Gateway 0 - Strategic Options Assessment for Responsive Repairs and Maintenance Works
NotedExecutive5 papers
AI summaryCabinet directed officers to plan non chargeable housing repairs through SBS for 12 months from October 2018, with a Cabinet report due March 2018 [D]. Related roofing and rainwater procurement was estimated at £1.3m per annum, with £3.9m including an optional extension year [P2].
Written from the decision and the officer reportPDF Pro
OutcomeNoted12 months from October 2018, with progress report due [D]
Money£1.3m per annum; £3.9m total [P2]Both are estimates; total includes one optional extension year [P2]
What happens nextPlans, progress report and tender [D]Progress report due to Cabinet in March 2018 [D]
Who it affectsCouncil housing and leaseholders [P40][P41]Roofs, rainwater drainage and communal areas [P40][P142]
What was decided
Cabinet noted that ending the housing repairs contracts in October 2018 created an opportunity to review service delivery and consider new, more effective delivery models.
Officers were instructed to develop detailed plans for all non chargeable repairs and associated works. SBS, the council's in house trading service, would undertake them for an initial 12 months from October 2018.
Cabinet required a progress report in March 2018 covering a proposed service model, project plans, full risk assessments and a full business case for SBS delivery. It also noted that procurement preparation for chargeable repairs had started and that the contracts would be tendered subject to approval of the report.
Why
The ending of the housing repairs contracts offered an opportunity to reconsider how the services were provided and to consider more effective delivery models.
Residents rely on the council to maintain roofs and rainwater drainage to prevent water entering homes and communal areas. These works support health and safety and quality of life. Report P40
Competitive tendering was intended to demonstrate best value for leaseholders and provide backup arrangements. The geographical work packages were expected to attract competitive tenders from local Small and Medium sized Enterprises. Report P41, P42
What happens next
Develop detailed plans for all non chargeable repairs and associated works by SBS for an initial 12 months from October 2018.
Provide Cabinet with a March 2018 progress report containing the proposed delivery model, project plans, full risk assessments and a full business case.
Make arrangements for chargeable repairs by 3 October 2018. Procurement preparation has started, with tendering subject to approval of the report.
The money
£1.3m per annum Estimated annual combined cost, met from the current (2017/18) repairs and maintenance budget Report P2, P135
£3.9m Total estimated value including the optional further year Report P2
£600k Revenue for roofing, asphalt, rainwater and drainage Report P34
£400k Revenue for scaffolding Report P34
£300k Contingency for building associated works Report P35
£55m Estimated value of the existing Mears contract Report P7
Options considered
Rejected: Do nothing. The council must maintain roofs and rainwater drainage as landlord and employer. Report P50
Rejected: Council provides the services in house. For chargeable leasehold works, the council could fail to recover its costs if the work was not procured. SBS would still be invited to tender. Report P51
Rejected: Internal or external frameworks. No existing external frameworks were available. Report P52
Rejected: Shared Services. Neighbouring boroughs had their own contracts, which were not open for other boroughs to use. Report P54
Chosen: Competitive tender. The other routes were unsuitable, and the estimated value was below the EU threshold for works contracts. Report P55
Implications
Financial: The estimated cost can be met from the current (2017/18) repairs and maintenance budget. The allocation may be adjusted under budgetary pressures and will be reconfirmed at the contract award stage. Report P135, P136
Legal: Contract Standing Orders, CSO 4.3, require all reasonable steps to obtain at least five tenders from the council's works Approved List. The contractor change is likely to be a service provision change under the Transfer of Undertakings (Protection of Employment) Regulations 2006, TUPE, so due diligence must determine the full scope before tender details are finalised. The intended contract values are below the EU threshold, so approval is reserved to the relevant chief officer or delegated authority. Report P75, P83, P85, P148, P150, P152
Staffing: No direct staff impact is expected because the existing engineering and compliance team already performs contract management. However, staff under the Mears Ltd contract and the SBS service level agreement may transfer to a new provider, and possible pension implications are still being assessed. Report P78, P79, P80, P81, P82, P131
Risk: If a contractor ceases trading, controls include checking Approved List credentials, testing financial stability and using a backup contractor during reprocurement. No performance bond is required. Money will be withheld until satisfactory completion, and a parent company guarantee will be required if the successful contractor has a parent company. Report P63, P64, P65, P66, P67, P68
Equalities: Successful contractors must demonstrate an Equal Opportunities Policy and comply with equalities legislation. Tenderers must confirm that staff are paid at least the minimum London Living Wage hourly rate and explain how productivity will improve. Report P114, P122
Climate: Contracts require roof and timber products to be recycled. Use of low emission vehicles and journey planning will be encouraged. Water authority approved chemical safe products will be used for rainwater and drainage works. Report P124, P125
Other: The scope covers pitched and flat roof coverings, rainwater goods and services, fascia and soffits, sundry and minor building works, access equipment and external associated repairs. Report P24, P25, P26, P27, P28, P29
Other: The contracts support the Fairer Future Promise of quality affordable homes. Contractors must provide apprenticeships for Southwark residents and work experience for schools and people not in education, employment or training. Residents will be consulted through monthly tenants and residents association meetings and estate walkabouts. Report P70, P105, P110, P138
Local Small and Medium sized Enterprises Report P42, P111
Southwark residents eligible for apprenticeship opportunities Report P105
Schools and people not in education, employment or training Report P110
Employees who may be in scope of TUPE transfer Report P78, P79, P80
Timeline
04/10/2017: Approval of the Gateway 1 procurement strategy report Report P73
12/02/2018: Closing date for return of tenders Report P73
March 2018: Progress report due to Cabinet
30/04/2018: Approval of the Gateway 2 contract award report Report P73
14/05/2018: Contract award Report P73
03/10/2018: Contract start Report P73
02/10/2021: Contract completion date if the extension is exercised Report P73
Plain English for the jargon
SBS: Southwark Building Service, the council's in house housing repairs service [P5][D].
Gateway 1: Approval of the procurement strategy at this stage of the procurement [P37][P38][P73].
Gateway 2: The contract award stage [P73][P136].
CSO: The council's Contract Standing Orders. CSO 4.3 requires at least five tenders from the works Approved List [P148][P150].
MEAT: Most economically advantageous tender, assessed at 70:30 for price and quality [P92].
SME: Small and Medium sized Enterprises that can tender for and resource the local work packages [P42].
LLW: London Living Wage [P107].
TUPE: Transfer of Undertakings (Protection of Employment) Regulations 2006, covering qualifying service provision changes [P75][P78].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item19
Resolved
That it be noted that the ending of the housing repairs contracts in October 2018 provides the council with an opportunity to review the way in which these services are offered and to consider new and more effective delivery models. 2. That officers be instructed to develop detailed plans that would allow all non chargeable repairs and associated works to be undertaken by the council’s in house trading service for housing repairs (SBS) for an initial period of 12 months with effect from October 2018. 3. That a progress report be received by cabinet in March 2018 setting out a proposed new service delivery model, project plans, full risk assessments and a full business case in support of the delivery of the service by SBS. 4. That it be noted that due to the requirement to have arrangements in place for chargeable repairs by 3 October 2018, preparation for the procurement process for these contracts has started and will be tendered subject to the approval of this report.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 14 pages
Recommendation
1.
That the strategic director of housing and modernisation approves the procurement strategy outlined in this report, to undertake a competitive tender using the council’s works approved list for two (2) roofing and rainwater contracts as detailed below at an estimated annual combined cost of £1.3m for a period of two years with the option to extend both contracts by a further year making a total estimated value of £3.9m commencing 3 October 2018.
* Contract A — North of the borough - £650,00 per arinum “= Contract B — South of the borough - £650,000 per annum BACKGROUND INFORMATION
2,
Currently, there is a contract for long term repairs and maintenance (the contract) with Mears Ltd (Mears) for the south of the borough and there is a service level agreement (SLA) in place with the council’s Southwark Building Service (SBS) for the north of the borough, ‘which provide housing repair and maintenance works to the geographical divisions.
The contract with Mears commenced on 3 October 2013 for an initial five year period, with the option to extend for a further 5 years (three years plus two
. years) for an estimated value of £55m. The initial period is due to expire on 2
October 2018. At this time, there are no plans to utilise the extension option.
The SLA with SBS commenced on 3 June 2009 for a 10 year period and is due to expire on 8 June 2019.
The SLA and the contract provide the following works across all trades to residential buildings;
e Day to day responsive repairs.
e Void works.
e Out of hours emergency works.
6.
7.
Both Mears and SBS sub-contract responsive repairs and maintenance roofing and rainwater works.
An options appraisal, for the future repairs service, was presented to cabinet member for Housing and cabinet member for Finance, Modernisation and Performance on 11 September 2017. This report detailed various options with the recommendation to;
« Implement a new SLA with SBS to deliver internal non leasehold chargeable repairs _ to tenant properties.
e Procure a number of measured term contracts for leasehold chargeable works as detailed below;
i. Two responsive repair and maintenance (2) roofing and rainwater contracts. ii. | Two responsive repair and maintenance (2) communal repairs contracts. iii. | Two responsive repair and maintenance (2) fire protection contracts: iv. One responsive repair and maintenance (1) metal works contract.
8. The asset management team undertake regular housing inspections of the roofs and rainwater drainage to ensure repairs are completed and free from hazards.
9. The responsive repairs and maintenance contracts aim to maintain roofs and drainage systems across the council's housing stock. These contracts will complement the quality homes improvement programmes (QHIP).
10. The proposed scope of works will be:
e Repair, overhaul and renew all types of coverings to pitched roofs, including all associated works
e Repair, overhaul, renew all types of coverings to flat roofs, including all associated works
e Repair, overhaul, renew all rainwater goods and services of all types of materials and sizes : : ,
e . Repair, overhaul, renew fascia’s, soffits and other associated works
e Sundry and minor building works
¢ All scaffolding, mobile towers, hydraulic lifts and working platforms to facilitate ‘the works e Repair all external associated repairs:
11. These new contracts will be awarded based on a geographical split (north and south) of the borough, each providing all of the works, with a maximum term for each contract of three years.
a. Contract A — north - Walworth, Borough and Bankside, Bermondsey, Rotherhithe
b. Contract B - south - Camberwell, Peckham, Nunhead and Peckham Rye; Dulwich . :
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.