Southwark Great Estates Programme Paper Two - Estate Improvement Plans
AgreedExecutive2 papers
AI summarySouthwark Cabinet agreed estate improvement pilots in the north, south and centre, with £970k identified for 2019/20. [D] [P39] Council leaseholders pay nothing for pilot work, and an evaluation with an action plan is due approximately 12 months after their commencement. [D] [P46]
Written from the decision and the officer reportPDF Pro
OutcomeAgreedThree areas. No charges to council leaseholders for pilots. [D]
Money£970k pilot funding [P39]Identified for 2019/20 pilot improvements. [P39] [P72]
What happens nextEvaluation and action plan [D]Officers report back approximately 12 months after their commencement. [D]
Who it affectsPilot estate residents [P38]Residents help shape communal area improvements. [P26]
What was decided
Cabinet agreed the principles of the Great Estates Programme and approved pilots in the north, south and centre of the borough. Report P2, P3
Council leaseholders will not be charged for Great Estates pilot work. Leaseholders may still be charged for works that fall under existing schemes or plans and did not arise solely because of the pilots. Report P4, P40, P85
Officers must bring an evaluation to Cabinet approximately 12 months after the pilots commence, with an action plan. The Leader delegated final selection of pilot estates to the cabinet member for social regeneration, great estates and new council homes, in consultation with the strategic director of housing and modernisation. Report P7, P44, P46
Why
The plans are intended to improve the look, feel and lived experience of estates while caring for their physical fabric. Residents will agree the plan and have a say in using internal and external resources to improve communal areas. Report P24, P26
The approach is based on residents as equal or principal partners, clear cost information and maximising resident involvement. Report P27, P28, P29, P30
Priority goes to estates with new council homes, wider regeneration opportunities and improvements linked to antisocial behaviour. Selection should balance geography, building type, the issues affecting each estate and investment need. Work addressing antisocial behaviour, gang violence and credible activities for young people will receive priority. Report P31, P32, P33, P34, P42
What happens next
Final pilot estates will be selected following an open call for projects and expressions of interest. Resident consultation is taking place through an online survey and community councils. The £970,000 budget will be allocated to individual schemes after the sites and nature of the works programme are determined. Report P38, P77, P85
The pilots are due to commence by the summer 2019, starting with consultation with residents on each estate. Officers will work closely with residents to guide them through the Estate Improvement Plan process. Report P45
Each pilot will be reviewed after one year and over the next two subsequent years. Officers must bring an evaluation to Cabinet approximately 12 months after their commencement, with an action plan. Findings will be used to update the Great Estates Guide. Report P46, P47
The money
£970k Identified to help fund the pilots in 2019/20. Report P39
£970,000 Specifically budgeted for the pilots and allocated to individual schemes once sites and works are determined. Report P85
£970,000 Identified as a source for a dedicated project manager post. Report P70
Options considered
Chosen: Pilot Estate Improvement Plans in the north, south and centre. This tests the approach with a balanced mix across the borough. Report P3, P38, P42
Rejected: Charge council leaseholders for Great Estates pilot work. The pilots are experimental, so leaseholder charging will not apply. Report P4, P40, P85
Chosen: Use external funding and council grants to supplement pilots. The pilots will test external providers, including Big Lottery, Arts council funding, GLA Grants, United St Saviours Grants and crowdfunding. Council grant programmes could also supplement proposals. Report P37, P60, P61, P62, P63
Rejected: Extend the programme beyond the pilots at this meeting. Any future roll out requires a separate official council decision, with financial implications considered then. Report P74
Implications
Financial: Pilot funding is £970k for 2019/20, and any wider roll out requires a separate council decision with financial implications considered then. Report P39, P74
Financial: Council leaseholders will not pay for pilot work, but normal leaseholder charges will apply beyond the pilot phase under their leases. Report P85
Legal: No legal or further policy implications are recorded at this stage, although legal advice covers consultation and delegated decision making powers. Report P66, P71
Equalities: Cabinet must have due regard to the continuing public sector equality duty as plans develop, and forum membership should be monitored to show genuine representation of diverse communities. Report P68, P81
Staffing: A dedicated project manager is needed because the programme creates significant new work streams, with the post funded from £970,000. Report P70
Risk: Improvement proposals will be coordinated with major works and new homes to avoid later work damaging estate improvements. Report P43
Climate: The housing strategy aims for environmentally and energy efficient new homes and existing homes that keep residents warm, dry and safe. Report P9
Other: New council homes and wider regeneration are intended to bring wider benefits to existing residents, including communal areas and repairs where possible. Report P52, P54
Who and where
Residents on selected pilot estates Report P38, P45
Residents on estates receiving new council homes Report P32, P52
Existing and new residents near regeneration projects Report P54
Residents in council, housing association and private housing Report P9, P57
Young people on estates needing alternatives to antisocial behaviour Report P34, P42
Communities across each pilot estate Report P68
Timeline
early 2018: The Southwark Conversation completed, providing feedback used to develop the emerging programme. Report P76
December 2018: Cabinet agreed the Great Estates vision and approach, including the estate improvement plan approach for new council homes on existing estates. Report P17, P22
29 January 2019: Residents were consulted at the Bermondsey and Rotherhithe Community Council. Report P77
1 March 2019: The final report was dated. Report P91
summer 2019: Pilots were due to commence, starting with consultation with residents. Report P45
approximately 12 months after their commencement: Officers were instructed to bring an evaluation to Cabinet with an action plan. Report P46
one year: Each pilot was due to be reviewed. Report P46
next two subsequent years: Further reviews were planned for each pilot. Report P46
Plain English for the jargon
Great Estates Programme: A programme with a vision and approach, a guarantee and commitments, and Estate Improvement Plans. [P13] [P15] [P16]
Estate Improvement Plan: A resident led plan through which communities agree improvements and help decide how communal resources are used. [P26]
Great Estates Guarantee: A commitment that every estate is clean, safe and cared for. [P11] [P15]
Great Estates Guide: A living document of case studies showing possible improvements, updated using pilot information. [P36] [P47]
Great Estates Advisory Group: A group that advises on delivery and external funding, with resident representatives. [P41] [P78]
Social regeneration: Regeneration intended to benefit both existing and new residents around development projects. [P54]
Individual Decision Making: The route for deciding funding for a particular estate. [P75]
Public sector equality duty: The continuing duty to eliminate discrimination, advance equality of opportunity and foster good relations. [P81]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
Decisions of the Cabinet 1. That the principles of the great estates programme - estate improvement plans be agreed. 2. That the estate improvement plans be piloted in the north, south and centre of the borough. 3. That it be agreed that council leaseholders will not be charged for any great estate pilot work (as set out in paragraph 20 of the report). 4. That officers be instructed to bring back an evaluation of the pilots to cabinet approximately 12 months after their commencement with an action plan. Decision of the Leader of the Council 5. That authority be delegated to the cabinet member for social regeneration, great estates and new council homes in consultation with the strategic director of housing and modernisation to agree the final selection of pilot estates.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 11 pages
Item No. Classification: Date: Meeting Name: 8. Open 12 March 2019 Cabinet
Report title: Southwark Great Estates Programme Paper Two – Estate Improvement Plans
Ward(s) or groups affected: All
Cabinet Member: Councillor Leo Pollak, Social Regeneration, Great Estates and New Council Homes
FOREWORD - COUNCILLOR LEO POLLAK, CABINET MEMBER FOR SOCIAL REGENERATION, GREAT ESTATES AND NEW COUNCIL HOMES
Last December's opening cabinet paper of our 'Great Estates' programme set out the council's fundamental approach to the long-term future of our council estates - to 'expand and enrich' our estates by a) identifying appropriate sites on our estates for building new council homes, and b) finding new ways of working with residents to improve the look, feel and lived experience of our estates.
The 'Estate Improvement Plans' cabinet report focuses on the 'enrich' part of the programme, setting out three principal routes towards improving the shared living experience of our estates, creating new opportunities for residents to come together, and to begin a process of upholding our estates as properly privileged parts of the city.
Firstly, as detailed in the 30 October 2018 New Homes Delivery Model Review cabinet report, we have reoriented how we approach the often challenging task of building new council homes on existing estates, by framing it as part of a wider 'estate improvement plan' approach. This means in practice that resident project groups and architects have a brief beyond the red line of the development plot, to think about how new homes can sit comfortably as part of the existing estate as well as how the process of development can capture wider visible improvements throughout the estate. It also seeks to align the repairs cycle wherever possible to new homes development activity to ensure existing homes are being refurbished and upgraded, and that everyone, not just residents of the new homes, sees an uplift in their living environment. We are already starting to see some of the early fruits of this approach with residents better welcoming development proposals that offer a more tangible account of what’s in it for them.
Secondly, a new strategic policy in the latest adjustments to the New Southwark Plan (SP2: Regeneration that works for all) explicitly commits us to working towards a tenure blind borough, where principles of tenure equality and tenure integration are applied where new private development comes forward adjacent to council estates. This will work by linking private development to proposed estate improvement projects on neighbouring estates, captured through s106, CIL and additional social regeneration commitments.
Thirdly, this report initiates a series of Estate Improvement Plan pilot projects over the coming year, covering all parts of the borough, older and younger estates and estates with or without active resident associations. Via workshops, drop-ins, wish list ballots and other methods of engaging and involving residents, the opening year’s pilots will trial different ways of devising and delivering improvement works on a range blocks and estates with residents at the centre of the process, and a license for creativity and risk-taking. The projects will also seek to maximise resources available by drawing on external funding and partnership opportunities, with a new advisory group helping to frame the process to ensure they have the greatest possible impact.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.