Resolved
: (1) That the report be noted.
Swale Joint Transportation Board noted this item on Monday 18 December 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
: (1) That the report be noted.
A2500 Lower Road / Barton Hill Road
To: Swale Joint Transportation Board – 18 December 2017
Main Portfolio Area: Growth, Environment & Transport
By: Roger Wilkin, Director of Highways & Transportation
Classification: For Information
Ward: Sheppey Central Division: Sheppey
Summary: Update on proposals for improving the A2500 Lower Road between Cowstead Corner and Barton Hill Drive and a junction improvement at Lower Road / Barton Hill Drive - Minster
1.0Introduction
1.1Members will be aware of the scheme to improve the junction of the A2500, Lower Road and Barton Hill Drive from previous reports and attendance by officers at meetings of this Board - most recently 26 June 2017.
1.2This report gives a further update on the South East LEP funding and the programme to deliver the junction improvements as well as advising on the National Infrastructure Productivity Fund (NPIF) bid for the new proposals to improve the A2500 Lower Road between the A249 at Cowstead Corner and Barton Hill Drive.
1.3The intention is to treat the improvements as a single project titled the A2500, Lower Road Improvement. This will be broken down into two phases.
Phase 1 – Lower Road/Barton Hill Drive - Junction Improvement Phase 2 – Lower Road Widening – Cowstead Corner to Barton Hill Drive
1.4The scheme for Phase 1 is a new roundabout at the junction of the A2500 Lower Road with Barton Hill Drive. Proposals are shown on the scheme plan in Appendix A
1.5The scheme for Phase 2 is to widen a 1.1km section of the A2500 Lower Road between the A249 at Cowstead Corner and Barton Hill Drive, including the construction of a new shared footway/cycleway alongside the road which will provide the infrastructure for all road users, currently lacking in this location. Proposals are shown on the scheme plan in Appendix B. 2.0 Current Situation
Phase 1 2.1 The SELEP funding has been confirmed and developer contributions from s106 agreements identified.
2.2Detailed design work has been progressing on the proposals for the roundabout junction of the A2500 Lower Road with Barton Hill Drive.
2.3A request for a screening opinion for Phase 1 was submitted to the planning authority. Confirmation has been received that a full Environmental Impact Assessment (EIA) is not required and that the proposals are therefore able to proceed as permitted development.
2.4WSP has been engaged as the engineering consultant to provide the detailed design and construction drawings for Phase 1, and the feasibility and detailed designs of Phase 2.
2.5Initial discussions have taken place with the KCC Streetworks Team to identify the most appropriate times to undertake these works. Details are still to be finalised but construction will ensure minimum traffic disruption in July and August to avoid delays to holiday traffic.
2.6The roundabout has been developed to incorporate the potential for a spur road for a fourth arm to serve as access to the development site identified as Policy A12 in ‘Bearing Fruits 2031: The Swale Borough Local Plan 2017.’
Phase 2 2.7 NPIF bid for part funding of Phase 2 was submitted in the summer of 2017 and the funding was confirmed in October 2017.
2.8Match funding and the provision of the land required for the widening of Lower Road has been identified and agreed in principal with the promoters of the site of Policy A12. The funding and land is conditional on receipt of planning consent for housing on the site of Policy A12 and will need to be secured through a s106 agreement.
2.9The improvement of the Lower Road is also part of the Local Plan Policy A12 and is to be provided in association with the residential development.
2.10The provision of the new footway cycleway will provide an important connection between the residential area of Minster with the retail and business areas at Rushenden and Neat’s Court. The proposals are for a 3.5m shared footway cycleway separated from the carriageway by a 1.5m verge; see the typical cross-section in Appendix 3.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
A2500: Appendix AAppendix | 556 KB | Download |
PDF |
A2500: Appendix BAppendix | 1.4 MB | Download |
PDF |
A2500: Appendix CAppendix | 159 KB | Download |
PDF |
Update on proposals for improving the A2500 Lower Road, Minster between Cowstead Corner and Barton Hill Drive, Minster and a junction improvement at Lower Road / Barton Hill Drive, MinsterReport | 74 KB | DownloadRead as text |
Follow Swale Joint Transportation Board at Swale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jun 2026 | Presentation from Network Rail(1) That it be recommended to the relevant parties at Swale Borough Council and Kent County Council that a joint work... | Decided | Open |
| 29 Jun 2026 | Update on the Local Electric Vehicle Infrastructure (LEVI) Project and other Electric Vehicle (EV) charging infrastructure(1) That the report be noted. | Noted | Open |
| 6 Oct 2025 | Highways Work Programme(1) That the report be noted. | Noted | Open |
| 6 Oct 2025 | Progress Update Report - including updates on Grovehurt Road junction Sittingbourne and Key Street junction Sittingbourne(1) That the update report and verbal updates be noted. | Noted | Open |
| 30 Jun 2025 | Update Report - Proposed Double Yellow Lines, Park Road, Faversham(1) That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.