Aylesbury Regeneration Programme Moving Forward

Noted Executive 3 papers

AI summaryLondon Borough of Southwark Cabinet activated Phase 4 pre allocation for social rented homes at the first development site and Plot 18, and required local lettings policies. There are no direct financial implications. [D] [P4] [P5] There are no direct financial implications. [P52]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPre allocation agreed; policies to be drafted. [D]
MoneyNo direct financial implications. [P52]Existing resources cover housing need and pre allocation. [P50]
What happens nextResident consultation and impact assessment. [D]Equalities impact assessments will start at the earliest opportunity. [D]
Who it affectsAylesbury tenants and future residents. [D]Pre allocation offers new social rented homes. [D]

What was decided

Cabinet noted the significant progress made in implementing the Aylesbury regeneration programme. [D] [P2] Report P2

Cabinet agreed to split Phase 4 into subphases. [D] [P3] Phase 4a was activated for pre allocation to new social rented homes at the first development site. [D] [P4] Phase 4 was activated for pre allocation to social rented homes for people over 55 at Plot 18. [D] [P5] Report P3, P4, P5

Cabinet required local lettings policies for both developments. [D] [P5] It noted the proposed extra social rented homes in Phase 2 and the planned early resident consultation and equalities impact assessments. [D] [P6] [P7] Report P5, P6, P7

Why

Phase 4a was the priority for moving households from homes because of stock condition. [P30] The paper expected enough new social rented homes at the first development site for all council secure tenants in Phase 4a. [P30] Early pre allocation would involve future residents in detailed design and help rebuild the community in the new neighbourhood. [P30] [P45] Report P30, P45

Plot 18's over 55s homes need a local lettings plan because the accommodation is specialist and residents have already been consulted. [P35] A community engagement plan, stakeholder consultation and an equalities impact assessment will inform the IDM. [P36] [P37] [P38] [P39] [P40] Report P35, P36, P37, P38, P39, P40

The proposed extra social rented homes in Phase 2 would let most secure tenants in Phases 4b and 4c move to new homes by 2028. [P41] Any revised scheme would be subject to planning and a GLA grant, and would cumulatively have 50% of all homes affordable by habitable room. [P41] A small number may need to move to Phase 3 by 2031. [P41] Report P41

What happens next

Local lettings policies must be drafted for the first development site and Plot 18. [D] [P43] A community engagement plan, stakeholder consultation and an equalities impact assessment will inform the IDM, which will consider the final plans. [P36] [P37] [P38] [P39] [P40] Housing Solutions will coordinate Phase 4a pre allocation, with Resident Services supporting tenant engagement throughout. [P68] Report P36, P37, P38, P39, P40, P43, P68

Phase 4a residents will be contacted about pre allocation to the first development site, and all Phase 4 residents about over 55s housing at Plot 18. [P55] Former secure tenants from the first development site will also be asked about returning, and the consultation findings will inform the equalities impact assessments. [P55] Report P55

Future Cabinet reports will cover starting the CPO process for Phases 2 and 3. [P16] [P17] A further report later this year will set out funding arrangements for independent advice and support to council and temporary accommodation tenants during the rehousing programme. [P19] Report P16, P17, P19

Options considered

  • Chosen: Split Phase 4 into Phase 4a, Phase 4b and Phase 4c. Phase 4a was prioritised based on stock condition, and the remainder was divided into two logical phases. Report P26, P30
  • Chosen: Pre allocate Phase 4a homes at the first development site. Enough new social rented homes were expected for all council secure tenants in Phase 4a, while early allocation would support design and community rebuilding. Report P30, P45
  • Chosen: Pre allocate the whole of Phase 4 for over 55s housing at Plot 18. The accommodation has a specialist nature and residents had already been consulted. Report P35
  • Chosen: Prepare local lettings policies for both developments. Local lettings plans were required for the first development site and Plot 18. Report P35, P43
  • Chosen: Note the proposal for additional social rented homes in Phase 2. Cabinet recorded that the proposal would accelerate the rehousing of secure tenants across the rest of the estate. Report P6
  • Rejected: Require weekly bidding by Phase 4a tenants. Pre allocation removes the need for weekly bidding and was described as straightforward and stress free. Report P70
  • Chosen: Carry out resident consultation and equalities impact assessments. Consultation must occur at a formative stage, and the assessments will support the council's equality duty. Report P48, P64

Implications

  • Financial: The report identifies no direct financial implications. Report P52
  • Financial: Phasing may affect the council's ability to use vacant estate units for temporary accommodation and reduce the high cost of this provision in the general fund. Report P66
  • Staffing: There are no direct resource implications, and existing resources will manage housing need and pre allocation. Report P50
  • Legal: Cabinet must have due regard to eliminating discrimination, advancing equality of opportunity and fostering good relations. Report P58, P59
  • Legal: Consultation must take place while proposals are formative, provide sufficient reasons and time, and have the outcome considered. Report P64
  • Equalities: Equalities impact assessments will examine possible disproportionate effects on residents with protected characteristics and identify mitigation. Report P48
  • Other: Early pre allocation gives secure tenants the option of a social rented home in their neighbourhood and allows future residents to influence detailed design. Report P45
  • Risk: No consultation with Phase 4 residents had taken place before Cabinet approval because the proposals first needed formal approval. Report P55

Who and where

  • Secure tenants and leaseholders in Phase 4a Report P27, P30
  • Secure tenants and leaseholders in Phase 4b Report P28, P30
  • Secure tenants and leaseholders in Phase 4c Report P29, P30
  • Former secure tenants from the first development site who did not move to Phase 1A Report P25, P55
  • Secure tenants, residents in temporary accommodation and leaseholders in Phase 2 Report P16, P47
  • Secure tenants, residents in temporary accommodation and leaseholders in Phase 3 Report P17, P47
  • People seeking social rented homes for over 55s at Plot 18 Report P12, P35
  • The Walworth community and residents in different housing tenures Report P20, P23, P45

Timeline

  • 14 November 2018, mid March and end March 2019: The CPO for the first development site was confirmed. Arrangements were in place for 2 of 3 leaseholders to move by mid March, with vacant possession sought by end March 2019. Report P14
  • July 2019 and 2021/2: Notting Hill Genesis was scheduled to appoint in July 2019, with building works at Plot 18 scheduled to complete in 2021/2. Report P12
  • 2019: Pre allocations were scheduled for Phase 4a to the first development site and Plot 18, Phase 4b to the first development site and Plot 18, and Phase 4c to Plot 18. Report P31, P32
  • 2021/2: Moves to completed first development site and Plot 18 homes were scheduled for all three subphases. Phase 4a leaseholders were also due to move in 2021/2. Report P31, P32
  • 2021 and 2028: Phase 2 was anticipated, subject to CPO, to be vacant in 2021. Most secure tenants in Phases 4b and 4c could move to new Phase 2 homes by 2028. Report P41
  • 2025 and 2029: Pre allocations to Phase 2 were scheduled for Phases 4b and 4c in 2025. Pre allocation to Phase 3 for Phase 4c was scheduled in 2029. Report P31, P32
  • 2027/30, 2029, 2030 and 2031: Moves to completed Phase 2 homes were scheduled for 2027/30. For Phases 4b and 4c, CPO confirmation was scheduled for 2029, demolition for 2030 and new build starts for 2031. Report P31, P32
  • 2022 and 2029/30: Phase 4a CPO confirmation and demolition were scheduled for 2022. The Phase 4a new build was scheduled to start in 2029/30. Report P31

Plain English for the jargon

  • Compulsory Purchase Order (CPO): The process used to secure vacant possession of remaining estate blocks. [P14] [P15]
  • First development site (FDS): The redevelopment site for social rented, intermediate and homes for sale. [P11]
  • IDM: The document that will consider the final local lettings plans. [P40]
  • Tenure blind: Design that lets residents with different housing tenures mix within and between developments. [P23]
  • Equalities impact assessment: An assessment of possible disproportionate effects on residents with protected characteristics and possible mitigation. [P48]
  • Over 55s housing: Specialist social rented accommodation planned at Plot 18. [P35]
  • Homesearch bidding scheme: A registration process that checks occupancy, household composition, medical needs and adaptations. [P33]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

That the significant progress on implementing the Aylesbury regeneration programme be noted. 2. That the sub-phasing of phase 4 be agreed. 3. That phase 4a be activated for pre-allocation to new social rented homes on the first development site. 4. That phase 4 be activated for pre-allocation to the new social rented over 55s housing on Plot 18. 5. That local lettings policies be drafted for the social rented over 55s housing on plot 18 and the social rented housing on the first development site. 6. That the proposed additional delivery of social rented homes in phase 2 which will accelerate the rehousing of secure tenants on the rest of the estate be noted. 7. That it be noted that the resident consultation and equalities impact assessments will be undertaken at the earliest opportunity.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 9 pages

Recommendations

Recommendations for the Cabinet

1. To note the significant progress on implementing the Aylesbury regeneration programme.

2. That the sub-phasing of Phase 4 be agreed.

3. That Phase 4a be activated for pre-allocation to new social rented homes on the first development site.

4. That Phase 4 be activated for pre-allocation to the new social rented over 55s housing on Plot 18. 5. That local lettings policies be drafted for the social rented over 55s housing on Plot 18 and the social rented housing on the first development site.

6. To note the proposed additional delivery of social rented homes in phase 2 which will accelerate the rehousing of secure tenants on the rest of the estate.

7. To note that the resident consultation and equalities impact assessments will be undertaken at the earliest opportunity.

BACKGROUND INFORMATION

Construction progress

8. The construction of the approved premises facility (see Appendix 1) started on site in September 2018. It is currently anticipated that the building works will complete in June 2020 which will allow the current facility at Ellison House to be vacated.

9. The first development site (FDS) (see Appendix 1) is being developed for 287 social rent (managed by Notting Hill Genesis), 54 extra care social rent, 7 Learning Difficulties social rent, 211 intermediate and 283 for sale homes. Arklow, Bradenham and Chartridge (blocks 1-68, 77-105, 69-76 and 104-119) have been demolished. A Section 73 variation to the planning consent was agreed at Planning Committee 6 November 2018. The build contract for the first phase of the development of this site is scheduled to be let by Notting Hill Genesis at the end of March 2019.

10. The development at Plot 18 (see Appendix 1) has planning permission for 17 social rent (over 55s managed by NHG), 6 shared ownership, 99 for sale, library, early years centre, health centre and GP facility. Demolition on the site is complete. The build contract is out to tender. Notting Hill Genesis is scheduled to appoint in July 2019. The building works are scheduled to complete in 2021/2.

Vacant possession

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Plan of development sitesAppendix 1 1 pages Download
PDF
Phase 4 Aylesbury RegenerationAppendix 2 1 pages Download
PDF
Report: Aylesbury Regeneration Programme Moving ForwardReport 9 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 14 attended
PJ
Councillor Peter John OBEChair, present
RL
Councillor Rebecca LuryCommittee Member, present
JA
Councillor Jasmine AliCommittee Member, present
EA
Councillor Evelyn AkotoCommittee Member, present
SC
Councillor Stephanie CryanCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
LP
Councillor Leo PollakCommittee Member, present
JS
Councillor Johnson SituCommittee Member, present
KW
Councillor Kieron WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

All 14 on the meeting page

On this subject at Southwark

Search all
  1. Aylesbury Regeneration Programme Moving ForwardThis decision
  2. Amending the Rehousing Policy for Homeowners affected by the Regeneration of the Aylesbury EstateDecided
  3. Aylesbury Regeneration - Phase 1: sites 7 & 10 Revised Delivery RouteDecided
  4. Aylesbury Regeneration - Next StepsNoted
  5. Gateway 1: Procurement Strategy Approval Aylesbury Regeneration: Development PartnershipApproved
  6. Selection of a Preferred Partner to Work with the Council to Deliver the Regeneration of the Aylesbury EstateApproved

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies