11,000 New Council Homes - Design Values and Standards

Approved Executive 3 papers

AI summaryCabinet approved the Southwark Design Values and interim Design Standards for 11,000 new council homes [D] [P6]. With Technical Specifications, they form the new Southwark Design Guide; implementation must use the council’s overall capital resources for the housing investment programme [D] [P76].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedThey become part of the new Southwark Design Guide [D]
MoneyImplementation within existing resources [P76]Development: Housing Revenue Account; implementation: capital resources [P49] [P76]
What happens nextTechnical Specifications in development [P10]Starting point for consultants preparing employer requirements [P10]
Who it affectsResidents, consultants and contractors [P32]It will be used across every New Homes project [P11]

What was decided

Cabinet approved Appendix 1, the Southwark Design Values, which set the council’s aspirations for design excellence and reflect its core values and commitment to residents. Report P2

Cabinet approved Appendix 2, the interim Design Standards, which commit the council to high quality and robust design. Report P3

Cabinet noted that the Design Values, Design Standards and Technical Specifications will form the new Southwark Design Guide. It thanked the deputy cabinet member for excellence in design and the officers involved.

Why

The Design Values define the outcomes sought, rather than the outputs required, for design quality in the New Homes programme. They also represent the council’s commitment to residents. Report P14

The 15 design values reflect the council’s core objectives. They draw on the 5 Fairer Future Principles, 10 Fairer Future Promises and four Housing Strategy principles. Report P15

The Design Standards act as a client brief for consultants and contractors, informed by planning guidance and the council’s experience as landlord. Their development drew on residents, councillors, council staff and consultants. Around 2,500 residents were engaged from June to August 2015, and their findings were addressed within the standards. Report P32, P33, P61, P62

What happens next

Complete the Technical Specifications. They are intended as the starting point for consultants developing the council’s employer requirements. Report P10

Update the Design Standards and Technical Specifications once the full national policy implications are clear and the emerging Southwark Plan gains weight. Review both regularly and seek feedback from residents, staff, housing managers and external development partners and consultants. Report P35, P36

Incorporate key standards and technical requirements into the Employers Requirements for every scheme. Evaluate implementation costs and benefits, including lifecycle values, through a development viability assessment for each project. Report P33, P50

Implications

  • Financial: Future implementation costs must be met from within the council’s overall capital resources for the housing investment programme. Report P76
  • Legal: National technical housing standards fully took effect from October 1 2015, restricting the council’s ability to impose optional standards relating to access to and use of buildings on developers. The council can still complete its own developments to a higher standard. Report P72, P73
  • Equalities: The guide aims to advance equality of opportunity and foster good relations through equitable treatment, tenure blind design, balanced bedroom sizes, Lifetime Homes standards and adequate wheelchair units. Report P46, P47
  • Climate: A lean, green and clean approach to energy consumption is intended to reduce fuel poverty and protect the natural environment. Report P26
  • Financial: The design values aim to reduce health and social care costs through homes and neighbourhoods that are safe, comfortable, accessible and adaptable to changing need. Report P25
  • Legal: The Design Standards and Technical Specifications will be updated when the full effects of national policy changes become clear and the emerging Southwark Plan gains weight. Report P35
  • Other: Every project starts with Design Values, then uses Design Standards as the main reference through planning and Technical Specifications more heavily thereafter. Project specific requirements will supplement the standards to reflect extra site needs while maintaining consistent quality and value for money over the long term. Report P11, P33
  • Risk: The design values are open to new ideas, innovation and the benefits of smart and sustainable technology, without taking undue risks. Report P22

Who and where

  • Future occupants of new council homes Report P11, P47
  • People needing different household sizes, ages, circumstances and lifestyles Report P18
  • People needing wheelchair units Report P47
  • Residents and communities Report P20, P29
  • Design consultants and contractors Report P32
  • Council housing managers and staff Report P36
  • External development partners and consultants Report P8, P36
  • Developers subject to optional building regulation standards Report P72

Timeline

  • July 2013: The council committed to build 11,000 new council homes by 2043, with the first 1500 delivered by 2018. Report P6
  • August to October 2014: Stage 1 of the public consultation covered the Charter of Principles. Report P52, P53
  • November 2014: Cabinet agreed the staged approach, with stage 2 covering borough wide principles including design. Report P7, P51
  • June to August 2015: Around 2,500 residents were engaged on the design of new homes and neighbourhoods during the consultation. Report P61
  • February to September 2015: Stage 2 covered borough wide principles for development. Report P54
  • 1 October 2015: Changes to planning and building regulation took effect, affecting GLA planning and funding standards and existing local planning policies. Report P35
  • Autumn 2015 onwards: Stage 3 was estate by estate and site specific engagement. Report P55
  • 2018: The New Southwark Plan was expected to be adopted, and the first 1500 new council homes were due for delivery. Report P6, P40

Plain English for the jargon

  • Southwark Design Values: Document defining the design quality outcomes sought for the New Homes programme. [P14]
  • Interim Design Standards: Client brief for design consultants and contractors, informed by planning guidance and the council’s experience as landlord. [P32]
  • Technical Specifications: Document still being developed, intended as the starting point for consultants developing employer requirements on the council’s behalf. [P10]
  • Southwark Design Guide: Suite of the Design Values, Design Standards and Technical Specifications. [P8]
  • Employers Requirements: Scheme requirements into which key standards and technical specifications are incorporated. [P33]
  • Tenure blind design: Design approach under which all new homes are tenure blind and occupants are treated equitably. [P47]
  • Lifetime Homes standards: Standard required for all new homes, with adequate wheelchair units also provided. [P47]
  • Development viability assessment: Project specific evaluation of implementation costs and benefits, including lifecycle values. [P50]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

That the Southwark Design Values attached in Appendix 1 of the report which sets out the council’s aspirations for design excellence and reflect the council’s core values and commitment to residents be approved. 2. That the interim Design Standards attached in Appendix 2 of the report which set out the council’s commitment to high quality and robust design be approved. 3. That it be noted that the two documents along with a third document, the Technical Specifications, will form the new Southwark Design Guide. 4. That Councillor Leo Pollak, deputy cabinet member for excellence in design, and the officers involved, be thanked for their work on the Southwark Design Guide.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 8 pages

Recommendations

That the Cabinet:

1. Approves the Southwark Design Values attached in Appendix 1 which sets out the council’s aspirations for design excellence and reflect the council’s core values and commitment to residents.

2. Approves the interim Design Standards attached in Appendix 2 which set out the council’s commitment to high quality and robust design.

3. Notes that the two documents along with a third document, the Technical Specifications, will form the new Southwark Design Guide.

BACKGROUND INFORMATION

4. In July 2013 this council made an historic commitment to build 11,000 new council homes by 2043; with the first 1500 delivered by 2018.

5. In November 2014 Cabinet agreed, as part of a staged approach to formalise further community engagement in the delivery of the new council homes, that the second stage engagement would address borough wide principles including design. A report noting the outcomes of the second stage engagement is being presented to Cabinet at this meeting.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Southwark design Values 2015Appendix 1 34 pages Download
PDF
Interim Southwark Housing Design StandardsAppendix 2 40 pages Download
PDF
Report: 11,000 New Homes Design Values and StandardsReport 8 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 12 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
SC
Councillor Stephanie CryanCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
DM
Councillor Darren MerrillCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, apologies
MS
Councillor Michael SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. 11,000 New Council Homes - Design Values and StandardsThis decision
  2. Developing Long Term Plans for the Delivery of New Council HomesNoted
  3. Next Steps on Developing Long Term Plans for the Delivery of New Council HomesNoted
  4. Update on Consultation and Plans for the Delivery of 11,000 New HomesAgreed
  5. Update on the Proposed Pipeline for the Delivery of 1,500 New Council Homes by 2018Noted
  6. Key Principles and Protocol for Developing New Council Homes in Partnership with ResidentsAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open