Phase A Contracts Performance Monitoring

Noted Committee 1 paper

South London Waste Partnership Joint Committee noted this item on Thursday 12 September 2013. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

To note the report.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to South London Waste Partnership Joint Committee

Page 7 Agenda Item 4 Item 2 – Phase A Contact Management Reporting

Report to: South London Waste Partnership (SLWP) Joint Waste Committee Date: Thursday 12 September 2013 Report of: SLWP Management Group

Author(s): Simon Mander , Interim Client Side Contract Manager (LBC) Chair of the Meeting: Councillor Colin Hall, Chair SLWP Joint Waste Committee

Report title: Phase A Contracts Performance Monitoring Summary: Contract 1 and 3 with Viridor for landfill, energy from waste, composting and recycling are performing well. Contract 2 with EWC for running the Household Reuse and Recycling Centres has seen a drop in performance compared to the same period last year. Recommendations: The Joint Waste Committee is asked to note the contents of this report, and to comment on any aspects of the performance of the Partnership’s Phase A contracts. Background Documents and Previous Decisions Phase A Contract Performance Monitoring updates have been presented to the Joint Waste Committee since 22 July 2010. The most recent reports were present at the meeting on 18 June 2013.

1. Background 1.1 This paper provides a quarter 1 update on the performance of the three Phase A contracts for the financial year 2013/14. These contracts have been in place and operating since 2008.

Contract 1 Landfill and Transportation.

Contract 2 Management of Household Reuse and Recycling Centres.

Contract 3 Materials Recycling Service, Composting and additional Treatment Service

1.2Contracts 1 & 3 are operated by Viridor Waste Management LTD.

1 Agenda Item 4 Page 8 1.3 Contract 2 was operated by Environmental Waste Controls (EWC) for the period that this report covers.

2. Issues CONTRACT 1 – LANDFILL AND TRANSPORTATION (VIRIDOR WASTE MANAGEMENT LTD.)

2.1The contract is operating effectively with municipal solid waste delivered to Viridor’s Beddington Farmlands Landfill facility by all Partnership boroughs.

2.2Viridor continued to operate in line with the contract and there were no operational issues reported.

2.3There is no performance or formal complaint issues relating to this contract.

2.4There has been damaged caused to the automatic gates which cover the out of hours operation. The damage was caused by two of the SLWP authorities and was investigated in a timely fashion. It was agreed that the cost of repairing the damage would be split between the two authorities.

2.5There has recently been an accident to a Viridor employee working in the out of hours tipping floor by a SLWP authority. This again was investigated in a timely fashion and Viridor provided with witness statements regarding the incident.

CONTRACT 2 – MANAGEMENT OF HOUSEHOLD REUSE & RECYCLING CENTRES (ENVIRONMENTAL WASTE CONTROLS)

2.6The issues covering EWCs exit are covered elsewhere on the agenda.

2.7In terms of performance there was a drop in the recycling rate and diversion rate for this period compared to Q1 2012/13. The recycling rate has dropped by 1.19% and the diversion rate has dropped by 0.81%.

2.8Despite EWC meeting its contractual performance targets the long term recycling performance of the contract continues to fall as set out in graph 1 below.

SLWP 12 month moving average recycling rate

77.00

76.00Recycling %

75.00

74.00

73.00

72.00Aug-09 Oct-09 Dec-09 Feb-10 Apr-10 Jun-10 Aug-10 Oct-10 Dec-10 Feb-11 Apr-11 Jun-11 Aug-11 Oct-11 Dec-11 Feb-12 Apr-12 Jun-12 Aug-12 Oct-12 Dec-12 Feb-13 Apr-13 Jun-13

Month

Graph 1 – SLWP 12 month moving average recycling rate.

2 Page 9 Agenda Item 4 2.9 The level of complaints remains broadly the same. These complaints can be split down into customer service issues, availability of recycling containers, residents not being allowed entry into a site and allegations of theft. All complaints are brought to the attention of EWC management who have in the majority cases of investigated the complaints and responded. There is still some concern regarding the quality of the responses and the timescales to receive the response.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 2: Phase A Contract Management ReportingReport 103 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 2 attended
CH
Councillor Colin HallCommittee Member, expected
JW
Councillor Jill WhiteheadCommittee Member, expected

On this subject at Sutton

Search all
  1. Phase A Contracts Performance MonitoringThis decision
  2. Communications and stakeholder engagement – Phase A and Phase B contractsNoted

More from Sutton South London Waste Partnership Joint Committee

All decisions
MeetingDecisionOutcome
26 Nov 2025 Minutes of the previous meetingThat the minutes of the previous meeting held on 11 June 2025 were approved as a correct record. Approved Open
26 Nov 2025 Communications and Engagement UpdateTo Note the contents of this report and comment on any aspects of communications and engagement activities relating t... Noted Open
26 Nov 2025 Contracts Performance ReportNote the latest position with the ERF residual waste treatment contract related to the recent CEMS calibration issue ... Noted Open
26 Nov 2025 Budget Update 2025/26To note the content of this report. Noted Open
26 Nov 2025 Proposed Management Budget 2026/27To approve the 2026/27 SLWP Budget of £707k. This represents an annual cost of £177k per borough and an increase of j... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies