Gateway 1: Peckham Rye Station Redevelopment Procurement Strategy
ApprovedExecutive1 paper
AI summarySouthwark Cabinet approved the London Construction Programme route for Peckham Rye station square redevelopment, with an estimated value of circa £6.2 million. It also approved retaining the feasibility design team through single supplier negotiations, with the appointment not exceeding £250,000.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedLCP route and feasibility design team extension approved
Moneycirca £6.2 millionConstruction estimate; design appointment not exceeding £250,000
What happens nextTender and appoint main contractorExpressions of interest, shortlisting, tender and Gateway 2 award
Who it affectsLocal businesses, passengers and residentsStation square, arches and Blenheim Grove redevelopment
What was decided
The procurement strategy for Peckham Rye Station Square redevelopment construction was approved through the London Construction Programme framework. Its estimated value is circa £6.2 million, based on the current cost plan, for June 2016 to July 2018. Report P1, P34, P35
Single supplier negotiations were approved to retain Landolt + Brown Architects, Sweett Group and Alan Baxter & Associates by extending their existing contract. This runs until the construction contract is signed, when the team will be novated or replaced by the main contractor’s design team. The appointment will not exceed £250,000 and will use the terms and fees from the initial appointment. Report P2
Why
The London Construction Programme was preferred because it offered the required flexibility and the largest number of contractors with relevant experience in Network Rail work, building remodelling, urban regeneration and inner London. Seven providers were on the framework, and preliminary testing found at least three relevant contractors were interested. Report P47, P56, P59
A two stage design and build process was identified as the most effective way to secure value for money and reduce construction risk. Early contractor involvement was needed for construction methods, site logistics and market testing. Report P53
Retaining the existing design team was considered to provide greater value for money than re-tendering. The team already understood the railway relationship, and its work towards a Network Rail Asset Protection Agreement was essential for delivery on time and to budget. Report P119
What happens next
After signing the LCP access agreement, the council will notify contractors, seek expressions of interest, shortlist on price and quality, and complete the two stage evaluation. At Gateway 2, subject to the developed scheme and cost plan, it will enter into the construction contract, and the design team will be novated or replaced. Report P76, P77, P78, P79, P80, P110
Additional programme funding must be identified before construction contracts are awarded at Gateway 2. This will be addressed through the quarter 3 capital budget monitoring report to Cabinet. Report P157, P182
The project manager will submit monthly monitoring reports to the GLA. The appointed contractor will attend the stakeholder working group, which meets on a 6 weekly basis. Report P152, P153
The money
circa £6.2 million Estimated construction contract value for June 2016 to July 2018. Report P1, P34
£250,000 Maximum additional design team appointment value, excluding surveys. Report P2, P118
approximately £7m Amount by which proposed commitments exceed the current agreed budget. Report P157
£5.25 million GLA project funding, subject to substantial works completion by April 2017. Report P51
£2,454,847 GLA allocation against the construction budget. Report P51, P159
£6,200,000 Total in the indicative procurement spend profile. Report P160
£3,745,153 Total Council capital in the indicative spend profile. Report P159
£4.8m Anticipated market value of the resulting commercial development. Report P162
Options considered
Chosen: London Construction Programme framework. It had the required flexibility and the largest number of contractors with relevant experience, subject to approval and signature of the access agreement. Report P1, P56, P59
Rejected: OJEU procurement route. The OJEU routes were not considered appropriate because of the project programme. Report P54
Rejected: Scape framework. Only two contractors were available, raising concerns about competition and the appropriate experience of those contractors. Report P56
Rejected: IESE framework. It did not offer the flexibility needed to obtain suitable competition under the proposed approach. Report P56
Rejected: Southern Construction framework. It had been put on hold and was not accessible at this stage. Report P56
Chosen: Retain the existing design team through single supplier negotiations. The team already understood the railway relationship, and its work towards a Network Rail Asset Protection Agreement was essential. Report P2, P119
Rejected: Re-tender the design work. Retaining the existing design team was considered to provide greater value for money. Report P119
Chosen: Two stage design and build process. It was identified as the most effective means of securing value for money and mitigating construction risk. Report P53
Implications
Financial: Total proposed commitments for compulsory purchases and construction exceed the current agreed budget by approximately £7m. Funding is sufficient for the CPO and works to proceed until the end of 2016/17. Additional funding must be identified before construction contracts are awarded. Report P157, P182
Legal: The construction procurement is subject to the full Public Contract Regulations 2015 tendering requirements. Competition through the compliant LCP framework is intended to satisfy those requirements, subject to an access agreement with Haringey Council. Each of the three design team retentions will not exceed the European Union services threshold. Report P178, P179
Risk: Delay in obtaining an Asset Protection Agreement from Network Rail, or discovery of asbestos within the Blenheim Grove building, could cause programme slippage. Report P35
Risk: The northern arches have structural uncertainty because the building supports the platform above. Further intrusive investigation is required, and detailed design must satisfy Network Rail's Asset Protection team. Report P22, P23, P91
Legal: Compulsory purchase of retail leases is part of site assembly. The council may use compulsory purchase powers for part of the adjacent Iceland site if the leaseholder and Network Rail cannot reach a development agreement. Report P10, P11, P14, P17
Equalities: Cabinet must have regard to the public sector equality duty. The Equalities Impact Assessment recommendations have been implemented, including independent advice and relocation support for affected businesses, with temporary accommodation considered for vulnerable hair and beauty businesses. Report P134, P145, P146, P147, P149, P180
Climate: The council requires sustainability to be maintained and improved through design and construction. Contractor requirements cover sustainable materials, low lifecycle impacts, local and recycled materials, and minimum Building Regulations standards. Report P140, P142, P143
Staffing: The project manager must resource and coordinate the programme and provide monthly monitoring reports to the GLA. The successful contractor must meet London Living Wage requirements, and apprenticeships must be secured through the contract. Report P135, P137, P153, P156
Who and where
Station passengers and railway users Report P5, P85, P86
Affected tenants, leaseholders and retail units Report P14, P17, P146
Local businesses and business owners at risk of losing premises Report P145, P149
Residents, visitors and community groups in Peckham Report P3, P41, P131, P132
Network Rail and the train operating company Report P9, P57, P85
The feasibility design team and main contractor Report P53, P117, P152
People with protected characteristics in affected communities Report P180
Shoppers and wider businesses in Peckham town centre Report P3, P40, P44, P94
Timeline
17/11/15: Gateway 1 approval date listed in the procurement plan. Report P104
08/12/15: Expressions of interest sought. Report P106
17/02/16: Invitation to tender issued. Report P109
13/04/16: Closing date for return of tenders. Report P110
June 2016 to July 2018: Programmed construction period from site start to completion. Report P35
08/08/16: Construction contract start. Report P111
2026-05-28: Cabinet meeting recorded for this decision.
Plain English for the jargon
LCP: London Construction Programme, the procurement framework for the main contractor.
GLA: Greater London Authority, which jointly funds the project.
Compulsory Purchase Order: An order used by the council to acquire leases for site assembly.
Asset Protection Agreement: The Network Rail agreement needed for work affecting the platform.
Gateway 1: The approval point for this procurement strategy.
Gateway 2: The approval point for the construction contract award.
London Living Wage: A minimum pay requirement for the successful contractor, where appropriate.
Equalities Impact Assessment: The March 2015 assessment used to identify project risks and social considerations.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12
Resolved
That the procurement strategy outlined in the report for the Peckham Rye Station Square redevelopment construction be approved. The procurement strategy will utilise the London Construction Programme framework at an estimated value of circa £6.2 million (based on the current cost plan) for the period of June 2016 to July 2018. 2. That the use of single supplier negotiations for the retention of the feasibility design team ( Landolt + Brown Architects, Sweett Group and Alan Baxter & Associates) through an extension to their existing contract be approved. This will be up to the point at which the construction contract is signed and the design team is either novated or replaced by the main contractor’s design team. The value of this appointment will not exceed £250,000 and will be based on the terms and fees outlined and procured for their initial appointment.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 22 pages
Recommendations
1. That Cabinet approve the procurement strategy outlined in this report for the Peckham Rye Station Square redevelopment construction. The procurement strategy will utilise the London Construction Programme framework at an estimated value of circa £6.2 million (based on the current cost plan) for the period of June 2016 to July 2018.
2. That Cabinet approve the use of single supplier negotiations for the retention of the feasibility design team (Landolt + Brown Architects, Sweett Group and Alan Baxter & Associates) through an extension to their existing contract. This will be up to the point at which the construction contract is signed and the design team is either novated or replaced by the main contractor’s design team. The value of this appointment will not exceed £250,000 and will be based on the terms and fees outlined and procured for their initial appointment. BACKGROUND INFORMATION
3. As one of Southwark’s major town centres, Peckham provides a key role in supporting its local community with a range of shopping, leisure, culture and entertainment options. Peckham town centre has the most shopping floor space of all town centres in Southwark (around 75,000sqm). Peckham town centre is formed around Rye Lane, long, narrow high streets whose busy shop fronts create a vibrant atmosphere but also contribute to pedestrian congestion along its length.
4. The town centre has smaller shops along Rye Lane as well as the Aylesham shopping centre and is a strong destination for food shopping, offering a wide variety of specialist and ethnic food. There are many small businesses in and around the town centre including a large and growing number of creative industries.
5. Peckham Rye Station is located at the heart of the retail centre. Opened in 1865, the Grade II listed building is an impressive station and is one of only four suburban stations on the London, Brighton and South Coast Railway in London designed in the house style of the 1860s. The station has been substantially amended from the original design as the large forecourt fronting Rye Lane was transformed into an arcade in the 1930s. The station is one of the main arrival points into Peckham and is key to supporting a vibrant local economy. Despite the grandeur of the building the station environs suffer from significant existing problems including; low quality public spaces, poor visibility of the station from Rye Lane, no physical focus for the area and a perception of crime in the area.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.