CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Swale Borough Council
Scrutiny Committee - Decommissioned 18.05.2022, Thursday 25 February 2021 at 7.00pm

Sittingbourne Town Centre Regeneration Update

Noted Scrutiny 1 paper

Scrutiny Committee - Decommissioned 18.05.2022 noted this item on Thursday 25 February 2021. Below is the council's own wording, with the papers it was decided on.

Item480

Resolved

(1) That the update be noted.
Word for word from the decision Swale published for this meeting. Source: democracy.swale.gov.uk

Follow this further

Built from Swale's papers

What the report saysPro

Report to Scrutiny Committee - Decommissioned 18.05.2022

Sittingbourne Town Centre Regeneration Update to Scrutiny Committee 25th February 2021

Progress Update SBC Bourne Place Unit Fit Outs (Cinema and Bowling Alley) The Light completed the fit out of both the cinema and the bowling alley just before Christmas 2020 with building control sign off and practical completion being reached on 18th December.

1|Page Unit Fit Outs (Unit 3b – Nando’s) Nando’s are awaiting completion of the base build changes being carried out by PDR prior to taking possession of their unit (3b). Currently Nando’s are in the process of submitting a planning application for slight changes to the front of their unit including the introduction of a hatch for takeaways and deliveries. The planning team have reviewed Nando’s outline drawing and confirmed that this can be done as a non-material amendment.

Prospective Tenants Savills continue to work to fill the vacant units in a challenging market caused by COVID-19. There is current interest in unit 1 which is being explored.

Travelodge Travelodge has continued to trade throughout the lockdown periods.

Communications SBC and Spirit’s communications team will work towards a communications strategy to coincide with the opening of the cinema, bowling alley and Nando’s when these dates of known.

Princes Street Retail The Food Warehouse, Home Bargains and Costa Coffee Park all continue to trade well on the retail development. Lease payments are being paid on time and currently Cushman & Wakefield maintain a healthy balance sheet for the site.

Managing Agent Cushman & Wakefield continue to assist with the Managing Agent duties for the Retail Park, MSCP and Bourne Place.

Cushman & Wakefield are also providing Building Surveyor expertise to monitor the fit outs.

Spring Street car park The edge protection/railing installation around Spring Street car park was completed by Lemar contractors on 29th January 2021.

Footpath between The 1st certificate was issued by KCC on 1st December MSCP & High Street 2020 with a requirement that the two highway lighting columns still needed to be inspected and approved by KCC’s street lighting team.

KCC’s Street lighting team inspected the 2no. highway columns on 20th January 2021 and confirmed their approval of the installations.

2|Page The final adoption certificate will be issued subject to an end of maintenance inspection in November 2021.

Meetings High Level meetings continue to be held with Spirit on a monthly basis by conference call with the previous meeting being held on 11th February.

Monthly meetings continue to be held with Cushman & Wakefield on a monthly basis by conference call with the previous meeting also being held on 11th February.

SPIRIT OF SITTINGBOURNE Highway Works Following practical completion of the highway areas on 9th October 2020 Erith contractors completed the main snagging item which was the resurfacing and the installation of an additional lighting column on the footpath that runs from the new Network rail car park behind Kwikfit on 29th January.

Bourne Place The vinyls for the glazing of the unlet units was installed by Spirit between the Christmas and New Year period.

Spirit/Erith are still to provide an update regarding the date for the Vodafone fibre optic cable relocation in the North West corner of Bourne Place.

Works commenced on 15th February to the base build for unit 3b ahead of Nando’s taking possession. The original base build main contractor, PDR and their selected subcontractors are carrying out the agreed works to ensure all warranties are maintained. The works are estimated to take approximately four weeks to complete.

Wayfinding Spirit’s Wayfinding consultant is still to provide an illustration of the mapping, history stories and directions arrows/labels for each totem panel for approval. This is currently being chased by Spirit and SBC.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sittingbourne Town Centre Regeneration UpdateReport 214 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 30 attended
AA
Anne AdamsOfficer, in attendance
CB
Cameron BeartVisiting Councillor, in attendance
MB
Monique BonneyVisiting Councillor, in attendance
LB
Councillor Lloyd BowenChair, present
RC
Roger ClarkVisiting Councillor, in attendance
RD
Councillor Richard DarbyCommittee Member, present
JD
Janet DartOfficer, in attendance
SD
Councillor Steve DaveyCommittee Member, present
MD
Councillor Mike DendorVice-Chair, present
TG
Councillor Tim GibsonCommittee Member, present
AG
Councillor Alastair GouldCommittee Member, present
JH
Councillor James HallCommittee Member, present

All 30 on the meeting page

On this subject at Swale

Search all
  1. Sittingbourne Town Centre Regeneration UpdateThis decision
  2. Sittingbourne Town Centre UpdateNoted
  3. Sittingbourne Town Centre UpdateNoted
  4. Sittingbourne Town Centre Update ReportNoted
  5. Sittingbourne Town Centre Regeneration UpdateNoted
  6. Sittingbourne Town Centre Regeneration Project - variations to the development agreementAgreed

More from Swale Scrutiny Committee - Decommissioned 18.05.2022

All decisions
MeetingDecisionOutcome
23 Mar 2022 Performance Monitoring Report(1) That the report be noted. Noted Open
23 Mar 2022 Cabinet Forward Plan(1) That the Forward Plan be noted. Noted Open
19 Jan 2022 Cabinet Forward Plan(1) That the report be noted. Noted Open
17 Nov 2021 Cabinet Forward PlanThat the report be noted. Noted Open
17 Jun 2021 Sittingbourne Town Centre Update(1) That the Sittingbourne Town Centre update be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies