South London Waste Partnership Joint Committee noted this item on Tuesday 10 December 2013. Below is the council's own wording, with the papers it was decided on.
( i ) To note the report. (ii) That the additional principles, as set out in the report, to be incorporated in a revised Inter Authority Agreement. (iii) To delegate to the Chair of Management Group, in consultation with the Management Group and Legal leads from each of the partner boroughs, to conclude the drafting of the revised Inter Authority Agreement. (iv) That each of the partnership boroughs approve and execute the final drafting of the revised Inter Authority Agreement.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to South London Waste Partnership Joint Committee
Page 45 Agenda Item 8
Report to: South London Waste Partnership (SLWP) Joint Waste Committee Date: 10 December 2013 Report of: SLWP Management Group Author(s): Cormac Stokes, Head of Street Scene and Waste (LBM), SLWP Lead Officer Governance Chair of the Meeting: Councillor Colin Hall, Chair SLWP Joint Waste Committee
Report title: Annual Review of the inter-Authority Agreement Summary: The Partnership is required to review the inter-Authority Agreement (IAA) on an annual basis. This report sets out the findings of the review and proposes some additional principles that should be incorporated within a further supplemental to the IAA in order for the Partnership to progress its agreed commercial and strategic approach to the future management of waste treatment services. Recommendations: It is recommended that the Joint Waste Committee: a) Note and comment on the contents of this report. b) Agree the additional principles to be incorporated in a revised IAA and delegate to the Chair of Management Group, in consultation with the Management Group and Legal leads from each of the partner boroughs, to conclude the drafting of the revised IAA; c) Recommend that each of the partnership boroughs approve and execute the final drafting of the revised IAA. Background Documents and Previous Decisions The current IAA is comprised of a suite of agreements and supplemental agreements Phase A Strategic Review (JWC, September 2013) HWRC Strategy (JWC, September 2013)
1. Background 1.1 The current IAA makes provision for an annual review of the Agreement to ensure that appropriate arrangements are in place for the ongoing management and procurement of waste contracts that are within the remit of the South London Waste Partnership Joint Waste Committee. Agenda Item 8 Page 46 1.2 This report sets out the findings of the most recent review of the IAA carried out by the Management Group and highlights that there is a need for further amendments and additions.
2. Details 2.1 Procurement
2.1.1 The review of the current IAA has concluded that it is fit for purpose with respect to the ongoing management of Phase A and Phase B contracts currently in place.
2.1.2 At its meeting of 12 September 2013 the Joint Waste Committee agreed to the proposed three stage strategy to exit from the existing arrangements for the management of HWRCs; move to a HWRC transition stage and embark upon a longer term re-procurement of HWRC Services.
2.1.3 The partnership is currently in the transition stage and the services are being managed in-house by the partnership with the Royal Borough of Kingston hosting all staffing and supplier arrangements. These arrangements are effectively covered through the existing IAA. The Partnership intends to commence the procurement of these services in the New Year.
2.1.4 At the same meeting (12 September 2013), the JWC considered the Partnership’s Phase A Strategic Review and agreed to support the proposed commercial and procurement strategy that would require the procurement of waste framework arrangements covering at least residual waste, co-mingled recyclates and food waste. The purpose of the framework would be to provide flexibility for waste streams not fully committed through current contractual arrangements.
2.1.5 It is intended that the London Borough of Croydon acts as the lead procuring authority for both the Waste Framework and the Management of HWRCs contracts. At present there is no inter-Authority Agreement in place with respect to LBC acting as lead procuring authority for these new contracts.
2.1.6 The Commercial Strategy sets out a number of activities that will rely on the partnership being flexible in terms of reacting to changing market conditions. In order to react swiftly to such conditions it is advisable that some flexibility is built into the IAA to enable the partnership to identify a lead authority and progress matters without having to refer back to the Joint Waste Committee to amend further the IAA.
2.2Resourcing
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow South London Waste Partnership Joint Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
Communications and Engagement UpdateTo Note the contents of this report and comment on any aspects of communications and engagement activities relating t...
Proposed Management Budget 2026/27To approve the 2026/27 SLWP Budget of £707k. This represents an annual cost of £177k per borough and an increase of j...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.