Southwark Cabinet sought planning consent for a library, community facilities and approximately 120 homes at Aylesbury’s Amersham site, with £12m existing funding, and approved disposal of a site for at least 56 extra care units. It approved a £48.3m asset programme and gas, electricity and major works contracts worth £46m, £25.6m and up to £528m.
What the committee will consider, in order, with every paper attached to its item. New Southwark Plan - Preferred Option is the main business; one item may be taken in private.
To receive any apologies for absence.
In special circumstances, an item of business may be added to an agenda within five clear working days of the meeting.
To note the items specified which will be considered in a closed meeting.
Members to declare any interests and dispensations in respect of any item of business to be considered at this meeting.
To receive any questions from members of the public which have been submitted in advance of the meeting in accordance with the cabinet procedure rules.
To approve as a correct record the minutes of the open section of the meeting held on 15 September 2015.
Decision: That the minutes of the meeting held on 15 September 2015 be approved as a correct record and signed by the chair. Decision page
To consider any deputation requests.
To note the “best start in life – Southwark school standards report 2015”.
Decision: That the ‘Best start in life - Southwark school standards report 2015’ attached at Appendix 1 of the report be noted. 2. That the GCSE provisional 2015 results from DFE (Department for Education) tabled at the meeting be noted and that the report at Appendix 1 be updated to reflect these results. Decision page
To agree the proposed response to the education and children’s services scrutiny sub-committee review on narrowing the achievement gap amongst pupils.
Decision: That the proposed response to the e ducation and children's services scrutiny sub-committee review on narrowing the achievement gap amongst pupils be agreed. Decision page
To agree the proposed response to the education and children’s services scrutiny sub-committee review of Southwark’s Adoption service and to agree a draft Adoption charter for consultation.
Decision: That the proposed response to the e ducation and children's services scrutiny sub-committee review of Southwark’s adoption service be agreed. 2. That the principle of an Adoption Charter be supported and that the draft Charter in Appendix 1 of the report be agreed for consultation with key stakeholders including potential and existing adoptive parents . Decision page
To agree the proposed response to the healthy communities sub-committee on the health of the borough.
Decision: That the proposed response to the healthy communities scrutiny sub-committee’s report on the health of the borough be agreed and that the progress in taking forward the recommendations be noted. Decision page
To consider recommendations from the overview and scrutiny committee.
Decision: That the overview and scrutiny committee recommendations be received. Decision page
To agree the proposed response to overview and scrutiny committee’s recommendations on Southwark’s Cemetery Strategy.
Decision: That the proposed response to overview and scrutiny committee’s recommendations on Southwark’s Cemetery Strategy be agreed. Decision page
To note the proposal to establish a joint committee with the London Boroughs of Lambeth and Lewisham to support governance arrangements of the Lambeth, Lewisham and Southwark (LLS) Better Placed community budget programme.
Decision: Decisions of the Cabinet 1. That the proposal to establish a Joint Committee with the London Boroughs of Lambeth and Lewisham to support governance arrangements of the Lambeth , Lewisham and Southwark (LLS) Better Placed Community Budget programme be noted. 2. That the draft terms of reference (Appendix A of the report) and memorandum of understanding (Appendix B of the report) that will be agreed at the inaugural meeting of the Joint Committee be noted. Decisions of the Leader of the Council... Decision page
To agree the New Southwark Plan Preferred Option for consultation.
Decision: That the New Southwark Plan Preferred Option (Appendices A and B of the report) be agreed for consultation subject to the following amendments: a) ‘ DM45 Low line walking routes’ to include reference to the coal line in Peckham . The proposed new bullet point is: Rye Lane to Old Kent Road, including the Coal Line. b) Changes set out in addendum report tabled that reference ‘DM34 Pubs’ and ‘DM54 Trees’ c) Amendment and expansion of take-away exclusion zones in ‘DM41 Hot food takeaways’ to... Decision page
To note the update progress report of the work carried out by the council and its development partner. To agree to proceed with the development of the Amersham site (plot 18) to ensure the early delivery of community facilities.
Decision: That the update progress report of the work carried out by the council and its development partner, Notting Hill Housing Trust (NHHT), in bringing forward the regeneration of the Aylesbury Estate as set out below be noted. Detailed Planning consent for the First Development Site and outline Planning consent for the remainder of the estate Masterplan (Phases 2, 3 and 4) has been granted by the council and the associated section 106 agreement has been signed. Demolition of vacant buildings within... Decision page
To approve the use of GLA’s London Development Panel and the inclusion of sites as listed in the appendix to the report.
Decision: Decisions of the Cabinet 1. That the use of the GLA’s London Development Panel as outlined in paragraphs 43 to 62 of the report to procure two development partners for a package of Southwark Regeneration in Partnership Programme sites over a 6 to 10 year period be approved. 2. That the inclusion of the sites as listed in Appendix 1 of the report in the package of the Southwark Regeneration in Partnership Programme to be tendered in two separate lots be approved. 3. That the indicative financial... Decision page
To note that cabinet may in the future be asked to resolve to make a compulsory purchase order in order to enable the regeneration of Elephant and Castle shopping centre to proceed.
Decision: That it be noted that cabinet may in the future be asked to resolve to make a compulsory purchase order to enable the regeneration of Elephant and Castle Shopping Centre to proceed. 2. That an equalities impact assessment be commissioned to guide cabinet on its Public Sector Equities Duty in the event it is asked to make the resolution referred to above. Decision page
To agree the procurement strategy outlined in the report for two asbestos consultancy services contracts.
Decision: That the procurement strategy outlined in the report for two asbestos consultancy services contracts - contract A – surveying and bulk sampling at an estimated annual cost of £1.2m and contract B – air sampling and monitoring at an estimated annual cost of £ 274,000, for a period of four years from 1 January 2017 to 31 December 2020, with the potential to extend each contract by a further 2 year period, making a total estimated value of £8.84m for both contracts be approved. Decision page
To approve the consultation plan for the strategy and approve the first year programme for delivery in 2016/17.
Decision: Cabinet provided comments on the draft asset management strategy for consultation. These comments included: the need for the consultation process to make clear amendments to timescale in order to be transparent and clear to check inclusion of estates ( Cossall and D’Eynsford mentioned) and that the relevant tenant management organisations are consulted ensure that all councillors are consulted and given an opportunity to comment on the strategy. 2. That the consultation plan for the strategy be... Decision page
To authorise the head of property to dispose of the council’s leasehold interests in 25 Browning Street, SE17, 8 Trafalgar Avenue, SE15, 26 Hannover Park, SE15 and 80 Darrell Road, London SE22 for a sum that equates to the market value of the individual properties.
Decision: That the head of property be authorised to dispose of the council’s freehold interest in 25 Browning Street, SE17, 8 Trafalgar Avenue, SE15, 26 Hannover Park, SE15 and 80 Darrell Road, SE22 ("the properties”), for a sum that equates to the market value of the individual properties. 2. That the earmarking of the capital receipts for the purposes of funding the housing investment programme be authorised. Decision page
To authorise the head of property to dispose of the council’s freehold interest in 66 and 68 Ambergate Street, London SE17 3RX.
Decision: That the head of property be authorised to dispose of the council’s freehold interest in 66 and 68 Ambergate Street, SE17 3RX (the “property”), for a sum that equates to the market value of the property. 2. That the earmarking of the capital receipts for the purposes of funding the housing investment programme be authorised. Decision page
To approve the procurement strategy for the provision of a commercial fleet under lease arrangements.
Decision: That the procurement strategy outlined in the report for the provision of a commercial fleet under lease arrangements up to a value of £9.2m over a period of six years through the use of established national framework agreements be approved. Decision page
To approve the supply of gas to all council sites to LASER.
Decision: RESOLVED; Decision of the Cabinet 1. That the award of the supply of gas to all council sites to LASER be approved. The estimated value of the contract is £11.5m per annumfor a period of four years (with effect from 1 October 2016) making a total contract value of £46m . This includes management fees from LASER. Decision of the Leader of the Council 2. That authority be delegated to the cabinet member for environment and the public realm, throughout the duration of the contract (as detailed in... Decision page
To approve the award of the supply of electricity to all council sites to LASER.
Decision: Recommendation for the Cabinet 1. That the award of the supply of electricity to all council sites to LASER be approved. The estimated value of the contract is £6.4m per annumfor a period of four years (with effect from 1 October 2016) making a total contract value of £25.6m . This includes management fees from LASER. Recommendation for the Leader of the Council 2. That authority be delegated to the cabinet member for environment and the public realm, throughout the duration of the contract (as... Decision page
To agree that the head of property agree terms to dispose of 94-116 Southwark Park Road, London SE16 to DV4 Limited SPV ( Delancey ).
Decision: That the head of property be authorised to agree terms to dispose of 94 -116 Southwark Park Road London SE16 to DV4 Limited SPV ( Delancey ) by way of a 999 year ground lease at a peppercorn rent and subject to a premium as outlined within the closed report. 2. That the earmarking of the capital receipts for the purposes of funding the capital programme be authorised. 3. That the sale is subject to a provision to obtain satisfactory planning consent for an extra care facility providing a... Decision page
To approve the establishment of the major works framework for a period of 4 years from 4 January 2016.
Decision: That the establishment of the major works framework for a period of 4 years from 4 January 2016 in the four Lots be approved as follows: a) Lot 1 - Main building works (low value schemes up to £3.5m) to six providers (A&E Elkins Ltd, Architectural Decorators Ltd, Niblock (Builders) Ltd, Saltash Enterprises Ltd, Standage & Co. Ltd and Thomas Sinden Ltd) at an estimated annual value of up to £50m making a total estimated contract value of up to £200m. b) Lot 2 - Main building works (high value... Decision page
That the press and public be excluded from the meeting for the following items of business on the grounds that they involve the likely disclosure of exempt information as defined in category 3 of paragraph 10.4 of the access to information rules of the Southwark Constitution. The following is a summary of the closed part of the meeting.
Item 15 is where most of this meeting's papers sit: 3 papers, about 2.2 MB.
To agree the New Southwark Plan Preferred Option for consultation.
This is the first time this subject appears in the meetings we have read.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 50 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
Every Cabinet (decommissioned, for the Executive after meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Southwark, Cabinet (decommissioned, for the Executive after
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Cabinet (decommissioned, for the Executive after, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.