(i) To approve the development of a Step 1 Area Based Scheme form and submission to Transport for London, seeking initial funding for the proposed Benhill Recreation Ground Area Based Scheme Streets-for-People project, subject to confirmation by the appropriate Local Committee; (ii) To approve the development of a Step 2 Area Based Scheme Station Access bid documents and submission to TfL to seek additional project funding for the Hackbridge Station and Wallington Station Access Schemes; (iii) To approve the further investigation and possible development of a ‘DIY Streets’ project for Wood Street, Beddington Corner, including undertaking any public consultation, and entering into a legal agreement with TfL/Sustrans, subject to confirmation by the appropriate Local Committee.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
London Borough of Sutton The Executive –9 July 2007
Report of the Executive Head of Planning, Transport and Highways
Proposed Home Zone Type Developments – Area Based Schemes and DIY Streets
Ward Location: Borough-wide Author(s) and Contact Phone Number(s): Tim Hogan ext. 6432
Area Served: Borough-wide Executive Member: Cllr Colin Hall
Executive Decision Report Summary The Report outlines the various ‘Home Zone’ style projects that could be implemented at various locations in Sutton, where the Council has been working in partnership with Transport for London and Sustrans, and seeks approval to develop these projects further.
Recommendations I recommend The Executive: (i) approve the development of a step 1 area based scheme form and submission to TfL seeking initial funding for the proposed Benhill Recreation Ground Area Based Scheme Streets for People project, subject to confirmation by the Local Committee. (ii) approve the development of step 2 Area Based Scheme Station Access bid documents and submission to TfL to seek additional project funding for the Hackbridge Station and Wallington Station Access schemes, (iii) approve the further investigation and possible development of a ‘DIY Streets’ project for Wood Street, Beddington Corner, including undertaking any public consultation, and entering a legal agreement with TfL/Sustrans, subject to confirmation by the Local Committee.
1. Background 1.1 Home Zones are residential streets designed and managed to allow people to share former carriageways and pavements. Vehicles should only be able to travel a little faster than walking pace. This means that the street can be modified to include children’s play areas, larger gardens or planting such as street trees, cycle parking and facilities such as seats at which residents can meet. Home Zones should therefore make residential areas safer for pedestrians and cyclists, and improve the quality of the street environment. 1.2 There are the two types of Home Zones that could be developed in the Borough whereby external funding and support could be provided. The two types are Transport for London funded Area Based Scheme projects and SUSTRANS DIY Streets. Agenda Item 16 Page 574
2. AREA BASED SCHEMES Background 2.1 The Area Based Schemes (ABS) programme is split into three discrete elements; Town Centres; Streets for People; and Station Access. 2.2 The key objectives for ABS include: • Improve the physical and living environment • Reduce vehicle dominance and create attractive outdoor living spaces • Improve personal security, reduce the fear of crime, particularly for travel during the hours of darkness • Increase the opportunities for local people to use streets as social spaces • Reduce social exclusion • Facilitate regeneration and increase transport opportunities for local communities, whilst encouraging shorter journeys to be made • Reduce the adverse effects of traffic • Improve conditions for cyclists, pedestrians and bus users to encourage more journeys by these modes • Improve accessibility of the public transport network for everyone. 2.3 The ABS programme is designed for schemes covering relatively large areas (with funding ranging between £0.5 million to over £2 million) and to be developed over a phased period of around three years. TfL require boroughs considering bidding for funds under this programme to complete a series of step submissions. An indicative timetable including the development and implementation phase for a proposed ABS is provided below.
Indicative ABS timetable Activity Date Submission of a scheme Step 1 bid to TfL July / August 2007 TfL decision on STEP 1 funding (2008/09 allocations) December 2007 announced as part of the LIP funding outcomes. Further scheme design and public consultation on January to May 2008 shortlisted scheme Submission of STEP 2 bid(s) to TfL September 2008 TfL allocations for 09/10 December 2008 Scheme(s) implementation 2009
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Domestic Violence - Strategic Options(i) That the proposals set out in paragraphs 4 to 6 in the report be endorsed; (ii) To agree to forward the report to...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.