What was decided
The council will enter the master development agreement with British Land for the Appendix 1 site. It will take a long lease of British Land’s freehold interests under s227 and delegate completion of the legal documents by 31 May 2018. Report P1, P2, P3, P24
The Director of Regeneration is delegated to enter a CPO indemnity agreement and to agree the planning application submission as landowner, within the endorsed masterplan. Report P4, P6
Cabinet endorsed the 15 year masterplan, plot A2 as the preferred leisure centre location and the project framework. It also endorsed four social regeneration themes and instructed officers to complete the social regeneration charter and report back before the planning application is determined. Report P5, P7, P8, P9, P52, P58, P60, P104
Why
The public and private partnership pools ownership, shares development risk and reward, and directs development through a masterplan consistent with the Canada Water Area Action Plan. Report P15, P19, P145
The ownership structure supports a mix of uses, better planning, other funding and options for either party to exit. Report P37, P49
The partnership is intended to provide long term returns that may help fund council services. Its social charter is intended to ensure local communities can benefit from the investment. Report P17, P18
What happens next
Complete the MDA legal formalities and sign the conditional agreement by 31 May 2018. British Land then has 28 days to submit the masterplan planning application. Report P3, P32, P68
Agree the detailed phase 1 and outline planning applications as landowner. The planning committee will determine them after statutory consultation, and the scheme will be referable to the mayor. Report P6, P78, P79
Complete the social regeneration charter and report to Cabinet before planning determination. The Directors of Regeneration and Leisure Services must agree the leisure centre specification by 31 May 2018. Report P9, P95, P105
The money
- £35m Council contribution cap for the standalone leisure centre. Report P87, P165
- £45.7m British Land’s current total leisure centre project price. Report P88
- £3.1m Council’s 20% contribution to the purchase price of the former Rotherhithe Police Station and Old Dock Office. Report P141
- £8m Included within the £35m cap for risk, contingency and professional fees. Report P88
- £250k per annum Cap on recovery of the council’s management costs, subject to annual indexation. Report P151
- up to £12m British Land may use from the housing zone designation for phase one affordable housing. Report P82
- £20m Total secured through the housing zone designation. Report P82
- 20% Council’s share of third party sale proceeds and its credited base ownership position. Report P43, P73, P133
Options considered
- Chosen: Enter the master development agreement. Pooling ownership allows a masterplan to direct development across the area. Report P1, P19
- Chosen: Take a 500 year lease under s227. It supplies the land needed for proper planning and the overarching Head Lease. Report P2, P35, P158
- Chosen: Enter a CPO indemnity agreement. It protects the council from CPO and compensation costs if powers are later used. Report P4, P60, P64
- Chosen: Endorse the masterplan. It provides the framework for redevelopment over the next 15 years. Report P5
- Chosen: Use plot A2 for the new leisure centre. The phase one site can accommodate the proposed high specification centre. Report P7, P72, P85
- Chosen: Endorse the four social regeneration themes. They provide a framework for social, health and economic benefits. Report P8, P99, P104
- Chosen: Use cost review and exit points for plot A2. The council or British Land can stop the plot A2 project if restated costs are unacceptable. Report P7, P89, P90, P91
- Chosen: Complete the social regeneration charter before determination. It will set shared priorities with community involvement and inform legal obligations. Report P9, P98, P104, P105
Implications
- Financial: Current 5% turn over rent and around £400k per annum Print Works rent stop under the new Head Lease. The council can then collect 20% of rent from Surrey Quays Shopping Centre and the Mast Leisure Centre, and has a base ownership position of 20%. Early modelling indicates at least neutral rent in the first five years after drawdown. Report P52, P53, P56, P133
- Financial: The council’s standalone leisure centre contribution is capped at £35m, while British Land prices the project at £45.7m. If the council proceeds above the cap, the shortfall is recovered through the infrastructure account on an 80:20 basis. Report P87, P88, P92, P165
- Legal: The agreement creates a 500 year lease of British Land’s land and a 500 year Head Lease over the site. The Head Lease disposal must be supported by external adviser confirmation that it represents best consideration under s123. Report P35, P36, P159
- Legal: Any use of CPO powers would need a separate Cabinet decision. The CPO indemnity would indemnify the council against CPO costs and compensation for compulsorily purchased interests. Report P60, P64
- Risk: The leisure centre requires planning permission, vacant possession and agreement on a final construction price. Significant cost risks remain, and the council may opt out if vacant possession is not secured by June 2023. Report P86, P88, P94
- Equalities: The council must have regard to the public sector equality duty in plot investment and planning decisions. The social regeneration charter and four themes are intended to secure local social, health and economic benefits. Report P98, P104, P147, P148, P149
- Staffing: Preparation requires officer time and external specialists, funded within existing budgets. The decision creates no new resource implication. Report P151
- Other: The phase one masterplan includes 35% affordable housing, split 70/30 social rent and shared ownership, space for a new sixth form and capacity for up to 20,000 new jobs. Transport, school and health capacity must meet increased demand over time through a Strategic Forum overseeing development and coordinating investment. Report P70, P73, P74, P77
Who and where
- People living, working and using services in Canada Water and Rotherhithe Report P12, P98
- People needing affordable housing and council housing Report P70, P71, P80, P81
- Future leisure centre users Report P72, P96
- Local schools, sixth form learners, education and training providers Report P74, P100
- Local organisations and businesses seeking employment and training opportunities Report P73, P100, P101, P102
- British Land, plot developers and third party investors Report P24, P42, P117, P118
- People affected if CPO powers are used Report P60, P64
- Transport, health and education providers serving the area Report P75, P76, P77
Timeline
- September 2017: Cabinet endorsed the Heads of Terms, including initial landowner shares of BL 80% and council 20%. Report P20
- 31 May 2018: Complete the MDA legal formalities, sign the conditional agreement, agree the leisure specification and complete the affordable housing option. Report P3, P32, P81, P95
- within 28 days: Submit the masterplan planning application after the council as landowner agrees the scheme. Report P32, P68
- the summer of 2018: Establish a steering group to oversee governance during delivery. Report P108
- 10 year long stop date: Conditions precedent must be satisfied or the agreement may be terminated. Report P33
- financial year 2020-21: The £3.1m contribution for the former Rotherhithe Police Station and Old Dock Office is expected to become due when the MDA becomes unconditional. Report P164
- June 2023: The council may opt out of plot A2 if vacant possession has not been secured. Report P94
- next 15 years: The masterplan provides the framework for redevelopment of the area. Report P5
Plain English for the jargon
- MDA: The Master Development Agreement for Canada Water. It covers ownership, plot development, finance, affordable housing and the leisure centre for the first development cycle [P24, P26, P27, P28, P29, P30, P31].
- CWAAP: The Canada Water Area Action Plan, adopted in November 2015 to guide development in the area up until 2026 [P12].
- Head Lease: An overarching 500 year lease of the entire site between the council and BL CW Holdings Ltd, with rent providing the council’s return [P35, P36].
- CPO: Possible compulsory purchase powers that may be used to obtain possession if agreement cannot be reached. Any use needs a separate Cabinet decision [P60].
- s227: Section 227 of the Town and Country Planning Act 1990, allowing the council to acquire land by agreement for proper planning [P158].
- s123: Section 123 of the Local Government Act 1972, requiring disposal consideration to be no less than the best reasonably obtainable, subject to Secretary of State consent [P159].
- Plot Proposal: Information about a serviced plot that enables the council to decide whether to invest in that plot [P120].
- Social regeneration charter: A shared document of priorities, jointly adopted and owned by the partnership, with local community involvement throughout its development, delivery and review [P98].