Gateway 2: Contract Award Approval - Southwark Solicitors Framework
NotedExecutive2 papers
AI summarySouthwark Cabinet approved a four year framework for external legal advice from 23 July 2018. [D] [P5] Southwark’s estimated spend is £9 million, with £2.25 million annually and a £25 million maximum if all participating organisations use it. [D]
Written from the decision and the officer reportPDF Pro
OutcomeNotedAward covers providers listed in Appendix 1. [D]
Money£9 million estimated council spend [D]£2.25 million estimated annual spend. [D]
What happens nextContract starts 23 July 2018 [P8]Award notices were due on 26/07/2018. [P8]
Who it affectsSouthwark and eligible London bodies [P6]Service departments will fund their own legal advice. [P99]
What was decided
Cabinet noted the changes to the evaluation criteria. [D] Report P1
The award was approved for the providers in Appendix 1 for four years from 23 July 2018. Its maximum value is £25 million if all organisations in paragraph 5, including Southwark, use it. [D] Report P2
Southwark’s use was approved at an estimated total spend of £9 million for the four year period, with estimated annual spend of £2.25 million. [D] Report P3
Why
The framework supplies specialist external legal support when the in house team lacks capacity or experience. It replaces the expired London Borough Legal Alliance Framework, which did not fully cover Southwark’s commissioning needs. [P5] Report P5
Competitive fixed rates and quality assured legal services are intended to secure value for money. Panel firms have also offered community benefits, including pro bono advice and school presentations. [P11] [P19] [P84] Report P11, P19, P84
Evaluation weightings were revised after August 2017 feedback to provide a better basis for each lot. The aim was to ensure the required expertise and specialism at acceptable cost. [P38] [P39] [P40] Report P38, P39, P40
What happens next
The timetable set contract award for 17/07/2018, contract start for 23/07/2018 and completion for 22/07/2022. [P8] Report P8
Transition will be gradual. New matters will use the new framework, while existing instructions finish under the previous arrangements. [P70] Report P70
Contract performance will be reviewed every 6 months. A six monthly report will go to the Departmental Contract Review Board, with an annual report to the Corporate Contract Review Board. [P43] [P45] Report P43, P45
The money
£25 million Maximum framework value if all organisations in paragraph 5 use it. Report P2
£9 million Estimated Southwark spend over the four year period. Report P3, P104
£2.25 million Estimated annual Southwark spend. Report P3
up to £7,000 Joining fee, depending on the number of panels used. Report P6, P101
approximately £30,000 External project manager fee for the end to end project lifecycle. Report P100
over £100k Briefing threshold for the relevant cabinet member. Report P8
Options considered
Chosen: Use a four year Southwark Solicitors’ Framework. It provides specialist support where in house capacity or experience is insufficient and replaces the expired previous arrangement. Report P5
Rejected: Continue using only the London Borough Legal Alliance Framework. It had expired and did not fully cover Southwark’s commissioning requirements. Report P5
Chosen: Divide the framework into three lots. The structure covers complex, general and routine or predictable legal work. Report P12, P13, P14, P15
Chosen: Use direct award call offs. A single provider may be approached only where it is shown to be the most economically advantageous solution. Report P67
Chosen: Use further competition call offs. Relevant panel firms can enter a mini competition to determine the most economically advantageous solution. Report P68
Implications
Financial: Service departments must agree and meet legal costs when advice is needed, within their legal budgets. Monitoring costs will come from Southwark’s legal services budget. [P99] [P100] Report P99, P100
Financial: Framework rates are fixed for four years and are not index linked. Benchmarked rates were lower than non framework rates in all cases, with some discounts above 40%. [P102] [P103] Report P102, P103
Legal: The procurement followed the approved EU restricted procedure under the light touch regime. Call offs may use direct award or further competition, subject to value for money tests. [P5] [P67] [P68] [P113] Report P5, P67, P68, P113
Risk: The framework may not cover every area or have enough expertise. This risk is rated low, with consultation and relevant tender questions used as controls. [P80] Report P80
Risk: The highest spending services may not use the framework, and rates may be higher than under the previous arrangement. These risks are rated low and medium respectively, with director approval for qualifying departures and competitive procurement as mitigation. [P80] [P81] Report P80, P81
Equalities: All service providers are regulated by the Law Society’s code on equalities and must comply with equalities legislation. Relevant panel staff must be paid at or above the London Living Wage rate. [P86] [P92] Report P86, P92
Climate: The report identifies no specific environmental or sustainability consideration for the framework. [P94] Report P94
Staffing: The framework is unlikely to cause TUPE or other staffing or pension implications. Panel firms must provide free training, and staff secondments are possible. [P98] [P11] Report P98, P11
Who and where
Southwark Council’s service departments Report P99
Southwark’s in house legal services team and client departments Report P11, P72
External solicitors appointed to the panels Report P66, P72
Other London boroughs and their wholly owned companies Report P6
14/05/2018 and 24/05/2018: Departmental and Corporate Contract Review Board reviews held. Report P8
26/06/2018: Gateway 2 contract award approval scheduled. Report P8
17/07/2018, 23/07/2018 and 26/07/2018: Contract award, contract start and award notice publication scheduled. Report P8
22/07/2022: Contract completion date. Report P8
Plain English for the jargon
Gateway 1: The approval stage for the procurement strategy. [P5]
Gateway 2: The approval stage for awarding the contract. [P7] [P8]
Framework: A purchasing arrangement with two call off routes: direct award and further competition. [P66] [P67] [P68]
Lot: A panel for a defined legal service area. [P12]
Light touch procurement: A flexible tender process subject to published notice, equal treatment, transparency and reasonable time limits. [P119]
LLW: London Living Wage. [P92]
Soft benefits: Community support offered by panel firms, including pro bono advice and school presentations. [P84] [P85]
TUPE: Staffing or pension implications considered unlikely because advice follows individual instructions of work. [P98]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13
Resolved
That it be noted that the evaluation criteria were amended for the reasons set out in paragraphs 27-28 of the report. 2. That the award of the Southwark Solicitors’ Framework to the providers listed in Appendix 1 of the report for a period of four years commencing on 23 July 2018 with a maximum value of £25 million if used by all the organisations mentioned in paragraph 5 of the report including Southwark be approved. 3. That Southwark’s use of this framework at an estimated total spend of £9 million for the four year period with an estimated annual spend of £2.25 million be approved.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 14 pages
Recommendations
1. That cabinet notes the evaluation criteria were amended for the reasons set out in paragraphs 27-28 of this report.
2. That cabinet approves the award of the Southwark Solicitors’ Framework to the providers listed in Appendix 1 (attached to this report) for a period of four years commencing on 23 July 2018 with a maximum value of £25 million if used by all the organisations mentioned in paragraph 5 of this report including Southwark.
3. That cabinet approves Southwark’s use of this framework at an estimated total spend of £9 million for the 4 year period with an estimated annual spend of £2.25 million.
BACKGROUND INFORMATION
4. The planned procurement strategy was the subject of a Gateway 1 report which was approved by cabinet on 18 July 2017. The approved EU restricted procedure procurement route was followed. 5. The framework will provide specialist legal services for those circumstances where an external solicitor is required and the service cannot be provided by the in-house legal services team due to a lack of capacity or experience, such as the framework makes provision for legal advice for complex matters across a range of areas including Property and Regeneration, Commercial Contracts and Procurement, Commercial Litigation, General Litigation, Housing, Health and Social Care/Social Care Litigation, Employment, Governance and Public Law, Education, Debt Recovery and Residential Conveyancing. The Southwark Solicitors Framework will replace the previous expired arrangement with the London Borough Legal Alliance Framework (LBLA) which did not fully cover Southwark’s commissioning requirements in this area.
6. The framework is open to all London boroughs, their wholly owned companies, London CCGs, London fire services, London Councils and the Local Government Association. In order to access the framework, the aforementioned organisations will be required to enter into an access agreement with Southwark and pay a joining fee of up to £7,000 depending on the number of panels that they wish use.
Procurement project plan (Key Decision)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.