Gateway 1 - Procurement Strategy Approval Main Contractor Procurement: Cator Street 2
ApprovedExecutive1 paper
AI summarySouthwark Cabinet approved a two stage design and build procurement for Cator Street 2, including about 50 extra care homes, a day centre and a community information hub. [D] [P14] The estimated main contract is £19.8m, with a £150,000 pre construction services agreement. [D]
Written from the decision and the officer reportPDF Pro
OutcomeApprovedAbout 50 homes, a day centre and information hub. [P14]
Money£19.8m main contract estimate [D]Pre construction services estimated at £150,000. [D]
What happens nextTwo stage procurement [P27]Award pre construction services, then approve main works. [P36] [P39]
Who it affectsResidents and service users [P14]Extra care homes, day centre and information hub. [P14]
What was decided
Cabinet approved the two stage design and build procurement strategy for Cator Street 2. The estimated contract value is £19.8m for 22 months, commencing in November 2019.
The relevant chief officer will approve the pre construction services agreement award under contract standing orders, with the relevant cabinet member. Report P2
The strategic director of housing and modernisation will make the main works award decision in consultation with the relevant cabinet member. Report P3, P40
Why
Notting Hill Genesis is the fastest procurement route and appears best suited to extra care projects on constrained inner London sites. Report P27
The two stage route lets the council and contractor finalise the design together and test current market prices. It also allows innovation and better construction methods to come early. Report P25
Delegating the main works award allows a quick move from recommendation to award and avoids serious impact on delivery timescales. Report P40
What happens next
Assess framework contractors' previous developments and have the project board confirm at least five tenderers. Report P31
Framework companies will be invited through ProContract. First stage assessment will use a 60:40 price and quality split. Report P64, P66
The relevant chief officer will award the pre construction services agreement after Gateway 2 approval. The council may re-tender if the fixed main works price is unacceptable. Report P2, P36, P39
The money
£19.8m Estimated main works contract value. Report P9, P127
£150,000 Estimated pre construction services agreement award.
£5,159,000 Confirmed Adult Social Care capital funding. Report P115
£3,000,000 Confirmed GLA Homes for Londoners grant. Report P115
12,616,000 Housing and Modernisation capital contribution, still to be confirmed. Report P115, P116
£20,775,000 Total funding listed in the financial table. Report P116
£1 million Contract value supporting each required apprenticeship. Report P98
£100k Cabinet member briefing threshold for this procurement. Report P53
Options considered
Chosen: Two stage design and build. The council and contractor can finalise the design together, with better risk transfer to the contractor. Report P25, P59
Chosen: Notting Hill Genesis framework. It is the fastest route, access is confirmed, and around half of its 23 suppliers have London extra care experience. Report P27, P30, P34
Rejected: Traditional procurement. Market testing suggested contractor input beyond Stage 3 would benefit design. Contractors prefer early engagement. Report P25
Rejected: OJEU procurement using the restricted procedure. The process is lengthy and would delay the start of works on site. Report P24
Rejected: London Development Panel 2 framework. It focuses on developers, creating a risk of little contractor interest. Report P23
Rejected: Do nothing. The council is committed to the project and needs new council homes. Report P20
Implications
Financial: The strategy itself has no direct financial implications. The £19.8m cost is indicative at this stage. Report P114
Financial: The final contract award needs approval of the remaining Housing and Modernisation capital contribution at the next capital refresh. Report P115
Legal: Because the scheme is above the EU works threshold, the full Public Contract Regulations 2015 and Public Sector Directive 2014/24/EU requirements apply. Framework use follows Contract Standing Order 5.1.2. Report P19, P132
Equalities: Officers will conduct an equalities impact assessment during consultation. The contract will comply with section 149 of the Equality Act 2010. Report P86, P99
Climate: Requirements cover energy, carbon, water, flooding and biodiversity, with sustainable materials and waste controls. All homes must meet Code for Sustainable Homes Level 5. Report P103, P104, P105, P107, P108
Risk: Controls include contractor experience review, price and quality assessment, financial checks, project contingency and site investigation. Report P43
Staffing: No TUPE implications are expected, subject to review if a replacement contractor or subcontractor is appointed or work is brought in house. A project manager will oversee the delivery team and programme resourcing. Report P57, P110, P113
Other: The contract must require London Living Wage and one apprenticeship for every £1 million. Apprentices must be paid at least 25% above the National Apprenticeship Wage or higher. Report P90, P97, P98, P129
Who and where
Residents with early onset dementia needing extra care housing Report P6
People living with dementia and frail older people using the day centre Report P5
Residents with severe disabilities needing signposting Report P14
People living, accessing or working near the development Report P83
Older people, minority ethnic groups, faith groups, disabled people and young people Report P84
Service users, affected businesses and internal stakeholders Report P85
Local residents seeking work, and careers participants at local schools Report P96, P97
Framework contractors and their subcontractors Report P29, P90
30/10/2019: Planned Gateway 2 contract award report approval. Report P54
28/11/2019: PCSA award, contract register entry and Contracts Finder notice. Report P55
13/12/2019: Second stage proposal return deadline. Report P55
Feb 2020: Main works contract award and start, with initial completion in Aug 2021. Report P55
Plain English for the jargon
PCSA: Pre construction services agreement for work before the main works award. [P2] [P36] [P37]
NHG: Notting Hill Genesis contractor framework used for this procurement. [P22] [P27]
Gateway 1: Cabinet approval stage for the procurement strategy. [P53] [P132]
Gateway 2: Contract award approval stage for the pre construction services agreement and main works. [P36] [P39] [P40]
MEAT: Most Economically Advantageous Tender protocol used to assess tenders. [P66]
LLW: London Living Wage requirement applying to the successful contractor and, where appropriate, subcontractors. [P90] [P129]
SQ: Standard Questionnaire stage used before direct tendering under a framework. [P27]
ITT: Invitation to tender used for Stage 1 and the second stage proposal. [P53] [P55]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14
Resolved
That the procurement strategy outlined in the report for a two stage design and build contract for the construction of Cator Street 2, comprising of extra care (flexi-care) housing, a day centre and community information hub at an estimated contract value of £19.8m for an anticipated period of 22 months commencing in November 2019 be approved. 2. That it be noted that the award of the pre-construction services agreement (PCSA), for an estimated £150,000, will be approved as set out in paragraph 28 of the report by the relevant chief officer in accordance with contract standing orders and in consultation with the relevant cabinet member. 3. That the delegation of the award decision in the gateway 2 report for the main works contract to the strategic director of housing and modernisation in consultation with the cabinet member for social regeneration, great estates and new council homes for the reasons noted in paragraph 31 of the report be approved.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 18 pages
Recommendations
That Cabinet:
1. Approves the procurement strategy outlined in this report for a two stage design and build contract for the construction of Cator Street 2, comprising of extra care (flexi- care) housing, a day centre and community information hub at an estimated contract value of £19.8m for an anticipated period of 22 months commencing in November 2019. 2. Notes that the award of the Pre-Construction Services Agreement (PCSA), for an estimated £150k, will be approved as set out in paragraph 28 of this report by the relevant chief officer in accordance with contract standing orders and in consultation with the relevant cabinet member.
3. Approves the delegation of the award decision in the Gateway 2 report for the main works contract to the strategic director of housing and modernisation in consultation with the cabinet member for social regeneration, great estates and new council homes for the reasons noted in paragraph 31.
BACKGROUND INFORMATION
4. Cator Street 2 is a proposed second phase of development on the site of the former council learning resource facility on Cator Street. The first phase comprised a new 42-unit extra care facility, Tayo Situ House, procured under Phase 1B Lot 1 of the directly funded housing delivery programme. The same direct delivery programme was also to include a ‘Centre of Excellence’ (a day centre for people living with dementia and the frail elderly) to be accommodated within the existing learning and resources centre, but intrusive structural investigation of the existing building raised concerns over its longevity and suitability for adaptation. Consequently, the existing learning resource centre was declared surplus to requirements and demolished under the Cator Street extra care contract, leaving a cleared site for development.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.