Quarter 2 Capital Monitoring for 2015/16 and Capital Programme Refresh for 2015/16-2024/25
NotedExecutive5 papers
AI summaryCabinet noted the general fund and housing investment programmes for 2015/16 to 2024/25 and approved Quarter 2 virements and variations. [D] Forecast capital spend is nearly £2 billion, with budgets due to be updated at Quarter 3. [P5] [P7]
Written from the decision and the officer reportPDF Pro
OutcomeNotedBoth capital programmes and projected resources were noted. [D]
MoneyNearly £2 billion [P7]Total forecast spend across managed programmes. [P7]
What happens nextQuarter 3 budget update [P5]Forecasts will be updated and budgets moved between years. [P5]
Who it affectsCapital projects and services [P8]Local residents, learners, visitors and businesses are affected. [P8]
What was decided
Cabinet noted the general fund and housing investment capital programmes for 2015/16 to 2024/25 at Quarter 2 2015/16. Report P2, P3
Cabinet approved the virements and variations to both capital programmes set out in Appendix C. Report P4, P47
Cabinet noted projected expenditure and resources; the position will be updated and budgets reprofiled at Quarter 3. Report P5
Why
The capital programme is a major element of the council's financial activities, with a total forecast spend of nearly £2 billion. Report P7
At Quarter 2, general fund expenditure was £25.8m against £125m, while housing investment expenditure was £72.9m against £352.6m, with both programmes at 20.6% of budget. Report P16, P18
Project delays are common, so officers review forecasts and move spending between years as information changes. Report P11, P12, P23
What happens next
The position will be updated at Quarter 3 and budgets reprofiled with more up to date information. Report P5
Officers will continue monitoring and reviewing the programme over the remainder of the financial year, then report the final outturn to Cabinet. Report P49, P160
Officers will monitor capital receipts, grants and other income and apply the resources to schemes in 2015/16. Report P40, P41, P42
The money
nearly £2 billion Total forecast spend across the capital programme. Report P7
£575.9m General fund expenditure budget for 2015/16 to 2024/25. Report P44
£1,391.1m Housing investment expenditure budget for 2015/16 to 2024/25. Report P45, P46
£25.8m General fund expenditure incurred at Quarter 2 2015/16. Report P16
£125m General fund re-profiled budget for 2015/16. Report P16
£352.6m Housing investment re-profiled budget for 2015/16. Report P18
£2m Additional Southwark Regeneration in Partnership budget requiring a virement. Report P155, P156
Options considered
Chosen: Note the general fund capital programme for 2015/16 to 2024/25. It records the current Quarter 2 programme position and forecast expenditure. Report P2, P13
Chosen: Note the housing investment programme for 2015/16 to 2024/25. It records the current housing investment position and forecast expenditure. Report P3, P13
Chosen: Approve the Quarter 2 virements and variations. Appendix C contains the budget changes arising in Quarter 2 for Cabinet approval. Report P4, P47
Chosen: Note projected expenditure and resources with a Quarter 3 refresh. The forecast will be updated when more up to date information becomes available. Report P5
Implications
Financial: At Quarter 2, general fund expenditure was 20.6% of £125m and housing investment expenditure was 20.6% of £352.6m. Report P16, P18
Financial: All commitments must be met from anticipated resources, with grants and other funding sources maximised before capital receipts are used. Report P22
Financial: The additional £2m for Southwark Regeneration in Partnership will be funded by reprofiling existing estate regeneration commitments. Report P155, P156
Risk: Construction market overheating may affect project cost and timing, while a shortfall in disposal funding could require short term sources, deferral or reprofiling. Report P35, P158
Legal: The concurrent Director of Law and Democracy report identifies legal implications, while the council must monitor its financial position and take appropriate action if it deteriorates. Report P168, P173
Equalities: The capital programme is intended to benefit local communities, and each project is assessed for age, disability and other protected characteristics. Report P162, P163, P164
Other: No consultation took place on the overall programme, but individual projects are subject to any required or desirable consultation. Report P170
Staffing: Staffing resources are generally within current establishments, with any additional or specialist resources subject to separate reports. Report P167
Who and where
People who live, learn, visit or do business in the borough Report P8
Children needing school places, maintenance and expansion Report P57
Adults using refurbished properties and the Telecare service Report P63
Council housing residents in the Warm, Dry and Safe programme Report P114
Disabled people needing home adaptations through the Disabled Facilities Grant Report P91
Users of roads, public spaces and town centres affected by works Report P77, P103
Users of libraries, parks, athletics tracks and swimming pools Report P81, P85, P86, P87
Local people affected by regeneration and development schemes Report P31, P162, P164
Timeline
6 November 2015: Final report issued. Report P179
Quarter 2 2015/16: General fund and housing investment positions reported. Report P16, P18
Quarter 3: Projected expenditure and resources updated, and budgets reprofiled. Report P5
over the remainder of the financial year: Programme monitored, reviewed and final outturn reported to Cabinet. Report P49
March 2016: Warm, Dry and Safe work due to be fully committed except for a few cases, with a 90% decency target. Report P114
end of March 2016: Peckham Pulse building management, metering and lighting work due to complete. Report P87
2016/17: Some capital forecasts and schemes move into this financial year. Report P54, P135
2017/18: £48.7m of the housing forecast variance is reprofiled into this year. Report P112
Plain English for the jargon
General fund capital programme: The council's general fund capital programme, shown in Appendices A and D. [P44] [P48]
Housing Investment Programme: The housing capital programme, shown in Appendix B, including Warm, Dry and Safe works. [P18] [P45]
Virement and variation: A budget transfer and a difference from planned spend, recorded for Cabinet approval. [P11] [P47] [P156]
Reprofiling: Moving forecast spending between periods as project information changes. [P12] [P23]
Section 106 and Community Infrastructure Levy: Planning obligations under Section 106 and a separate source of capital funding. [P26]
Capital receipts: Money received from property disposals that can fund capital expenditure. [P34] [P40]
Outturn: The final actual expenditure used to determine the final funding requirement. [P22]
Warm, Dry and Safe: A housing works programme forecast to spend £185m in 2015/16. [P18]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
That the general fund capital programme for the period 2015/16 to 2024/25 as at Quarter 2 2015/16, as detailed in Appendix A and D of the report be noted. 2. That the housing investment programme for the period 2015/16 to 2024/25 as at Quarter 2 2015/16, as detailed in Appendix B of the report be noted. 3. That the virements and variations to the general fund and housing investment capital programme as detailed in Appendix C of the report be approved. 4. That the projected expenditure and resources for 2015/16 and future years for both the general fund and housing investment programmes as detailed in Appendices A, B and D of the report as at Quarter 2 2015/16 be noted, and that it also be noted that this position will be updated during the year and the budgets re-profiled accordingly at Quarter 3 when more up to date information is available.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 16 pages
Recommendations
That cabinet:
1. Notes the general fund capital programme for the period 2015/16 to 2024/25 as at Quarter 2 2015/16, as detailed in Appendix A and D.
2. Notes the housing investment programme for the period 2015/16 to 2024/25 as at Quarter 2 2015/16, as detailed in Appendix B.
3. Approve the virements and variations to the general fund and housing investment capital programme as detailed in Appendix C.
4. Notes the projected expenditure and resources for 2015/16 and future years for both the general fund and housing investment programmes as detailed in Appendices A, B and D as at Quarter 2 2015/16 and this position will be updated during the year and the budgets re-profiled accordingly at Quarter 3 when more up to date information is available.
BACKGROUND INFORMATION
5. The scale of the capital programme being managed within the council is immense and with a total forecast spend of nearly £2 billion the capital
1 programme represents a major element of the council’s financial activities. It has a significant and very visible impact on the borough and hence on the lives of those who live, learn, visit and or do business in the borough.
6. The quarter 1 2015/16 capital monitor report indicated that expenditure of £14.1m had been incurred on the general fund capital programme against a budget of £119.5m. This represented a spend of 11.8% to budget as at quarter 1 and a favourable variance of £1.5m was projected against the budget for the year at that point.
7. The quarter 1 2015/16 capital monitor report also reflected a spend of £24.7m on the Housing Investment Capital programme against a budget of £356.8m which represented a spend 6.9% against the budget for the year.
8. Due to the size and scale of the capital programme and the number of projects involved, it is inevitable that unforeseeable delays can occur which lead to some variations against planned spend. Historically the capital programme has been over programmed in year to compensate for these variations, whilst retaining a balanced programme overall.
9. The capital programme is subject to on-going review by service managers and the quarter 1 2015/16 capital monitor report noted that some of the expenditure forecast will need to be updated as the capital schemes progress through the year and it is expected that further re-profiling of budgets will be required when more up to date information is available.
10. This report sets out the current profiled budget and forecast outturn position for 2015/16 for the General Fund and the Housing Investment Programme (HIP).
KEY ISSUES FOR CONSIDERATION
General Fund Capital Spend
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.