(i) To agree to procure and build the Centre on the site identified and agree the facilities and functionality contained within the scheme; (ii) To agree to relocate the entire Ridge Road Library operation into the new centre; (iii) To agree funding of £3m from the capital budget and that the capital receipt from the sale of the Ridge Road Library site be assigned to the project; (iv) To agree to underwrite a further £1.3m of capital at this time, to enable the project to progress, with the expectation of recovery of at least this sum from external sources; (v) To agree the feasibility study, its findings and conclusions as a robust and valid rationale for the above decisions; (vi) To note that related business consideration, such as the possible temporary provision of a youth facility, broader public consultation and the agreement of a procurement strategy, will need to be actioned separately to this report; (vii) To agree that a competition be arranged in the borough to choose the name of the new Centre.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report of the Head of the Safer Sutton Partnership
PRESENTATION OF FEASIBILITY STUDY FOR THE CITIZENSHIP AND SAFETY CENTRE
Ward Location: N/A Author(s) and Contact Phone Number(s): Warren Shadbolt 0208 649 0601 Area Served: Borough wide Executive Councillor: Graham Tope
Key Decision Report
Summary This report establishes the background to the proposed development of a multi purpose Citizenship and Safety Centre in Sutton; “The Campus” (a working title that will change post feasibility). The centre will incorporate a Lifeskills and Safety Centre, a Library, a Youth Zone and several community and training rooms. The Campus will also include a café and will be serviced by a central management team. The report explains the concept for the Campus, the development work that has taken place so far, the key points in the feasibility study, and the recommendations for progressing the project. The report shows that the Campus would be a nationally unique landmark facility that is both financially viable and likely to attract interest and visitors from within and outside of the borough. Recommendations. This report recommends that the Executive Committee: 1 Agree to procure and build the Centre on the site identified and agree the facilities and functionality contained within the centre. 2.i Agree to relocate the Ridge Road Library operation in its entirety into the new centre. 2.ii Agree funding of £3m from the capital budget, and the receipt of capital from the Ridge Road Library site (est £1m) be assigned to the project. 2.iii Agree to underwrite a further £1.3m of capital at this time, to enable the project to progress, with an expectation of recovery of at least this sum from external sources. 3 Agree the feasibility study, its findings and conclusions as a robust and valid rationale for the above decisions. Agenda Item 10 Page 196
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Domestic Violence - Strategic Options(i) That the proposals set out in paragraphs 4 to 6 in the report be endorsed; (ii) To agree to forward the report to...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies