Resolved
(1) That the report be noted.
Swale Joint Transportation Board noted this item on Monday 18 December 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) That the report be noted.
To: Swale Joint Transportation Board
By: KCC Highways and Transportation
Date: 18th December 2017
Subject: Highway Works Programme 2017/18
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction in 2017/18
1. Introduction
This report provides an update and summarises schemes that have been programmed for delivery in 2017/18
Footway and Carriageway Improvement Schemes – see Appendix A
Drainage Repairs & Improvements – see Appendix B
Street Lighting – see Appendix C
Traffic Systems – see Appendix D
Developer Funded Works – see Appendix E
Transportation, PROW and Safety Schemes – see Appendix F
Public Rights of Way – see Appendix G
Bridge Works – see Appendix H
Member Highway Fund – see Appendix I
Conclusion
1. This report is for Members information.
Contact Officers:
The following contact officers can be contacted on 03000 418181
Kirstie Williams Highway Manager (Mid) Alan Blackburn Swale District Manager Alan Casson Road & Footway Asset Manager Kevin Gore Interim Drainage Manager Paul Hopkins Interim Structures Manager Sue Kinsella Street Lighting Manager Toby Butler Intelligent Transport Systems Manager Andrew Hutchinson Transportation, PROW and Safety Schemes Nick Abrahams Economic Development Appendix A – Footway and Carriageway Improvement Schemes
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.
Machine Resurfacing – Contact Officer Byron Lovell
Road Name Parish Extent of Works Current Status
Junction with Tunstall Programmed 13th Woodstock Road Sittingbourne Road and Cromer Road March 2018
Junction with Barton Hill Programmed 12th B2008 Minster Road Minster Drive March 2018
Watsons Hill Sittingbourne Full length Completed
Footway Improvement - Contact Officer Neil Tree
Extent and Road Name Parish Current Status Description of Works Between No’s. 2 and 72 Chilton Avenue. Chilton Avenue Sittingbourne Completed (Footway Reconstruction) From the junction with the A2 London Road to Re-programmed for A251 Ashford Road Faversham O/S No. 91 Ashford February 2018 Road. (Footway Protection). Re-programmed for Entire length Ashtead Drive Bapchild February /March (Footway Protection). 2018 From the junction with Ashtead Drive to the Re-programmed for School Lane Bapchild junction with February /March St.Laurence Close. 2018 (Footway Protection). Re-programmed for Entire length St Lawrence Close Bapchild February /March (Footway Protection). 2018 Re-programmed for Entire length Wihtred Road Bapchild February /March (Footway Protection). 2018
Surface Treatments - Contact Officer Jonathan Dean
Micro Surfacing Road Name Parish Extent of Works Current Status
Addington Rd From Ufton Road To Sittingbourne Completed Park Road
To be Oare Road To Cole The Street Oare Re-programmed for Gates Road March 2018.
Selling Road To Perry Wood Chilham / Perry Wood Completed Perrywood
Grove Road To Perry Perry Wood Chilham / Perry Wood Completed Wood
Elm Lane Minster Whole Road Completed
To be B2008 Back Lane & Minister Whole Road Re-programmed for High Street March 2018. Rodmersham Green / Rodmersham Whole Road Completed Bottles Lane
From Kettle Hill To Stalisfield Road Rodmersham Completed Haywards Hill
From Bridge To Shadow Wormdale Hill Newington Completed Motors
Forge Lane Up Church Oak Lane To The Street Completed
The Knole Faversham Whole Length Completed
From the junction with Whitstable Road to its Westgate Avenue Faversham Completed junction with Gordon Square. From the junction with Whitstable Road to its Cyprus Road Faversham Completed junction with Gordon Square.
Surface Treatments - Contact Officer Jonathan Dean
Surface Dressing Road Name Parish Extent of Works Current Status
Plough Road To Eastchurch Road Eastchurch Roundabout Completed
Everland Lane To Eastling Road Eastling Scotts Lane Completed
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highway Works ProgrammeReport | 127 KB | DownloadRead as text |
Follow Swale Joint Transportation Board at Swale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jun 2026 | Presentation from Network Rail(1) That it be recommended to the relevant parties at Swale Borough Council and Kent County Council that a joint work... | Decided | Open |
| 29 Jun 2026 | Update on the Local Electric Vehicle Infrastructure (LEVI) Project and other Electric Vehicle (EV) charging infrastructure(1) That the report be noted. | Noted | Open |
| 6 Oct 2025 | Highways Work Programme(1) That the report be noted. | Noted | Open |
| 6 Oct 2025 | Progress Update Report - including updates on Grovehurt Road junction Sittingbourne and Key Street junction Sittingbourne(1) That the update report and verbal updates be noted. | Noted | Open |
| 30 Jun 2025 | Update Report - Proposed Double Yellow Lines, Park Road, Faversham(1) That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.