Land at Goschen Estate, Camberwell

Approved Executive 3 papers

AI summarySouthwark Cabinet approved changing land at Goschen Estate from housing to planning use, then back to housing [D]. An approved construction budget exists and must cover possible compensation claims, while the change is intended to reduce injunction risk [P16] [P25] [P45].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedHousing to planning, then back to housing [D]
MoneyConstruction budget approved [P45]Must cover possible compensation claims [P45]
What happens nextComplete both appropriations [D] [P3]Procure contractor, then review budget [P10] [P45]
Who it affectsOccupiers and new residents [P12] [P30]Minor lighting and short term disturbance [P12] [P30]

What was decided

Cabinet confirmed that the Appendix A land was no longer required for housing and approved its appropriation to planning purposes. The approval uses section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972. Report P2

After the housing to planning appropriation is completed, Cabinet confirmed that the land would no longer be required for planning and approved its appropriation back to housing purposes. This uses section 9 of the Housing Act 1985 and section 122(1) of the Local Government Act 1972. Report P3

Why

Appropriating the land for planning allows third party rights to be overridden once construction begins, so beneficiaries cannot use an injunction to stop the development. Beneficiaries may claim compensation for loss of value. Report P16, P17, P65

The strategy is intended to prevent construction being frustrated or delayed, encourage the maximum number of bidders and achieve a lower construction cost. Report P25, P26

Returning the land to housing reverses the debt transfer and avoids adverse accounting implications. It also advances the Council Plan promise of quality affordable homes. Report P27, P28, P46

What happens next

Complete the housing to planning appropriation and carry out the authorised works. Then appropriate the land back to housing purposes. Report P3, P65, P66

Procure the regeneration contract and appoint a contractor. Construction is intended to commence as early as possible afterwards. Report P10

The budget must make provision for diminution in value compensation claims and be reviewed after procurement. The compensation and new homes budget also needs consideration in future capital programme budget setting. Report P45, P68

Options considered

  • Chosen: Appropriate from housing to planning, then back to housing. It reduces injunction risk, supports more bidders and lower costs, and avoids adverse accounting effects. Report P18, P25, P26, P27
  • Rejected: Keep the land held for planning purposes. Holding the land for planning purposes may cause adverse financial implications. Report P18
  • Rejected: Accept the risk of an injunction stopping development. The risk may be fatal to development or create significant unquantifiable costs. Report P16

Implications

  • Legal: Authorised work can proceed even where it interferes with third party rights after planning appropriation. Beneficiaries cannot use an injunction to stop or delay the development, but may claim compensation for loss of value. If compensation is not agreed, the Upper Tribunal (Lands Chamber) determines it. Report P16, P17, P65
  • Legal: The land is owned freehold by the council, which legal advice identifies as a requirement for appropriation. It is no longer required for its present housing purpose. Report P4, P50, P51, P52
  • Financial: Construction has a significant cost and an approved budget exists. The budget must provide for diminution in value compensation claims and will be reviewed after procurement. Report P45
  • Financial: The land appropriation is expected to have a neutral financial impact. Transferring the land from the general fund to the housing revenue account reverses the debt transfer. Report P46, P68
  • Risk: Planning appropriation is intended to reduce construction delay and frustration, encourage more bidders and lower construction cost. Report P25, P26
  • Equalities: The council says it had regard to possible effects on protected groups. It considers that no such groups will be adversely affected. Report P43, P44
  • Other: The approved proposals include new homes at council rent levels and a formal play space. A commitment makes 50% of the new social rented homes available to local residents in housing need. Report P7, P8, P9, P30, P70
  • Other: A specialist assessment found no notable reduction in daylight or sunlight for neighbouring buildings, although some reduction remains. Short term construction disturbance may occur. Over 400 occupiers were consulted and nine objections were lodged, with one concerning daylight and sunlight. Report P12, P13, P14, P30

Who and where

  • Future residents of the new homes at council rent levels Report P9, P30
  • Nearby occupiers affected by lighting and construction disturbance Report P12, P13, P30
  • Beneficiaries of third party rights over the land Report P16, P17
  • Local residents in housing need Report P70
  • Prospective builders and construction contractors Report P10, P13, P26
  • Nearby youngsters using the play space Report P30

Timeline

  • 22 October 2013: Cabinet approved the Phase 2 housing report, which included the Goschen Estate site. Report P6
  • 25 February 2015: Council Assembly approved the current Council Plan, including the Fairer Future promise of quality affordable homes. Report P5
  • 13 July 2016: Section 203 of the Housing and Planning Act 2016 came into force. Report P54
  • 9 May 2017: Cabinet approved a similar appropriation strategy for regeneration at Commercial Way. Report P23
  • 3 October 2017: Planning subcommittee A resolved to grant consent, subject to completing a section 106 agreement, for two residential blocks. Report P7, P8
  • 30 November 2017: The final report was sent to the Constitutional Team. Report P75
  • as earliest as possible once a contractor is appointed: Construction of the regeneration is intended to commence. Report P10
  • by 2018: The council had an aspiration to provide 1,500 new homes. Report P6, P70

Plain English for the jargon

  • Appropriation: The process by which a council changes the purpose for which it holds land [P16].
  • Planning purposes: Statutory purposes for which land may be acquired under sections 226 or 227 of the Town and Country Planning Act 1990 [P53].
  • Third party rights: Rights over land that can be overridden after appropriation, with compensation available [P16].
  • Injunction: A court order that affected people may seek to stop development [P13] [P16].
  • Diminution in value: The reduction in affected property value used to calculate compensation [P17].
  • Right to light: An example of an unregistered right over land that may be overridden [P16].
  • Housing revenue account: The account involved when land is appropriated from the general fund, reversing an earlier debt transfer [P46].
  • Council rent levels: The rent basis on which all seventeen new housing units will be let [P9].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item21

Resolved

That it be confirmed that the land shown hatched on the plan at Appendix A of the report that is currently held for housing purposes is no longer required for those purposes and that the appropriation of the land to planning purposes to facilitate the carrying out of the development proposals for the area in accordance with section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972 be approved. 2. That it be confirmed that following completion of the appropriation in resolution 1 the land shown hatched on the plan at Appendix A of the report, will no longer be required for planning purposes and that the appropriation of the land to housing purposes in accordance with section 9 of the Housing Act 1985 and section 122(1) of the Local Government Act 1972 be approved.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 8 pages

Recommendations

That cabinet:

1. Confirms that the land shown hatched on the plan at Appendix A that is currently held for housing purposes is no longer required for those purposes and approves the appropriation of the land to planning purposes to facilitate the carrying out of the development proposals for the area in accordance with section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972.

2. Confirms that following completion of the appropriation at paragraph 1 the land shown hatched on the plan at Appendix A will no longer be required for planning purposes and approves the appropriation of the land to housing purposes in accordance with section 9 of the Housing Act 1985 and section 122(1) of the Local Government Act 1972. BACKGROUND INFORMATION

3. The land in question is shown hatched on the plan at Appendix A. It is owned freehold by the council. It comprises garages, car parking, cycle parking, landscaping, a pram store and former meeting room. It is bounded by the railway line to the east, Harford House to the north and Horsman House to the west. It forms part of the Goschen Estate.

4. On 25 February 2015 council assembly approved the current Council Plan. This sets out Fairer Future promises one of which is: quality affordable homes. Within this commitment is the policy to improve housing standards and build more homes of every kind. This promise was in fact reinforcing previous policy to directly provide additional housing to meet the need for affordable housing within the Borough.

5. In pursuit of this cabinet has received a number of reports both before and after the Council Plan adoption to deliver new housing sites and the subject site was included in the Phase 2 report approved by cabinet on 22 October 2013. This report contained proposals for around 277 new council homes and followed an earlier report to directly deliver 290 new homes. These initiatives form part of the council’s aspiration to provide 1,500 new homes by 2018.

6. On 3 October 2017 planning sub-committee A resolved to grant consent subject to completion of a s106 agreement for the regeneration of the land in two residential blocks to provide the following:

 6 one bedroom flats  6 two bedroom flats  5 three bedroom flats  associated landscaping  carparking

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Plan of land at land at Goschen Estate CamberwellAppendix A 1 pages Download
PDF
Rationale for appropriations of the landAppendix B 2 pages Download
PDF
Report: Land at Goschen Estate, CamberwellReport 8 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 13 attended
PJ
Councillor Peter John OBEChair, present
SC
Councillor Stephanie CryanCommittee Member, present
MA
Councillor Maisie AndersonCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
JS
Councillor Johnson SituCommittee Member, present
IW
Councillor Ian WingfieldCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, apologies
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

All 13 on the meeting page

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies