Southwark Council's Buy-back Offer for Ledbury Towers Leaseholders
NotedExecutive1 paper
AI summaryCabinet noted a buy back policy for leaseholders at Ledbury Towers and delegated individual purchases to the Director of Regeneration. A detailed cost assessment and funding identification are required, with £10m provisionally set aside.
Written from the decision and the officer reportPDF Pro
OutcomeNotedIndividual buy backs delegated to the Director of Regeneration.
MoneyProvisionally £10mExpected cost is £10m. Additional council costs are £35,000 - £45,000.
What happens nextAssess cost and identify fundingIndividual valuations will establish market values and council costs.
Who it affectsLedbury Towers leaseholdersFour blocks, with 14 of 33 leaseholders interested in valuations.
What was decided
Cabinet noted the proposed policy for the council to buy back leaseholder properties at Bromyard House, Peterschurch House, Skenfrith House and Sarnsfield House, which are subject to structural investigations.
Cabinet required a detailed financial assessment and funding identification for the Ledbury buy back offer.
Authority for individual buy backs was delegated to the Director of Regeneration.
Why
Extraordinary circumstances at Ledbury Towers and the complexity of the required works led to the recommendation. Report P10, P32
The policy seeks to redress the imbalance in landlord support between tenants and those who buy their homes. An Equalities Impact Assessment was provided. Report P8
The offer responds to leaseholders' collective and individual concerns. Public meetings for residents and leaseholders called for a policy and procedures to start the process. Report P34
What happens next
Carry out individual property valuations to establish market values, stamp duty costs and the council's additional costs. Report P1, P2, P3
Undertake a detailed financial assessment and identify funding for the buy back offer.
Seek to identify the likely spend profile in this and next year. The growing resource gap may require borrowing. Report P6
The money
£10m Expected cost and provisional sum identified in the existing Housing Investment Programme. Report P6, P32
over £10 million Potential cost if all thirty three leaseholders purchase alternative property. Report P6
£35,000 - £45,000 Estimated additional council costs based on existing buy back programmes. Report P3
£100,000 Threshold above which acquisitions outside an agreed scheme are reserved to Cabinet. Report P15
£200,000 Value of 45 Sarnsfield, a 2 bed property sold on 4/3/17. Report P6
£200,000 Value of 28 Sarnsfield, a 2 bed property sold on 23/2/17. Report P6
£250,000 Value of 55 Skenfrith, a 3 bed property sold on 3/3/16. Report P6
Options considered
Chosen: Proceed with a Ledbury Towers buy back policy for leaseholders. The offer applies only to Ledbury Towers because of the extraordinary situation and complexity of the works required. Report P32
Implications
Financial: The full cost is unknown because the number intending to sell, property values and additional costs are not yet known. It is unlikely all 14 leaseholders who expressed interest would convert to a sale. Report P1, P2, P3, P32
Financial: The cost is expected to be in the region of £10m. The amount is provisionally set aside in the Housing Investment Programme and is expected to be financed from Right To Buy receipts, other sources and borrowing. Report P6, P32
Financial: An ever increasing resource gap may require borrowing. The council will seek to identify its likely spend profile in this and next year. Report P6
Legal: The council can lawfully acquire the properties under section 120 of the Local Government Act 1972. Report P13, P14
Legal: Purchases costing more than £100,000 are reserved to Cabinet under Part 3C of the Constitution if no scheme has already been agreed. The intended Scheme treatment would allow individual purchase authority to be delegated to the Director of Regeneration. Report P15
Equalities: The council must consider possible disproportionate effects on groups sharing protected characteristics and take mitigation steps where needed. Report P16, P18, P28
Risk: Buying back properties would increase the number of vacant properties, supporting any potential future decant programme. Report P10
Other: The offer applies only to Ledbury Towers because of the extraordinary situation and complexity of the works required. Report P32
Who and where
All 33 leaseholders at Ledbury Towers, across Bromyard House, Peterschurch House, Skenfrith House and Sarnsfield House. Report P1
The 14 leaseholders who have expressed interest in having their property valued. Report P1
Tenants and people who buy their homes, whose support the policy seeks to balance. Report P8
Residents and leaseholders who raised concerns and attended public meetings. Report P34
Timeline
3/3/16: 55 Skenfrith, a 3 bed property, sold for £250,000. Report P5, P6
23/2/17: 28 Sarnsfield, a 2 bed property, sold for £200,000. Report P5, P6
4/3/17: 45 Sarnsfield, a 2 bed property, sold for £200,000. Report P5, P6
29 November 2017: The report reached final version and was dated. Report P39
1 December 2017: The final report was sent to the Constitutional Team. Report P39
2026-05-28: Cabinet made the Ledbury Towers buy back decision.
Plain English for the jargon
Buy back: Purchase by the council of a leaseholder's property.
Leaseholder: An owner of one of the 33 properties at Ledbury Towers who may wish to sell it to the council.
Housing Investment Programme: The programme from which acquisitions are to be funded in the year they occur.
Right To Buy receipts: A proposed funding source, combined with other sources and borrowing.
Decant programme: A possible future programme that increased numbers of vacant properties would support.
Scheme: The constitutional treatment intended for these acquisitions, allowing authority for individual purchases to be delegated.
Equalities Impact Assessment: An assessment provided with the report to support the recommendation.
Protected characteristic: A characteristic listed under the Equality Act 2010, such as age, disability, race, sex or religion.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item16
Resolved
That the proposed policy to allow the buy-back of leaseholder properties in Ledbury Towers (Bromyard House, Peterschurch House, Skenfrith House and Sarnsfield House), which are currently the subject of structural investigations be noted. 2. That a detailed financial assessment of the Ledbury buy-back offer is undertaken, funding is identified and delegated authority for individual buy backs be given to the director of regeneration.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 7 pages
Item No. Classification: Date: Meeting name: 16. Open 12 December 2017 Cabinet
Report title: Southwark Council’s Buy-Back Offer for Ledbury Towers Leaseholders
Ward(s) or groups affected: Livesey Ward
From: Councillor Stephanie Cryan, Deputy Leader and Cabinet Member for Housing
FOREWORD BY COUNCILLOR STEPHANIE CRYAN, DEPUTY LEADER AND CABINET MEMBER FOR HOUSING
Following the tragedy of the Grenfell Tower fire, Southwark took action to check that its tower blocks were fully compliant with current fire regulations. That included the four tower blocks on the Ledbury Estate; Bromyard House, Peterschurch House, Skenfrith House and Sarnsfield House.
Residents of those tower blocks told us about concerns with some cracks appearing in their homes. Arup, a structural engineering company, were engaged to inspect the cracks and advise on what that meant for the buildings and the safety of residents. Their interim report concluded that the cracks could compromise the compartmentalisation of the buildings and have an impact on fire safety. It also concluded that the buildings could be affected by a catastrophic event, such as a gas explosion.
Following receipt of that interim report the council took the decision to turn off the gas supply to the buildings. Since then efforts have been made to restore heating and hot water facilities to the blocks and put measures in place to mitigate the fire risks. A temporary district heating system has been installed for each of the four tower blocks. Heating and hot water was restored to all of the flats by 16th October. There are fire wardens stationed in each of the four blocks and the stay put policy in the event of fire has been suspended and there is an immediate evacuation policy in place.
This is a unique situation and the council ensured to reassure residents of the steps being taken to manage their concerns, but quite understandably, some residents did not feel safe and wanted to move. Some residents took up offers of temporary accommodation while the work to install the heating and hot water solution was carrying on. Others were, and are, seeking a longer term move away from the towers.
This report provides a buy-back offer for the 33 leaseholders who may feel that their future no longer lies in the towers. The offer to buy back leaseholder’s properties will remain open while the future of the towers is being considered. Arup have produced a second and fuller report which provides additional information on the state of the blocks. The council and residents will need to consider that report carefully and draw conclusions on the viability of the blocks and how best to proceed. In the meantime, this report recommends a mechanism for handling properties which leaseholders would prefer sell back to council. RECOMMENDATIONS
1. That cabinet notes the proposed policy to allow the buy-back of leaseholder properties in Ledbury Towers (Bromyard House, Peterschurch House, Skenfrith House and Sarnsfield House), which are currently the subject of structural investigations.
2. That a detailed financial assessment of the Ledbury buy-back offer is undertaken, funding is identified and delegated authority for individual buy backs be given to the Director of Regeneration.
BACKGROUND INFORMATION
3. The current situation relating to the four tower blocks on the Ledbury Estate appears to be unprecedented. Following the tragedy of Grenfell Tower, the council carried out extensive fire risk assessments on all high rise blocks (those over 7 stories). At the four high rise blocks on the Ledbury estate it was identified that due to the construction/design and age of the blocks, the compartmentalisation of the flats could be compromised in the event of fire, so compromising the safety of residents.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.