Resolved
(1) That the report be noted.
Scrutiny Committee - Decommissioned 18.05.2022 noted this item on Wednesday 7 November 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) That the report be noted.
Sittingbourne Town Centre Regeneration Scheme
Update to Scrutiny Committee 7th November 2018
Update
Construction All three retail units (The Food Warehouse, Home Bargains & Costa Drive Through) continue to trade successfully on Princes Street Retail Park. The minor snagging items are now planned to be complete by the end of November although the removal of the hoarding along Milton Road will be programmed to align with the next road closure at Milton Road planned by Erith. There are a few minor snagging items to complete in the Forum car park. The installation of the electricity meter and the connection to the Distribution Network Operators (DNO) supply to energise the new lighting columns was completed on 12th October. The Phase 2 roadworks partially opened to traffic on 22nd October (St. Michael’s Road through the station & Milton Road) with works continuing in Dover Street until week commencing 29th October and to the paving in front of the station during November. PDR, the contractor constructing the Leisure Quarter were on site on schedule from 23rd October and are currently in the process of site set up and the erection of hoardings. As part of the PDR work, a section of Station Street within the footprint of the leisure development was stopped up on 22nd October and closed off to traffic. Huber, the contractor for the multi-storey car park are on schedule and continue to erect the last elements of the steel frame as well as installing the deck sheeting and deck reinforcement ahead of the concrete pour programmed for the beginning of November. Electricians are also installing the first fix electrics to the lift shafts and stair cores and to the decking.
Planning Spirit continues to work with the Planning Team for the pre-commencement conditions relating to the Leisure site.
Utility Services Spirit and PDR continue to work with the utility companies in preparation for the leisure development.
Risks Spirit is maintaining the Developers risk register through all phases of the scheme. The SBC specific Risk Register continues to be updated to reflect the current project risks.
Communications Spirit’s communication team continue to field and respond to enquiries regarding the scheme on a daily basis. Spirit’s communication team issued a press release and email to their business list (40+town centre businesses) on 19th October detailing the opening schedule for the A2 and personally visited businesses on Station Street ahead of the Station Street closure. An email announcement was sent to all members on 22nd October providing an update on the road opening The Leader and the Cabinet Member for Regeneration visited the Leisure site again on 25th October Spirit’s communication team will issue a further press release and email once Dover Street is open to traffic. The Kent Messenger will visit the leisure site during week commencing 29th October.
SBC Team and The appointed QS/Employers Agent for the MSCP Governance from Ian Sayer & Co continues to take responsibility for the regular meetings during the construction phase (the next monthly progress meeting is scheduled for 31st October) and is currently reviewing variations relating to the initial subterranean works. The first progress meeting with Spirit, PDR and the Councils monitoring surveyor from Ward Williams Associates is scheduled for 1st November. Cushman & Wakefield continue to assist with the Managing Agent duties for the Retail Park and are currently developing a MA specification for the MSCP and Leisure Quarter. Board meetings, Key Officer Group meetings and Internal Officer Group meetings continue.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Sittingbourne Town Centre Update ReportReport | 168 KB | DownloadRead as text |
Follow Scrutiny Committee - Decommissioned 18.05.2022 at Swale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Mar 2022 | Performance Monitoring Report(1) That the report be noted. | Noted | Open |
| 23 Mar 2022 | Cabinet Forward Plan(1) That the Forward Plan be noted. | Noted | Open |
| 19 Jan 2022 | Cabinet Forward Plan(1) That the report be noted. | Noted | Open |
| 17 Nov 2021 | Cabinet Forward PlanThat the report be noted. | Noted | Open |
| 17 Jun 2021 | Sittingbourne Town Centre Update(1) That the Sittingbourne Town Centre update be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.