London Borough of Southwark
Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 4.00pm

Gateway 1: Procurement Strategy Approval - Contractor Services for the Delivery of Commercial Way New Homes Delivery

Noted Executive 1 paper

AI summarySouthwark Cabinet approved the strategy for an OJEU tender for 112 new homes at Commercial Way, with an estimated construction works contract sum of £16,735,230 [D] [P2] [P9]. The Council Leader delegated Gateway 2 to the chief executive [D] [P4].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommercial Way works, two sites bordering Cronin Street [D] [P2]
Money£16,735,230 [D] [P2]Estimated construction works contract sum [D] [P2]
What happens nextGateway 2 delegated [D]Chief executive will decide Commercial Way [D] [P4] [P48]
Who it affects112 new homes [P9]Affordable homes for households in need [P75] [P86]

What was decided

Cabinet approved the procurement strategy for an OJEU tender at Commercial Way, covering two sites bordering Cronin Street [D] [P2]. The estimated construction works contract sum is £16,735,230, with individual build contracts expected to run for approximately 18 to 24 months [D] [P2]. Report P2

The Leader of the Council delegated the Gateway 2 decision for Commercial Way to the chief executive [D] [P4] [P48]. Report P4, P48

The approved procurement strategy uses an EU restricted procedure with two stages: a pre qualification questionnaire followed by an invitation to tender [P32]. At least five organisations will be shortlisted, and awards will use a 70/30 price/quality ratio [P33] [P60]. Report P32, P33, P60

Why

A design and build fixed price route is expected to be quicker than traditional building contracts [P14]. It is intended to mitigate cost increases and unforeseen issues, while allowing alternative build solutions and maintaining the specification, planning obligations and core design principles [P15]. Report P14, P15

The iESE framework initially offered a quick route, but the process was felt to be too drawn out [P23] [P24]. It has a limited number of contractors and often excludes medium sized and local contractors [P25]. Report P23, P24, P25

An individual fixed lump sum tender should give more contractors an opportunity to compete and achieve value for money [P18]. It also allows the council to target appropriate building contractors for the largest phase 2 site [P17] [P29]. Report P17, P18, P29

What happens next

The Employers Agent and New Homes Delivery Team will complete the tender documents, and local residents will continue to be consulted at each development stage [P53] [P54] [P55] [P78]. Tendering will start after the architects finish Stage D+ drawings [P30]. Report P30, P53, P54, P55, P78

The tender will run through a pre qualification questionnaire and invitation to tender [P32]. The evaluation panel will assess price and quality, and the Employers Agent will submit a tender and value for money report [P60] [P70] [P71]. Report P32, P60, P70, P71

The chief executive will take the Gateway 2 decision because Cabinet approval would add at least 4 to 6 weeks [D] [P48]. The procurement plan records contract award on 03/01/2017 and initial completion on 06/12/2018 [P47]. Report P47, P48

The money

  • £16,735,230 Estimated construction works contract sum for Commercial Way Report P2
  • £3,362,363 Estimated total on costs Report P9
  • £20.1m Estimated value of works and professional fees Report P106
  • £18m Estimated funding required Report P125
  • £13.5m Around this amount could be applied for Section 106 funding Report P123
  • £4.5m Around this amount is estimated for Right to Buy funding Report P124
  • £75.5m Projected Right to Buy receipts up to March 2018 Report P110
  • £176.4m Projected Section 106 fund up to March 2019 Report P110

Options considered

  • Chosen: Individual project OJEU tender. It provides a fixed price design and build route, supports competition, and allows appropriate building contractors to be targeted [P14] [P17] [P18] [P29]. Report P14, P17, P18, P29
  • Rejected: iESE consultancy and contractor framework. The process was felt to be too drawn out, and the framework has a limited contractor pool that often excludes medium sized and local contractors [P23] [P24] [P25]. Report P23, P24, P25
  • Rejected: London Construction Panel, London Development Panel and Scape Framework. The council did not believe these frameworks would address the concerns with using iESE [P27]. Report P27
  • Rejected: Traditional building contract route. The design and build fixed price route was preferred as it was likely to be quicker, reduce risks and be more competitive on cost [P14] [P15]. Report P14, P15

Implications

  • Financial: The estimated value of works and professional fees is £20.1m [P106]. The report gives 72 units for Social Rent and 40 for intermediate rented housing [P109], while the finance advice gives 88 dwellings for Council tenants and 24 for intermediate rented housing [P122]. Report P106, P109, P122
  • Financial: The scheme is expected to use Right to Buy receipts for 30% and Section 106 funding for 70% [P109]. The Section 106 estimate depends on future developer contributions, which may be affected by economic conditions or government policy changes [P123]. The report also warns that long term affordability may require existing plans to be reviewed, their timing changed, the programme lifecycle extended and, in extreme cases, programmed activity curtailed [P126]. Report P109, P123, P126
  • Legal: Because the estimated contract value exceeds £15m, approval of the procurement strategy is reserved to Cabinet [P134]. The procurement must meet the full tendering requirements of the Public Contract Regulations 2015 and be advertised in OJEU or use another EU compliant process [P135]. The award will use the most economically advantageous tender with a 70/30 price/quality ratio under the two stage restricted procedure [P32] [P60]. Report P32, P60, P134, P135
  • Risk: Tendering will happen before planning permission, so contractors may prioritise tenders that already have planning permission [P30]. Report P30
  • Equalities: The proposals will benefit households in need across Southwark and increase housing options for older people and people with disabilities [P75]. Half of the homes are intended for existing local tenants in need, with the remainder for other households in need on the council housing register [P86] [P137]. Report P75, P86, P137
  • Climate: Environmental assessments will identify the impact of the proposed development [P93]. The project brief will address whole life cycle costs, sustainable sourcing, environmentally benign heating and lighting, water recycling and Code of Sustainable Homes criteria [P95] [P96]. Report P93, P95, P96
  • Staffing: The New Homes Delivery Team plans to procure 13 sites with concurrent or overlapping processes and must ensure necessary staff resources are available [P49]. This project will use existing staff and budgets, and the report says staff resources are sufficient [P103] [P104]. Report P49, P103, P104
  • Risk: Nearby communities may face short term inconvenience and disruption while works take place, followed by longer term benefits from new homes [P76]. Report P76

Who and where

  • Council tenants Report P122
  • People needing intermediate rented housing Report P122
  • Existing local tenants in housing need Report P86
  • Other households in need on the council housing register Report P86
  • Older people needing improved housing options Report P75
  • People with disabilities needing improved housing options Report P75
  • Nearby residents during construction works Report P76
  • Local people receiving employment and training Report P84

Timeline

  • 07/06/2016: Approval of Gateway 1 procurement strategy report Report P47
  • 01/07/2016: Publication of OJEU notice Report P47
  • 07/08/2016: Closing date for expressions of interest Report P47
  • 01/09/2016: Invitation to tender Report P47
  • 15/10/2016: Closing date for return of tenders Report P47
  • 10/12/2016: Approval of Gateway 2 contract award report Report P47
  • 03/01/2017: Contract award Report P47
  • 06/12/2018: Initial contract completion date Report P47

Plain English for the jargon

  • OJEU: Official Journal of the European Union, where the contract notice will be published [P57].
  • PQQ: Pre Qualification Questionnaire, used to shortlist tenderers [P32] [P33].
  • ITT: Invitation to Tender, the second stage of the restricted process [P32].
  • MEAT: Most economically advantageous tender, the award basis using a 70/30 price/quality ratio [P60].
  • iESE: Improvement and Efficiency South East consultancy and contractor framework [P23].
  • LLW: London Living Wage, which the successful contractor is expected to meet [P83].
  • PSED: Public Sector Equality duty under the Equality Act 2010 [P137].
  • Gateway 2: The contract award decision in the procurement plan [P47] [P48].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item16

Resolved

Decision of the Cabinet 1. That the procurement strategy to undertake an OJEU tendering process for one of the New Homes Delivery Phase 2 sites (as noted in paragraph 3 of the report) – Commercial Way (two sites bordering Cronin Street) be approved. The total estimated construction works contract sum of the project is £16,735,230. It is estimated that the length of the individual build contracts will be for approximately 18 to 24 months. Decision of the Leader of the Council 2. That the Gateway 2 decision for Commercial Way be delegated to the chief executive for the reason outlined in paragraph 28 of the report.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 13 pages

Recommendations

Recommendation for the Cabinet

1. That cabinet approves the procurement strategy to undertake an OJEU tendering process for one of the New Homes Delivery Phase 2 sites (as noted in paragraphs 3) – Commercial Way (two sites bordering Cronin Street). The total estimated construction works contract sum of the project is £16,735,230. It is estimated that the length of the individual build contracts will be for approximately 18 to 24 months.

Recommendation for the Leader of the Council

2. That the leader of the council agrees to delegate the Gateway 2 decision for Commercial Way to the chief executive for the reason outlined in paragraph 28.

BACKGROUND INFORMATION

3. This procurement strategy relates to the procurement of the construction works contract for Commercial Way, which is part of the council’s programme to build 11,000 new homes. The initial target of which is to build 1,500 new homes by 2018. 4. This report forms part of a larger procurement strategy for the next phase of the New Homes Programme.

5. The New Homes Delivery Programme is aimed at creating new homes from existing council assets.

6. The principle of New Homes Delivery was agreed in July 2012, with phase 2 of the New Homes Delivery Programme approved in October 2013.

7. This approval will deliver a total of 112 new homes at an estimated works cost of £16,735,230 and estimated total on costs of £3,362,363. The on costs include:

a. Architects Fees b. Employer Agent Fees

8. The architect / employers agent role has been previously tendered using the Hyde and Peabody approved framework and was approved in a Gateway 2 report in November 2015.

Summary of the business case/justification for the procurement

9. The council has committed to the delivery of 11,000 new homes programme by 2043. The initial target is to build 1,500 new homes by 2018. This procurement exercise will build on the progress made to date and enable the progression of a further 112 new homes.

10. This procurement process will secure the works contracts on a design and build fixed price basis. This route is preferred to a traditional building contract route because:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report: Contractor services for Commercial Way New HomesReport 13 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 12 attended
PJ
Councillor Peter John OBEChair, present
SC
Councillor Stephanie CryanCommittee Member, present
MA
Councillor Maisie AndersonCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, apologies
RL
Councillor Richard LivingstoneCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
JS
Councillor Johnson SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
IW
Councillor Ian WingfieldCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Gateway 1: Procurement Strategy Approval - Contractor Services for the Delivery of Commercial Way New Homes DeliveryThis decision
  2. Gateway 1 – Procurement Strategy Approval -The NestApproved
  3. Gateway 1 - Procurement Strategy Approval - Southwark and Lambeth Barristers FrameworkApproved
  4. Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking ServicesApproved
  5. Gateway 2: Contract Award Approval - Corporate Insurance Procurement (excluding Property Insurance)Approved
  6. Gateway 1 - Initial Procurement Strategy, Parking and Traffic Enforcement Services ContractAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies