East Surrey Grounds Maintenance Contract for Schools and other Surrey County Council Properties

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 27 November 2012. Below is the council's own wording, with the papers it was decided on.

Item172/12

Resolved

That following consideration of the results of the procurement process, set out in item 21, the award of a contract be agreed on the basis, as set out in the Part 2 Annex. Reasons for Decisions The existing contracts will expire on 31 December 2012, a waiver has been agreed by PRG number WR0590 (8/8/12) to extend existing contract arrangements for one month until 31 January 2013 to allow for adequate ‘start up’ processes to be ready. A full tender process, in compliance with the requirement of EU Procurement Legislation and Procurement Standing Orders has been completed, and the recommendations provide best value for money for the Council following a thorough evaluation process. [The decisions on this item can be called in by the Council Overview and Scrutiny Committee]
Word for word from the decision Surrey published for this meeting. Source: mycouncil.surreycc.gov.uk

Follow this further

Built from Surrey's papers

What the report saysPro

Report to Cabinet

Recommendations

It is recommended that following consideration of the results of the procurement process in Part 2 of the meeting (as required), the award of a contract be agreed on the basis set out in the Part 2 Annex (circulated to Members) be agreed.

Reason for recommendations

The existing contracts will expire on 31 December 2012, a waiver has been agreed by PRG number WR0590 (8/8/12) to extend existing contract arrangements for one month until 31 January 2013 to allow for adequate ‘start up’ processes to be ready. A full tender process, in compliance with the requirement of EU Procurement Legislation and Procurement Standing Orders has been completed, and the recommendations provide best value for money for the Council following a thorough evaluation process.

Page 463 DETAILS:

1. This report recommends that a contract for the provision of Grounds Maintenance for Schools and other SCC Properties to commence on 1 February 2013 is awarded to the suppliers named in the Part 2 Annex (circulated separately to Members). Together with the Part 2 Annex, this report demonstrates why the recommended contract award delivers best value for money for Surrey County Council.

Background and options considered

2. The expiry of existing contracts and the essential need to have well maintained School and Surrey CC properties requires this contract to be renewed via a competitive tender exercise. Well maintained School and Surrey County Council properties rank high in the general public’s perception of Local Authority value for money. Maintained and prepared School grounds are an essential requirement for the Schools to deliver the National Curriculum as laid down by the Department for Education e.g sports pitches prepared and athletic facilities maintained.

3. The existing contracts for the provision of Grounds Maintenance for Schools and SCC Properties will expire on 31 December 2012. There is no existing or comparable contract for the provision of Grounds Maintenance. A full tender process, compliant with the European Public Procurement Regulations and Procurement Standing Orders, has been carried out following the receipt of authority from Procurement Review Group (PRG) on 8 August 2012. This included advertising the contract opportunity on the Bravo Solutions SCC portal on 13 August 2012.

4. This East Surrey contract comprises of the following six Boroughs and Districts split into contract lots: Spelthorne; Elmbridge; Epsom and Ewell; Mole Valley; Reigate and Banstead; and Tandridge. It will complement the West Surrey contracts let in 2010 which encompasses the remaining Districts and Boroughs.

Procurement Strategy

5. Several options were considered when completing the Strategic Procurement Plan (SPP) prior to commencing the procurement activity including SCC procuring and managing the contract versus Babcock entering into direct arrangements with schools.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
East Surrey Grounds Maintenance Contract for Schools and other Surrey County Council PropertiesReport 64 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
DH
Mr David HodgeChairman, present
PM
Mr Peter MartinVice-Chairman, present
MA
Mrs Mary AngellCommittee Member, apologies
HC
Helyn ClackCommittee Member, present
JF
John FureyCommittee Member, present
MG
Mr Michael GoslingCommittee Member, present
KH
Mrs Kay HammondCommittee Member, present
LK
Mrs Linda KemenyCommittee Member, present
DL
Ms Denise Le GalCommittee Member, present
TS
Tony SamuelsCommittee Member, present

On this subject at Surrey

Search all
  1. East Surrey Grounds Maintenance Contract for Schools and other Surrey County Council PropertiesThis decision
  2. Interim statutory officer designations for east surrey shadow authorityApproved

More from Surrey Cabinet

All decisions
MeetingDecisionOutcome
27 Nov 2012 Members' QuestionsSix Members questions and their responses are attached as Appendix 1. Decided Open
27 Nov 2012 Public QuestionsSix questions from members of the public and the responses were tabled (Appendix 2) Decided Open
27 Nov 2012 Communities Select Committee Call-in - Magna Carta 800th Anniversary CelebrationsConfirmed the decision made at Cabinet on 23 October 2012. Reasons for Decision This is an in principle decision, whi... Decided Open
27 Nov 2012 School Organisation PlanThat the 2012 – 22 be approved for recommendation to Council. Reasons for Decisions The is a key contextual document ... Approved Open
27 Nov 2012 Public Value Review Programme Closing ReportThat the achievements delivered through the Public Value Review Programme be acknowledged. 2. That officers, Members ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies