CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Swale Borough Council
Scrutiny Committee - Decommissioned 18.05.2022, Wednesday 12 August 2020 at 7.00pm

Sittingbourne Town Centre Update

Noted Scrutiny 1 paper

Scrutiny Committee - Decommissioned 18.05.2022 noted this item on Wednesday 12 August 2020. Below is the council's own wording, with the papers it was decided on.

Item40

Resolved

(1) That the update be noted.
Word for word from the decision Swale published for this meeting. Source: democracy.swale.gov.uk

Follow this further

Built from Swale's papers

What the report saysPro

Report to Scrutiny Committee - Decommissioned 18.05.2022

Sittingbourne Town Centre Regeneration Update to Scrutiny Committee 12th August 2020

Progress Update SPIRIT OF SITTINGBOURNE Highway Works Following a series of night-time works between April and June Erith have now substantially completed all of the outstanding resurfacing, remedial resurfacing and civils remedial works as well as items identified as part of the Stage 3 (post construction) Road Safety Audit.

KCC have now issued the first certificates for highway sections, 1, 2, 3, 4, 5, 6 and 8 and Spirit’s Principal Designer is currently reviewing all of the as-built drawings and associated handover documentation provided by Erith Contractors ahead of Practical Completion which Erith are bound to meet within 30 days of the 1st Certificates being issued.

Spirit have now issued instructions to Erith to install additional areas of double yellow lining in Station Street and in Fountain Street in accordance with the revised traffic regulation orders that have been agreed with KCC. A ‘live’ date for these orders has yet to be confirmed but the lining will deter unauthorised parking and obstruction in these two roads. Leisure Development As a result of the government announcement on COVID- (Bourne Place) 19 in March PDR initially advised Spirit on 26th March that they would be closing the site. Following further evaluation by PDR’s senior team and CDM/Health & Safety advisors they then confirmed on 30th March that limited external works could continue in accordance with public health guidance and therefore the site would remain open. Works continued on site from that point on however the number of resources were reduced significantly by PDR due to social distancing requirements and the majority of suppliers delivering to the site had closed so plant and materials were not freely available. This had a direct impact on the delivery timescales and delayed the Practical Completion date.

Following the Practical Completion of the hotel building on 19th February Practical Completion of the remainder of the leisure site (cinema, units beneath the cinema and external areas) was finally reached on Friday 26th June 2020. Two previous inspections took place on 12th and 22nd June but PC was not granted by Spirit’s employer’s agent on those dates due to a number of snagging items still being outstanding. PDR had a continual presence on site until Friday 3rd July to complete minor snagging items.

The contractor carrying out the commissioning of the external building lighting to the cinema and hotel attended site again at the end of July to complete their works. Training on the system for SBC and Cushmans (managing agent) staff has yet to be arranged.

The gas connection to the cinema was finally installed in July however we are still awaiting an update from Spirit/Erith regarding the Vodafone fibre optic cable relocation in the North West corner of Bourne Place.

PDR have now replaced the seven sections of the granite benching that arrived damaged and also installed the anti- skateboarding studs during week commencing 3rd August. The Heras fencing surrounding the benching has now be removed.

Heras fencing along the front of the units was put in place by the managing agent and will remain in place to safeguard the glazing from vandalism and enable the fit out works to progress without being affected by the public.

ATS, the Lights fit out contractor will be installing temporary edge restraint on the cinema roof week commencing 10th August. This will enable the contractor to get additional resources on the roof at the same time when the ventilation and extraction equipment is installed on the roof. The current wired ‘mansafe’ system only allows for two operatives to be on the roof at any one time.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sittingbourne Town Centre UpdateReport 101 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 15 attended
LB
Lloyd BowenChair, present
RD
Richard DarbyCommittee Member, present
SD
Steve DaveyCommittee Member, present
MD
Mike DendorVice-Chair, present
TG
Tim GibsonCommittee Member, present
AG
Alastair GouldCommittee Member, present
JH
James HallCommittee Member, present
CJ
Carole JacksonCommittee Member, present
EJ
Elliott JayesCommittee Member, present
DK
Denise KnightsCommittee Member, present
LM
Lee McCallCommittee Member, present
JM
Jo MillardOfficer, in attendance

All 15 on the meeting page

On this subject at Swale

Search all
  1. Sittingbourne Town Centre UpdateThis decision
  2. Sittingbourne Town Centre UpdateNoted
  3. Sittingbourne Town Centre Regeneration UpdateNoted
  4. Sittingbourne Town Centre Update ReportNoted
  5. Sittingbourne Town Centre Regeneration UpdateNoted
  6. Sittingbourne Town Centre Regeneration Project - variations to the development agreementAgreed

More from Swale Scrutiny Committee - Decommissioned 18.05.2022

All decisions
MeetingDecisionOutcome
23 Mar 2022 Performance Monitoring Report(1) That the report be noted. Noted Open
23 Mar 2022 Cabinet Forward Plan(1) That the Forward Plan be noted. Noted Open
19 Jan 2022 Cabinet Forward Plan(1) That the report be noted. Noted Open
17 Nov 2021 Cabinet Forward PlanThat the report be noted. Noted Open
17 Jun 2021 Sittingbourne Town Centre Update(1) That the Sittingbourne Town Centre update be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies