Policy and Resources: Out-turn capital monitoring report 2025-26
NotedExecutive6 papers
AI summarySouthwark Executive noted the 2025-26 capital outturn: £198.4m Housing Investment Programme spend and £111.8m General Fund spend, with £313.7m and £332.2m borrowing to be drawn over the remaining programme term. Variations and virements were approved.
Written from the decision and the officer reportPDF Pro
OutcomeNotedThree points noted, one recommendation approved
Money£198.4m HIP, £111.8m General Fund2025-26 outturn capital spend in each programme
What happens nextInclude approved virements in capital programmeFormal alignment of budgets to live schemes
Who it affectsBorough residents, tenants, schools, servicesHousing, schools, IT, climate and leisure projects
What was decided
The Executive noted the 2025-26 outturn and ten year capital programme forecasts for the General Fund and Housing Investment Programme. Report P1
The Executive noted borrowing requirements of £313.7m for the General Fund and £332.2m for the Housing Investment Programme, to be fully delivered over the remaining term. Report P2, P29, P27
The Executive approved variations and virements to the General Fund and Housing Investment Programme capital budgets as set out in Appendix 5. Report P2, P42, P43
Why
The capital programme totals £1.8bn over the ten years to 2034-35, with unavoidable variations against planned spend caused by project slippage and changing funding flows. Report P8, P9
Housing Investment Programme outturn was £31.4m below the month 6 forecast, largely due to reprofiled Tustin Phase 2 spend, with slippage expected to be largely recovered in 2026/27. Report P18
What happens next
Approved virements and variations will be included in the capital programme to align budgets with the correct live schemes and funding lines. Report P6, P43, P45
Slippage in the New Homes and General Fund programmes is expected to be largely recovered during 2026-27, with closer monitoring introduced in 2026-27 to strengthen forecasting. Report P18, P40
Officers will continue to monitor inflation, interest rates, and global market conditions to maintain affordable borrowing within the Prudential Indicators. Report P28, P50
The money
£1.8bn Total ten year capital programme to 2034-35, comprising £1.3bn HIP and £479m General Fund Report P8
£68.0m Borrowed share of General Fund outturn (61%) Report P48
Options considered
Chosen: Approve the variations and virements in Appendix 5. Aligns budgets to live schemes without increasing total programme spend and follows established governance routes Report P43, P45, P47
Rejected: Consider alternative options. None considered, as this is the 2025-26 capital outturn report Report P3, P4
Implications
Financial: Construction cost inflation, supply chain volatility, and higher PWLB rates raise the cost of borrowing, requiring careful management of the Minimum Revenue Provision and Prudential Indicators. Report P19, P20, P21, P49, P50
Risk: Global geopolitical instability, including the conflict in the Middle East, is driving volatility in energy markets, material costs, and contractor capacity, risking further slippage and scheme cost increases. Report P20, P21
Legal: Section 28 of the Local Government Act 2003 requires the council to monitor its budgets and take action to address deterioration. Decisions on capital virements over £1m sit with the Executive under the constitution. Report P59, P60, P61
Equalities: The public sector equality duty under section 149 of the Equality Act 2010 applies, although this outturn report is judged to have no direct impact on local people and communities. Report P52, P62, P63, P64, P65, P66
Climate: The report includes climate change programme updates; impacts of individual projects will be assessed through subsequent decision making and procurement. Report P53, P54
Who and where
Council housing tenants and applicants for new council homes Report P17, P18
Residents and users of parks, streets, leisure, and climate programmes in the borough Report P40
Children and adults using schools and social services, including pupils at Beormund, Ivydale, Comber Grove and Highshore Report P36
Schools receiving Devolved Formula Capital grants Report P37
Visitors, businesses, and people who live, learn and do business in the borough Report P8
Timeline
2025-26: Housing Investment Programme outturn of £198.4m and General Fund outturn of £111.8m reported Report P18, P25, P30, P35
March 2026: Over 3,200 new council homes delivered, including 333 completed during 2025-26 Report P17
2026/27: Most programme slippage expected to be largely recovered, with stronger monitoring of environment schemes Report P18, P40
2025-26 to 2034-35: Ten year capital programme of £1.8bn, with £313.7m General Fund and £332.2m HIP borrowing Report P8, P27, P29, P33
8 July 2026: Final report sent to the Constitutional Team Report P71
Plain English for the jargon
CIL: Community Infrastructure Levy, a charge on development used to fund infrastructure
CERA: Capital Expenditure charged to the Revenue Account
DFC: Devolved Formula Capital, a Department for Education grant passed to maintained schools
HIP: Housing Investment Programme, the council's housing capital programme
LAHF: Local Authority Housing Fund, used to buy back properties for temporary housing
MRP: Minimum Revenue Provision, the annual charge to revenue for repaying historic borrowing
NCIL: Neighbourhood Community Infrastructure Levy, a share of CIL for local priorities
PPM: Planned Preventative Maintenance, routine capital upkeep of buildings
PSTN: Public Switched Telephone Network, the analogue telephone system being replaced with digital
PWLB: Public Works Loan Board, a government body that lends to local authorities
s106: Section 106 planning obligations, contributions from developers towards infrastructure
SEND: Special Educational Needs and Disabilities
Virement: Transfer of budget between headings within the approved capital programme
Variation: Change to the overall capital programme, usually from new external funding or developer contributions
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
That the following recommendations be noted: 1. The outturn 2025-26 and financing for the general fund and the housing investment programme (HIP), together with the ten-year capital programme forecasts. 2. The borrowing requirement of £313.7m for the general fund to be fully delivered over the remaining term of the programme, as detailed in Table 2 and Appendix 1 of the report. 3. The borrowing requirement of £332.2m for the HIP to be fully delivered over the remaining term of the programme, as detailed in Appendix 4 of the report. That the following recommendation be approved: 4. The variations and virements to the general fund and housing investment programme (hip) (capital programme as detailed in Appendix 5 of the report.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
5. Executive is asked to note the capital outturn position for the General Fund and the Housing Investment Programme.
6. Executive is asked to approve the virements and variations to the General Fund and Housing Investment Programme.
ALTERNATIVE OPTIONS CONSIDERED AND NOT RECOMMENDED
7. None considered as this is a capital outturn report for 2025-26.
POST DECISION IMPLEMENTATION
8. For the approved virements and variations to be included in the capital programme.
BACKGROUND INFORMATION
9. The scale of the capital programme is immense, representing a major element of the council’s financial activities. It has a significant and very visible impact on the borough and hence on the lives of those who live, learn, visit and do business in the borough. Housing Investment Programme (HIP) spend is estimated at £1.3bn over the 10 year period to 2034-35 and the General Fund £479m – total of £1.8bn.
10. Due to the size and scale of the programme and the number of projects involved, it is inevitable that unforeseeable delays can occur which lead to some variations against planned spend. Actual resources may also vary to the plan, due to, for example, a delay in the sale of a property, or an external development with s106 or Community Infrastructure Levy (CIL) obligations not being brought forward as quickly as anticipated.
KEY ISSUES FOR CONSIDERATION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Gateway 1 - Highway works contractThat the procurement strategy outlined in the report for the provision of Highways Works be approved, comprising: · L...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.