Gateway 1 - Procurement Strategy Approval Main Contractor Procurement: Albion New Homes

Agreed Executive 2 papers

AI summarySouthwark Cabinet approved a two stage Notting Hill Genesis procurement for 76 new homes on the former Albion Civic Centre and Primary School sites [D] [P2] [P15]. The estimated contract value is £22m, including £1.1m for pre construction services [D] [P2].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreed76 homes across two former Albion sites [P15] [P16]
Money£22m estimated contract value [D] [P2]Includes £1.1m for pre construction services [P2]
What happens nextPCSA Gateway 2 approval required [P42]Main works approval delegated, subject to Gateway 2 [D] [P3] [P45]
Who it affectsNot stated

What was decided

Cabinet approved the procurement strategy for a two stage design and build contract through the Notting Hill Genesis framework for the former Albion Civic Centre and former Albion Primary School sites. The anticipated contract period is 32 months commencing on 30 July 2019, with an estimated value of £22m, including £1.1m for the first stage pre construction services agreement. Report P2

The award of the pre construction services agreement will be approved by the relevant chief officer under contract standing orders, with the cabinet member for social regeneration, great estates and new council homes consulted. The Gateway 2 main works award is delegated to the strategic director of housing and modernisation, with the same cabinet member consulted. Report P3

The procurement strategy agreed on 5 October 2015 for lot A2 within the Southwark Regeneration in Partnership Programme did not proceed. The new strategy replaces that original procurement. Report P4

Why

The two sites are being packaged together because they are close and this eases construction logistics. It is expected to save money on preliminaries. Report P7

The November 2017 procurement for lot A2 received no final tenders. The council attributed the lack of interest to poor viability, with 100% affordable units sought at the Civic Centre site and 72.9% at the Primary School site. Report P8, P9

The removal of the housing revenue account cap enabled direct council delivery. The Notting Hill Genesis framework was the fastest route and offered 23 contractors with relevant experience, while planning permission and demolition were expected to attract contractors. Two stage design and build enables early contractor engagement, current market prices, innovation and risk transfer, although the council has less control over the design team. Report P10, P23, P29, P32, P34

What happens next

The project team will complete further design work and procure ground surveys before tender. A capability assessment will support a shortlist of at least five contractors, who will be invited through the council's electronic tender portal, ProContract. Report P35, P38, P68

After assessment, the pre construction services agreement requires Gateway 2 approval. The successful contractor must help develop the design, cost plan, programme and method, obtain subcontractor prices and tender the main work packages. Report P42, P44

The main works price will be considered through a second Gateway 2 report. The council may re-tender if the fixed main works price is not acceptable. Report P45

The money

  • £22m Indicative value of pre construction and construction works Report P2, P119
  • £1.1m Estimated first stage pre construction services agreement Report P2, P133
  • £1 million Contract value requiring one apprenticeship Report P101

Options considered

  • Chosen: Notting Hill Genesis framework. It is the fastest route, has 23 contractors and offers experience with new homes and constrained inner London sites. Report P29, P34
  • Chosen: Two stage design and build. It supports early contractor engagement, current market prices, innovation and risk transfer, although the council has less control over design. Report P32, P44
  • Chosen: Direct council delivery. The housing revenue account cap was removed, and direct delivery was expected to attract contractors because both sites have planning permission and are demolished. Report P10, P23
  • Rejected: OJEU procurement using the restricted procedure. It could provide wider contractor choice and competition, but the longer process would delay site works. Report P31
  • Rejected: Traditional contract. It gives the council more design control, but may attract little interest if design moves beyond Stage 3. Report P32
  • Rejected: London Development Panel 2 framework. It focuses on developers, creating a risk that the schemes would receive little interest. Report P30
  • Rejected: Retender lot A2 to developers. Lot A2 received no final tenders because its affordable housing requirements made viability poor. Report P8, P9
  • Rejected: Do nothing. The council said this was not possible because it is committed to the project and needs to provide new council homes. Report P27

Implications

  • Financial: No direct financial effect arises from approving the strategy. The £22m cost is indicative and is included within the Housing Investment Programme, funded from HRA capital resources including RTB receipts, grants, S106 and borrowing as appropriate. Report P119, P120
  • Legal: Strategic procurement approval is reserved to Cabinet. The procurement must follow the full Public Contract Regulations 2015 and Public Sector Directive 2014/24/EU requirements. Use of NHG can satisfy EU tendering requirements if its processes are followed, and third party framework use is subject to Contract Standing Order 5.1.2. Report P26, P138, P139
  • Risk: Planned tender evaluation uses a 60:40 price and quality split, with price deciding tied top scores. Exploring the social value portal may change the split, with details set out at Gateway 2. Key risks are insufficient contractor interest, weak competition, construction inflation, contractor insolvency and mobilisation delays, with market testing, price and quality assessment, contingency, financial checks and site investigation as controls. Report P48, P70, P73, P84
  • Equalities: Officers will prepare a community impact statement and conduct an equalities impact assessment. The council must have due regard to the Public Sector Equality Duty under section 149 of the Equality Act 2010. Report P90, P104, P141
  • Climate: The contractor must follow London Construction Guide guidance on sustainable materials, recycled content and waste. All homes must meet Code for Sustainable Homes Level 5, and the new national technical standards also apply. Design requirements cover energy efficiency, carbon emissions, water and energy conservation, flooding and biodiversity. Report P108, P109, P110, P112
  • Staffing: A client team will include a quantity surveyor and employer's agent, subject to separate gateway approvals. The project manager will oversee the delivery team. Report P12, P115, P118
  • Other: The contract will require London Living Wage payment where appropriate and one apprenticeship for every £1 million of contract value. The framework also allows local employment and training initiatives. Report P94, P101, P102
  • Legal: No TUPE implications are expected for these new works contracts. The position must be reviewed if the council appoints a replacement contractor, brings the work in house, or a contractor appoints a replacement subcontractor. Report P61

Who and where

  • Southwark residents needing new council homes Report P11, P129
  • People living, accessing or working close to the development Report P87
  • Future occupiers of 39 social rented and 24 intermediate homes Report P16
  • Prospective buyers of 13 private sale homes Report P17, P129
  • Older people, minority ethnic groups, faith groups, disabled people and young people Report P88
  • People with protected characteristics Report P104, P141
  • Service users, internal stakeholders and affected businesses Report P89
  • Potential local residents, apprentices and work placement participants Report P102, P103

Timeline

  • 12/03/2019: Approval of Gateway 1: Procurement strategy report Report P58
  • 04/04/2019: Shortlisting of contractors Report P58
  • 24/05/2019: Closing date for return of tenders Report P58
  • 16/07/2019: Approval of Gateway 2: PCSA Contract Award Report Report P59
  • 30/07/2019: Contract award for PCSA, register entry and award notice Report P59
  • January 2020: Invitation to submit second stage proposal Report P59
  • May 2020: Contract award for Main Works Report P59
  • March 2022: Contract completion date Report P59

Plain English for the jargon

  • Gateway 1: Procurement strategy approval stage [P2] [P139]
  • Gateway 2: Contract award approval stage [P42] [P45]
  • HRA: Housing revenue account [P10]
  • LDP2: London Development Panel 2 [P30]
  • MEAT: Most Economically Advantageous Tender [P70]
  • NHG: Notting Hill Genesis [P2]
  • PCSA: Pre construction services agreement [P2]
  • SRPP: Southwark Regeneration in Partnership Programme [P4]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

That the procurement strategy outlined in the report for a two stage design and build contract through the Notting Hill Genesis (NHG) framework, for the construction of the Albion new homes schemes (consisting of two sites - the former Albion Civic Centre and former Albion Primary School) for an anticipated period of 32 months commencing on 30 July 2019, at an estimated contract value of £22m, which includes the cost of the first stage tender process (pre-construction services agreement - PCSA) at an estimated value of £1.1m be approved. 2. That it be noted that that the award of the pre-construction services agreement (PCSA) will be approved as set out in paragraph 34 of the report by the relevant chief officer in accordance with contract standing orders and in consultation with the cabinet member for social regeneration, great estates and new council homes. 3. That the delegation of the award decision in the gateway 2 reports for the main works contract to the strategic director of housing and modernisation in consultation with the cabinet member for social regeneration, great estates and new council homes for the reasons noted in paragraph 37 of the report be approved. 4. That it be noted that the original procurement strategy agreed by cabinet on 5 October 2015 in relation to these sites, identified as part of lot A2 within the Southwark Regeneration in Partnership Programme (SRPP) did not proceed as further detailed in paragraphs 6 and 7 of the report. Therefore, the recommended procurement strategy outlined in the report will replace the original procurement .
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 19 pages

Recommendations

That the cabinet:

1. Approves the procurement strategy outlined in this report for a two stage design and build contract through the Notting Hill Genesis (NHG) framework, for the construction of the Albion new homes schemes (consisting of two sites - the former Albion Civic Centre and former Albion Primary School) for an anticipated period of 32 months commencing on 30 July 2019, at an estimated contract value of £22m, which includes the cost of the first stage tender process (pre-construction services agreement - PCSA) at an estimated value of £1.1m

2. Notes that the award of the PCSA will be approved as set out in paragraph 34 by the relevant chief officer in accordance with contract standing orders and in consultation with the cabinet member for social regeneration, great estates and new council homes. 3. Approves the delegation of the award decision in the Gateway 2 reports for the main works contract to the strategic director of housing and modernisation in consultation with the cabinet member for social regeneration, great estates and new council homes for the reasons noted in paragraph 37.

4. Notes that the original procurement strategy agreed by cabinet on 5 October 2015 in relation to these sites, identified as part of lot A2 within the Southwark Regeneration in Partnership Programme (SRPP) did not proceed as further detailed in paragraphs 6 and 7 of this report. Therefore, the recommended procurement strategy outlined in this report will replace the original procurement.

BACKGROUND INFORMATION

5. On 27 January 2015 the cabinet agreed the Southwark Regeneration in Partnership Programme (SRPP). The programme identified a number of council owned sites which had development potential. On 20 October 2015, cabinet agreed that the sites be packaged into two lots that allowed for a more manageable delivery for their development. Each site varied and presented an individual opportunity, which included mixed uses e.g. housing, commercial and education. It was envisioned that values would be realised for these assets by leveraging the investment and expertise of established developers through a joint partnership.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Site layout plansAppendix 1 4 pages Download
PDF
Report: Gateway 1: Procurement Strategy Approval Main Contractor Procurement: Albion New HomesReport 19 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 14 attended
PJ
Councillor Peter John OBEChair, present
RL
Councillor Rebecca LuryCommittee Member, present
JA
Councillor Jasmine AliCommittee Member, present
EA
Councillor Evelyn AkotoCommittee Member, present
SC
Councillor Stephanie CryanCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
LP
Councillor Leo PollakCommittee Member, present
JS
Councillor Johnson SituCommittee Member, present
KW
Councillor Kieron WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

All 14 on the meeting page

On this subject at Southwark

Search all
  1. Gateway 1 - Procurement Strategy Approval Main Contractor Procurement: Albion New HomesThis decision
  2. Gateway 1 – Procurement Strategy Approval -The NestApproved
  3. Gateway 1 - Procurement Strategy Approval - Southwark and Lambeth Barristers FrameworkApproved
  4. Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking ServicesApproved
  5. Gateway 2: Contract Award Approval - Corporate Insurance Procurement (excluding Property Insurance)Approved
  6. Gateway 1 - Initial Procurement Strategy, Parking and Traffic Enforcement Services ContractAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open