AI summaryCabinet approved a two stage EU restricted tender for Maydew House and the Bede Centre, with an estimated contract value of £61.5 million and total scheme cost of £65.5 million [D] [P3]. The estimated contract period is 208 weeks from July 2019 [P2].
Written from the decision and the officer reportPDF Pro
OutcomeApprovedTwo stage design and build for both schemes [P49] [P54]
MoneyScheme cost £65.5 million [P3]Total cost includes £4 million professional fees [P3]
What happens nextStage 1 then Stage 2 [P54] [P59]Stage 2 requires separate Gateway 2 approval [P59] [P61]
Who it affects199 homes retained [P12]Social rent homes at Maydew and Bede [P12]
What was decided
Cabinet approved the further revised strategy to revert to an EU restricted tender. The estimated contract value is £61.5 million, split between £39 million for Abbeyfield Estate HINE at Maydew House and £22.5 million for the Bede Centre new build, for an estimated 208 weeks from July 2019. Report P2
Cabinet noted estimated professional fees of £4 million, including £1 million recharged to capital for internal staff. This makes the total estimated scheme cost £65.5 million. Report P3
The approved strategy uses a two stage design and build process, with pre construction services followed by construction. Report P49, P52, P54, P59
Why
Maydew House had been stripped for refurbishment. Its asbestos levels and communal heating and hot water infrastructure required major investment. Report P34, P45
The Greater London Authority London Development Panel route was not viable because only two contractors showed interest, one withdrew and one remained undecided. Restrictions affecting companies aligned with registered providers may also have reduced interest. Report P5, P6
The current project structure allows contractors to take ownership of homes for sale, reducing council risk while sharing higher sale proceeds. The design and build route transfers maximum risk to the contractor, helps control costs, and enables early engagement in a volatile market. Report P19, P49, P52, P55
What happens next
Calfordseaden and council teams will develop the tender documentation. The council will test market interest, hold a site open day, issue a PIN and advertise through OJEU, Contracts Finder and Pro-contract. Report P39, P40, P86, P88, P89
PAS 91 responses will assess economic and financial standing, technical knowledge, accreditation, experience and capacity. The top five suppliers will be shortlisted for Stage 1, with 70% price and 30% quality weighting. Report P91, P92, P93
Stage 2 construction will require separate Gateway 2 approval. The Stage 1 contractor is expected to receive the works contract, subject to the contracting authority's decision. Report P59, P61
The money
£61.5 million Total estimated contract value Report P2
£39 million Abbeyfield Estate HINE, Maydew House works Report P2
£22.5 million New build development at the Bede Centre Report P2
£4 million Estimated professional fees Report P3, P148
£1 million Capital recharge for the internal staff element Report P3
£65.5 million Total estimated scheme cost Report P3
£29.9m Funding requirement for homes for sale Report P26
£65.5m Council forward funding under Option 1 Report P25
Options considered
Chosen: EU restricted tender using a design and build contract. It transfers maximum risk to the contractor, helps control the specification and council costs, and brings contractor design expertise and financial incentives. Report P49, P52
Chosen: Proceed with the current Maydew and Bede proposals. The Housing Investment Board agreed this structure. Contractors may take ownership of homes for sale at tender stage, reducing council risk while allowing the council to share higher sale proceeds. Report P19
Rejected: Use the GLA LDP, Hyde or South East Consortium frameworks. The LDP route was not viable after only two contractors showed interest. The council thought South East Consortium could have a similar outcome, and provider alignment restrictions may have limited interest. Report P5, P6, P47
Rejected: Use an EU traditional tender. The council would retain design and consultant performance responsibility, and the route is slow and confrontational. It also conflicts with the planned design and build contract because Bills of Quantities have not been produced. Report P48
Rejected: Do nothing. Maydew House has already been stripped for refurbishment, and the council could lose social rented units. Report P45
Rejected: Provide the works in house. The council does not have the resources or expertise needed for this type of work. Report P46
Rejected: Break the contract into lots. The contract is too large to divide, and the development is on one site. Report P50
Rejected: Deliver the project through regeneration. Legal advice found that no existing council contracts applied to the project. Report P51
Implications
Financial: Provision for the full scheme cost is in the housing investment programme. Sale receipts and previously approved council funds are expected to fund the scheme, while the Bede new build is funded from section 106 and right to buy receipts. Costs will be confirmed at Gateway 2, and the programme's resource shortfall requires careful monitoring and accurate forecasting. Report P151, P152, P153, P164, P165
Legal: Because this is a strategic procurement, Cabinet or Cabinet committee authorisation follows Corporate Contract Review Board consideration. The restricted tender must comply with the Public Contracts Regulations 2015 and council Contract Standing Orders. Report P170, P173, P174
Legal: Pre construction and construction each require separate Gateway 2 reports. Any contract variation or extension beyond the report's scope needs further approval under council procurement protocols. Report P166, P175
Equalities: The scheme is intended to increase good quality affordable homes, including larger homes, and improve options for older and disabled people. Half of the new homes are for existing local families under a local lettings policy, with new rented homes at social rent levels. Nearby households may face disruption during construction but are expected to benefit from the new homes. Report P107, P109, P110, P119, P120
Climate: New council homes have a target carbon reduction rate of 15% by 2022, and homes must meet Code for Sustainable Homes Level 5. Requirements also cover energy, carbon, water, flooding, biodiversity and construction waste. Report P126, P127, P130, P134
Risk: Controls include financial checks, a performance bond, retention, a 12 month defects liability period and an extended new build warranty. A parent company guarantee is required where the contractor has a parent company, while mortgage availability for sale units remains a medium risk. Report P64, P68, P69, P70, P71
Staffing: The report says staffing is sufficient for the timetable and will use existing staff and budgets. Calfordseaden will manage the contract, supported by council investment and engineering staff. Report P136, P137, P142, P143
Other: All sold flats in Maydew have been bought back, so the contract has no service charge implications. Other HINE work at Thaxted and Damory will be service chargeable under a separate scheme with leaseholder consultation. Garages under Maydew will be demolished without replacement, causing a loss of amenity. Report P177, P179
Who and where
Current and future residents of Maydew House Report P7, P121
The Bede Centre and people who use it Report P7, P14
Existing local families needing affordable housing Report P110, P119
Households in need, older people and disabled people Report P107, P109
The council social housing portfolio Report P12, P37
Nearby communities and Southwark Park users Report P15, P110
Leaseholders and garage users at Maydew House Report P177, P179
Local workers, apprentices, contractors and suppliers Report P114, P117, P169
Timeline
13/03/2018: Scheduled approval of the Gateway 1 procurement strategy report. Report P82
26/04/2018: Scheduled publication of the OJEU notice. Report P82
27/04/2018: Scheduled publication on Contracts Finder. Report P82
28/05/2018: Scheduled closing date for expressions of interest. Report P83
13/7/2018: Scheduled invitation to the Stage 1 tender for five tenderers. Report P83
3/12/2018: Scheduled approval of the Gateway 2 contract award report. Report P83
Jun 2019: Scheduled contract award and addition to the Contract Register. Report P83
July 2019: Scheduled contract start, with initial completion set for June 2023. Report P83
Plain English for the jargon
HINE: High investment needs estate, the designation used for the Abbeyfield Estate refurbishment programme [P5].
EU restricted tender: A two stage process in which interested firms express interest, pass prequalification and then receive an invitation to tender [P54].
Design and build: A contract arrangement where the contractor takes design and construction responsibility, transferring maximum risk to it [P49].
Gateway approvals: Gateway 1 approves the procurement strategy, while later Gateway 2 reports cover pre construction and construction [P61].
PIN: Prior Information Notice, used to announce the planned procurement and invite suppliers to a meeting [P41] [P88].
OJEU: Official Journal of the European Union, used to advertise the contract [P89].
PAS 91: The prequalification questionnaire used to assess economic and financial standing and technical capability [P91].
Contract Standing Orders: Council rules requiring publicly advertised competitive tendering for contracts above EU threshold values [P174].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item18
Resolved
That the further revised procurement strategy set out in the report reverting back to the EU restricted tender process with a total estimated contract value of £61.5 million, which is split across Abbeyfield Estate HINE (Maydew House) with an estimated value of £39 million and the new build development at the Bede Centre with an estimated value of £22.5 million, for an estimated period of 208 weeks from July 2019 be approved. 2. That it be noted that there are estimated professional fees of £4 million which includes £1 million recharged to capital for the internal staff element. This makes a total estimated scheme cost of £65.5 million.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 20 pages
Recommendations
That Cabinet:
1. approves a further revised procurement strategy set out in this report reverting back to the EU restricted tender process with a total estimated contract value of £61.5 million, which is split across Abbeyfield Estate HINE (Maydew House) with an estimated value of £39 million and the new build development at the Bede Centre with an estimated value of £22.5 million, for an estimated period of 208 weeks from July 2019.
2. notes that there are estimated professional fees of £4 million which includes £1 million recharged to capital for the internal staff element. This makes a total estimated scheme cost of £65.5 million.
BACKGROUND INFORMATION
3. Cabinet approved the enhanced refurbishment works to Abbeyfield Estate designating a high investment needs estate (HINE) on 20 March 2012. 4. Cabinet approved the gateway 1 for the procurement process on 22 July 2014 for an EU restricted tender procurement, however this procurement did not proceed due to the requirement to appoint specialist architects which subsequently had an impact on the procurement timetable, this is further explained in paragraph 10. Following this Cabinet further approved a revised procurement process on 13 December 2016 for the use of the Greater London authority (GLA) London Development Panel (LDP) framework. It is now not viable to procure the works through this route as interest was received from only 2 contractors of which one further withdrew and one contractor remained undecided. Prior to the Grenfell tragedy this was previously identified as a low risk as soft market testing was carried out and a bidders day was held to promote the programme.
5. Interest from the contractors on the GLA LDP framework deteriorated since the tragic events at Grenfell. The council has considered using another framework (i.e. the South East Consortium) but the outcome may well be the same as the interest from the LDP framework. It was also recognised that whilst the GLA LDP framework had 25 companies on it there were restriction around certain companies who could tender because of their alignment with Registered Providers (RP’s) which was a possible cause of little interest.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.