 procedures, with contract award reserved to Cabinet. The First Tier Property Tribunal dispensed with leaseholder consultation because fuel costs were unknown in advance. Report P105, P106, P108, P115
Staffing: The Energy Team will manage the contract and act as the single point of contact with the supplier. Client departments will pay and monitor their own invoices. Report P87, P89, P91
Climate: Energy reduction work includes efficient lighting and financially viable solar panels. LASER will be asked to present consumption data and further solutions. Report P77, P85
Equalities: The council found no equality implications associated with the procurement. Report P83
Who and where
All council electricity sites Report P74
Council offices Report P74
Schools and leisure centres Report P74, P98
Housing estates Report P74
Street lighting Report P74
Tenants and leaseholders Report P75, P113
Client departments Report P91
Energy Team Report P87, P89
Timeline
01/04/2015: Forward Plan activity completed Report P10
20/10/2015: Gateway 2 contract award approval listed in the project plan Report P14
27/10/2015: Scrutiny call in and implementation notice listed Report P14
31/03/2016: Purchasing option and management solution decision planned Report P15
01/10/2016: Southwark buy in and contract start scheduled Report P15
30/09/2018: Possible termination date for the rolling two year commitment Report P15, P46
30/09/2020: Contract completion Report P15
Plain English for the jargon
LASER: A local government purchasing consortium and part of Kent County Council. [P100]
CCS: The alternative framework provider evaluated with LASER. [P17] [P18]
LEP: The London Energy Project, which supplied independent evaluation information. [P19]
Rolling two year commitment: A four year framework that lets customers give exit notice after two years. [P45] [P46]
PIA: Purchase in advance, with electricity bought before delivery. [P131]
PWP: Purchase within period, with some electricity bought during the supply period. [P132]
Unmanaged service: The council procures electricity and deals directly with the supplier. [P29]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item25
Resolved
Recommendation for the Cabinet 1. That the award of the supply of electricity to all council sites to LASER be approved. The estimated value of the contract is £6.4m per annumfor a period of four years (with effect from 1 October 2016) making a total contract value of £25.6m . This includes management fees from LASER. Recommendation for the Leader of the Council 2. That authority be delegated to the cabinet member for environment and the public realm, throughout the duration of the contract (as detailed in the procurement project plan) to: · approve the management option selected for the contract, and consider the flexibility to change the management option (detailed in paragraphs 10, 24 and 29 of the report), and · amend the purchasing solution (purchase in advance or purchase within period detailed in paragraph 13 of the report).
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 15 pages
Recommendation
Recommendation for the Cabinet
1. That cabinet approve the award of the supply of electricity to all council sites to LASER. The estimated value of the contract is £6.4m per annum for a period of four years (with effect from 1 October 2016) making a total contract value of £25.6m. This includes management fees from LASER.
Recommendation for the Leader of the Council
2. That the Leader delegates authority to cabinet member for environment and public realm, throughout the duration of the contract (as detailed in the procurement project plan) to;
• approve the management option selected for the contract, and consider the flexibility to change the management option (detailed in paragraph 10, 24 and 29), and; • amend the purchasing solution (Purchase in Advance or Purchase within Period detailed in paragraph 13).
BACKGROUND INFORMATION
3. The recommendation of this report is that the electricity requirements are secured via a four year framework contract which expires 30 September 2020 on a rolling two year commitment. As electricity is a volatile traded commodity, the ‘wholesale’ cost of electricity has been excluded from the tender (electricity will be purchased from the wholesale market at different times both before and during the contract term). This contract has therefore not been awarded on the basis of electricity price. The contract costs set out above are therefore estimates, and actual costs will depend upon market conditions and purchasing decisions taken during the contract.
4. This contract has no extension duration built into the contract.
Procurement project plan
Date Activity completed Forward Plan (if Strategic Procurement) 01/04/2015
DCRB/CCRB/CMT Review Gateway 1: Procurement Strategy Approval DCRB 28/05/2015 CCRB 04/06/2015 Issue Notice of Intention Note: this is for contracts that only affect Leaseholders. This period is 20/07/2015 for 8 weeks Gateway 1: Procurement strategy for approval report 23/06/2015 Scrutiny Call-in period and notification of implementation of Gateway 1 decision 06/07/2015
Completion of tender documentation Advertise the contract Closing date for expressions of interest These tasks Invitation to tenders completed by consortia Closing date for return of tenders Completion of evaluation of tenders Completion of any post-tender clarification meetings Council evaluation of consortia 03/08/2015 Council evaluation of purchasing solution 03/08/2015 Issue Notice of Proposal Note: this is for contracts that only affect Leaseholders. This period is 06/09/2015 for 8 weeks
Review Gateway 2: Consortia and Contract award report DCRB 26/08/15 CCRB 03/09/15
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.