To note Councillor Dunlop’s comments and agree: (i) to authorise an amendment to the contract with Steria that amends the technical solution and the locations of the proposed data centres and the related network connections; (ii) to THUS being the new third party involved with the provision of the Data Centres, on the terms reported; (iii) To a rescheduling of the planned implementation date from 1 October to 1 December 2007.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
The revised data centre proposals have been developed to provide enhanced disaster recovery resilience, in particular making this available if required for all Unix based systems and implementing this for the PARIS Social Services system from day one.
The revised proposal also provides greater network capacity, increasing the original 20 megabytes capacity to a ring network with at least 100 megabytes, and up to 200 megabytes. This will provide greater flexibility if the demand placed on the network through a growth in graphic intensive applications such as document management takes place.
The revised solution offers greater resilience in both the services available at the backup data centre and the network capacity and resilience. Agenda Item 17 Page 580
MATTERS TAKEN INTO CONSIDERATION Including policies complied with/policy implications, legal/personnel issues.
The alternative proposal increases the managed services contract fee by £9,700 per annum. The additional disaster recovery facilities and service continuity resilience it offers provide significant benefits to the Council.
The impact of this proposal has led to a delay in commencing some key talks in the project plan, in particular ordering some of the equipment and installing the servers and network links. This follows on from the delay in signing the contract, which was originally expected in January, but took place in March.
This has allowed more time to work through the project plan, and to scope and agree the detailed activities required within the Council, the plan has not come to a halt. We believe that rescheduling the service commencement date now by 2 months poses least risk to the overall project, and allows both parties sufficient time to complete their respective tasks.
Financial implications
The additional cost of £9,700 per annum represents an increase in the managed services fee of just over half of one percent. This additional cost can be contained within the general ICT development provision of £25,000 within 2007/08 revenue estimates.
Delays to the start of the contract will result in increased charges of between £5,051 and £7,302 in 2007/8 (subject to any further change controls agreed to the existing contract between now and the new start date). This is because the current monthly charges (which vary slightly each month) are higher than the agreed charges for the first year of the contract. Those lower charges would commence in December 2007 and be split 4 months in 2007/8 and 8 months in 2008/9 instead of 6 months in each year. This small increase in 2007/08 will be contained within existing overall ICT estimates.
Agreed by (group accountant)…Steve Robinson….…Date…06/06/2007
Background papers
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Domestic Violence - Strategic Options(i) That the proposals set out in paragraphs 4 to 6 in the report be endorsed; (ii) To agree to forward the report to...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.