That the revised list of Surrey County Council Major Schemes be endorsed and that this change to the Major Schemes programme in the Local Transport Plan be referred to the Council, as set out in Annexes 1 and 2. 2. That the choice of Major Schemes to be progressed in any given year to be taken by the Strategic Director Environment and Infrastructure in consultation with the Cabinet Member for Transport and Environment . 3. That the “New Homes Bonus” funding be used to provide for that proportion of the preparatory work relating to the schemes, which is not recoverable from capital funding. The estimated cost of this for the 2012-15 period is c. £1.2m. 4. That the Cabinet be provided with a high-level update on the Major Schemes programme every 2 years, except where significant developments require immediate referral. 5. That support continues to be given to Highways Agency (HA) and National Rail (NR) schemes in Surrey detailed in their programmes, set out in Annex 3 of the submitted report. 6. Delegated authority be given to the Strategic Director for Environment and Infrastructure in consultation with the Leader and Cabinet Member for Transport and Environment to approve changes to the list of schemes where these are individually valued at less than £5 million. Reason for Decisions The programme has been designed primarily to support economic growth and regeneration in Surrey , in partnership with district and borough councils . However, schemes will also be consistent, where applicable with other objectives in the Surrey Local Transport Plan. [The decisions on this item can be called in by the Environment and Transport Select Committee]
Word for word from the decision Surrey published for this meeting.Source: mycouncil.surreycc.gov.uk
REPORT OF: MR JOHN FUREY, CABINET MEMBER FOR TRANSPORT AND ENVIRONMENT
LEAD MR TREVOR PUGH, STRATEGIC DIRECTOR, ENVIRONMENT OFFICER: AND INFRASTRUCTURE
SUBJECT: SUPPORTING THE ECONOMY THROUGH INVESTMENT IN TRANSPORT INFRASTRUCTURE 2012 - 19
SUMMARY OF ISSUE: Improving transport infrastructure to address congestion is an important priority for businesses and residents. Preparing infrastructure schemes that address this, so that they are ready to be submitted for funding opportunities, is an important way that the County Council can promote growth in the Surrey economy ie developing so- called "shovel -ready" schemes. Building on the council's success in attracting c. £20m of funding through the Local Sustainable Transport Fund, this report sets out proposals for developing up to 16 schemes for bidding. The Government has released a number of new funding and financing sources to facilitate the development of major transport infrastructure, in particular those supporting the economy. This includes the Growing Places funding provided to Local Enterprise Partnerships (LEPs) and most recently, financing expected to become available through the Local Transport Bodies (LTBs) yet to be set up. This is expected to amount to £7 – 10m per annum for Surrey, based on a per capita share. This paper seeks endorsement: (a) for the preparatory work required to enable Surrey County Council to bid for all new funding sources to deliver major transport infrastructure, and (b) for the list of Major Schemes. The Government is intending to delegate funding of these schemes to new LTBs to be set up broadly within each LEP geography. There is a tight timetable for this process. Submissions for funding are expected to commence from April 2013 and schemes will need to be fully developed subsequently to the Business Case stage to qualify for funding. A delivery pipeline for a programme of fully worked-up schemes will be developed to shorten the time to delivery from whatever funding source. The paper summarises the various schemes being proposed as the new Major Schemes programme. This includes some new schemes that have been proposed by district and borough councils, to tackle key areas of congestion on our transport network, including several town centres. The report re-prioritises the previous list of proposed schemes to be in line with the Government's proposed funding regime and to more accurately meet current and anticipated needs. Through the Surrey Future programme of work with partners, we will be developing a strategy to tackle congestion that will include 3 elements: small local schemes, medium sized schemes such as the ones proposed for preparation in this report and larger and more transformational schemes that will need other funding mechanisms.
1 Page 403 RECOMMENDATIONS: It is recommended that: 1. The revised list of Surrey County Council Major Schemes is endorsed. This change to the Major Schemes programme in the Local Transport Plan is referred to the Council.
2. The choice of Major Schemes to be progressed in any given year to be taken by the Strategic Director Environment and Infrastructure in consultation with the Cabinet Member for Transport and Environment.
3. “New Homes Bonus” funding is used to provide for that proportion of the preparatory work relating to the schemes, which is not recoverable from capital funding. The estimated cost of this for the 2012-15 period is c. £1.2m.
4. The Cabinet is provided with a high-level update on the Major Schemes programme every 2 years, except where significant developments require immediate referral.
5. Support continues to be given to Highways Agency (HA) and National Rail (NR) schemes in Surrey detailed in their programmes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.