Cabinet approved grants within a £2,449,997 children’s centres programme budget, an estimated £16,735,230 construction contract for 112 new homes, and immediate Thames Water refunds estimated at c. £28.6 million. It also approved the draft Old Kent Road Area Action Plan and consultation on a £218 per square metre residential levy expected to generate around £158m.
What the committee will consider, in order, with every paper attached to its item. Draft Old Kent Road Area Action Plan is the main business.
To receive any apologies for absence.
In special circumstances, an item of business may be added to an agenda within five clear working days of the meeting.
There are no closed items scheduled for consideration at this meeting. However a closed appendix has been circulated for Item 8, Scrutiny Review of Southwark’s Non-residential property.
Members to declare any interests and dispensations in respect of any item of business to be considered at this meeting.
To receive any questions from members of the public which have been submitted in advance of the meeting in accordance with the cabinet procedure rules. The deadline for the receipt of public questions is midnight Wednesday 1 June 2016.
To approve as a correct record the minutes of the open section of the meeting held on 15 March 2016.
Decision: That the open minutes of the meeting held on 15 March 2016 be approved as a correct record and signed by the chair. Decision page
To consider any deputation requests. The deadline for the receipt of deputations is midnight Wednesday 1 June 2016.
To consider recommendations from the overview and scrutiny committee and for the relevant cabinet member to report back within eight weeks.
Decision: That the recommendations below be noted and a report be brought back by September 2016: a) That a new policy should be introduced which makes available to the public information about the non-residential properties Southwark is renting and leasing out. The register should include the name of the tenant, the annual rent, the amount of any up front premium paid, the date the agreement was signed and the date the agreement is due for renewal. This should be phased in over two years b) That... Decision page
To consider recommendations from the healthy communities scrutiny sub-committee and for the relevant cabinet member to report back within eight weeks.
Decision: That the recommendations be noted and that the cabinet member for adult care and financial inclusion brings back a report to cabinet by September 2016, in order to respond to the overview and scrutiny committee. Decision page
To note the progress in implementing a new model of managing the delivery of Children’s Centres in Southwark, following changes in national policy and to approve grants to lead agencies for the delivery of the children’s centres programmes.
Decision: That the progress in implementing a new model of managing the delivery of children's centres in Southwark following changes in national policy be noted. 2. That grants to lead agencies for the delivery of the children's centres programme in line with the model as set out in paragraph 32 of the report be approved. Decision page
To agree a new approach to agreeing valuations to property with affected homeowners on the Aylesbury Estate from phase 2 onwards.
Decision: That the new approach to agreeing valuations of property with affected homeowners on the Aylesbury Estate from Phase 2 onwards to include a non-binding arbitration process, as set out in the report be agreed, if requested by the leaseholder or freeholder. Decision page
To approve the draft Old Kent Road Area Action Plan and the proposed changes to the adopted policies map for public consultation.
Decision: That the draft Old Kent Road Area Action Plan (Appendix A) and the proposed changes to the adopted policies map (Appendix B) for public consultation be approved. 2. That the integrated impact assessment (Appendix C), the consultation plan (Appendix D) and Habitats Regulations assessment (Appendix E) be noted. Decision page
To approve the Community infrastructure levy (CIL) preliminary draft charging schedule and the draft “Regulation 123 List” (the list of infrastructure items which will not be funded by section 106 planning obligations) for public consultation.
Decision: That the Community Infrastructure Levy (CIL) preliminary draft charging schedule (Appendix A) and the draft “Regulation 123 List” (the list of infrastructure items which will not be funded by section 106 planning obligations) (Appendix B) be approved for public consultation. 2. That the draft addendum to the adopted Section 106 and Community Infrastructure Levy Supplementary Planning Document (2015) (Appendix C) be approved for public consultation. 3. That the draft infrastructure plan... Decision page
To agree to consider using the provisions of s227 of the Town & Country Planning Act 1990 on a case by case basis to enable stalled developments to proceed and to a dopt the principles set out in the report to evaluate applications to use the provision of s227 of the Town & Country Planning Act 1990.
Decision: That it be agreed to consider using the provisions of s227 of the Town & Country Planning Act 1990 on a case by case basis to enable stalled developments to proceed. 2. That the principles set out in Appendix A of the report to evaluate applications to use the provision of s227 of the Town & Country Planning Act 1990 be adopted. Decision page
To approve the Fairer Future Procurement Strategy.
Decision: That The Fairer Future Procurement Strategy be approved. This replaces the contracts and procurement strategy in the medium term resources strategy. 2. That the introduction of a strategic assessment (gateway zero) into the procurement governance process for service contracts over £10m be approved. 3. That the next steps for enhancing our commitment and approach to social value in procurement as outlined in paragraphs 23 to 32 of the report be noted. 4. That the additional actions to combat the... Decision page
To approve the procurement strategy to undertake an OJEU tendering process for one of the new homes delivery phase 2 sites.
Decision: Decision of the Cabinet 1. That the procurement strategy to undertake an OJEU tendering process for one of the New Homes Delivery Phase 2 sites (as noted in paragraph 3 of the report) – Commercial Way (two sites bordering Cronin Street) be approved. The total estimated construction works contract sum of the project is £16,735,230. It is estimated that the length of the individual build contracts will be for approximately 18 to 24 months. Decision of the Leader of the Council 2. That the Gateway... Decision page
To note the progress against the council’s workforce strategy 2013-16.
Decision: That the progress made against the council’s workforce strategy 2013-16 be noted. 2. That the workforce reports attached as appendix one and two of the report be noted and that these reports: a) Demonstrate that the council continues to reflect the diversity of the borough in the makeup of its workforce and the levels of change that have taken place have not impacted negatively on the diversity of the workforce; b) Demonstrate that the council has protected frontline staff despite the level of... Decision page
To agree that the council proceeds with immediate refunds to current tenants, with interest calculated under the provisions of the Water Resale Order 2006 and to instruct the strategic director of housing and modernisation to make the necessary arrangements for refunds to former tenants.
Decision: That the council proceeds with immediate refunds to current tenants, with interest calculated under the provisions of the Water Resale Order 2006, the refunds themselves covering the period 1 April 2001 to 28 July 2013, and with interest covering the period 1 April 2001 to 30 June 2016. 2. That the strategic director of housing and modernisation be instructed to make necessary arrangements for refunds to former tenants covering the periods outlined in paragraph 1 to take place during the course... Decision page
To note the progress made on the creation of the new My Southwark Homeowners Service as agreed by cabinet in December 2015.
Decision: That the progress being made on the creation of the new My Southwark Homeowners service as agreed by Cabinet in December 2015 be noted. Decision page
To consider motions on the following: Low water pressure in Bermondsey East Street Market.
Decision: Low water pressure in Bermondsey That the motion referred from council assembly as a recommendation to cabinet, set out below, be noted: Council Assembly: 1. Notes with concern ongoing reports from residents and businesses about low water pressure affecting residents across the borough, which is causing problems for residents with daily essentials, including boilers, showers and washing machines. 2. Further notes that Thames Water has acknowledged that the low pressure is a deliberate strategy... Decision page
To consider and agree appointments to outside bodies for 2016/17.
Decision: That the appointments to the outside bodies listed in Appendix A of the report for the 2016/17 municipal year be agreed as follows: Age UK London Councillor Richard Livingstone Better Bankside Board Councillor Mark Williams Canada Water Consultative Forum Councillor Mark Williams Councillor Kath Whittam Councillor Stephanie Cryan Councillor James Okosun Central London Forward Councillor Peter John Centre for Literacy in Primary Education Councillor Catherine Rose Creation Trust Councillor Mark... Decision page
To agree the allocations of places and nominations to the panels, boards and forums for 2016/17.
Decision: That the allocation of places to the panels and boards and forums set out in Appendix A of the report for the 2016/17 municipal year be agreed as follows: Joint Partnership Panel (Trade union consultation) Councillor Peter John Councillor Fiona Colley Homeowners Service Charge Arbitration Tribunal (Members to act as a pool) Councillor Sandra Rhule Councillor Sunny Lambe Councillor Evelyn Akoto Councillor Jon Hartley Councillor Tom Flynn Councillor Kath Whittam Councillor Lorraine Lauder... Decision page
Item 12 is where most of this meeting's papers sit: 2 papers, about 6.4 MB.
To approve the draft Old Kent Road Area Action Plan and the proposed changes to the adopted policies map for public consultation.
This is the first time this subject appears in the meetings we have read.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 33 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
Every Cabinet (decommissioned, for the Executive after meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Southwark, Cabinet (decommissioned, for the Executive after
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Cabinet (decommissioned, for the Executive after, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.