Contract Award Report: Framework of Contractors for Housing Renewal and Adaptations works.

Decided Executive 1 paper

Cabinet decided this item on Thursday 20 September 2018. Below is the council's own wording, with the papers it was decided on.

Item67

Resolved

Resolved that: 1) The suppliers listed in Appendix 1 of the report be appointed to the Framework for the three lots listed .
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Cabinet

Background

2.1The Housing Renewal and Adaptations service needs to procure a framework of contractors to undertake housing adaptation and repair grant/ loan works to assist elderly and disabled residents to remain living independently within their own homes.

2.2Corporate Building and Property Services have previously determined that this work does not fall within the definition of core business and therefore external suppliers need to be procured through a framework in accordance with Contract Procedure Rules.

2.3The framework consists of three separate lots of work that consist of : Lot A Disabled Facilities Adaptations primarily bathroom conversions with associated minor builders work, typical values £5,000 to £7,500.

Lot B Disabled Facilities Adaptations primarily large domestic alterations including extensions, ramps, and attic conversions, maximum individual project value £36,000.

Lot C House Renovation Works including repair or renewal of roof, rendering, structural repairs, damp proofing, windows, doors and sundry repair works, maximum individual project vallue £30,000.

2.4The suppliers selected for each Lot of the framework will be allocated schemes in rotation. The framework will also have a reserve list for each Lot to replace poor performing providers , and will also be used to allocate additional works within the Lot at times of high output, where framework suppliers are at full capacity and unable to take on further work.

2.5The period of operation of this framework will be for an initial period of 2 years, with an option to extend up to a further 2 years.

3.0Procurement process

3.1The Council’s intention was to enter into a framework agreement with a number of suppliers : Lot A : 12 suppliers, 8 reserve.

Lot B : 15 suppliers, 10 reserve.

Lot C : 7 suppliers, 3 reserve.

3.2The tender was advertised through Sell2Wales.

3.3The award criteria used for this process are tenders are evaluated in terms of quality only, with cost being determined by a pre-priced Housing Grants schedule of rates.

3.4The ‘open’ procedure was selected.

3.5The Invitation to tender (ITT) was issued on 19th April 2018 via the eTenderWales Portal.

3.6Thirty six suppliers in total submitted tenders, twenty eight for Lot A, twenty five for Lot B, thirteen suppliers for Lot C, with some suppliers tendering for more than one lot, returned by the deadline date of 24th May 2018.

3.7The tenders were opened by Commercial Services in accordance with Contract Procedure Rules, with one contractor disqualified at this stage, Contractor 3 as they submitted a tender after the submission deadline.

3.8Tenders were evaluated by five officers of the Council’s Housing Renewal and Adaptations service with support from an officer of the Commercial Services Department.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Contract Award Report: Framework of Contractors for Housing Renewal and Adaptations works.Report 30 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 24 attended
RS
Rob StewartChair, present
MC
Mark ChildCommittee Member, present
WE
William EvansCommittee Member, present
RF
Robert Francis-DaviesCommittee Member, present
DH
David HopkinsCommittee Member, present
AL
Andrea LewisCommittee Member, present
CL
Clive LloydCommittee Member, present
JR
Jennifer RaynorCommittee Member, present
MS
Mary SherwoodCommittee Member, present
MT
Mark ThomasCommittee Member, present
CS
Chris SiversOfficer, expected
MN
Martin NichollsOfficer, expected

All 24 on the meeting page

On this subject at Swansea

Search all
  1. Contract Award Report: Framework of Contractors for Housing Renewal and Adaptations works.This decision
  2. Contract Award Report – Contracts for Local Bus Services.Decided
  3. Second Stage (Construction) FPR7 Contract Award and associated Capital Programme Authorisation for the Remodelling and Refurbishment Project at Bishopston Comprehensive School.Approved
  4. Contract Award and Capital Programme Authorisation for the Extension and Remodelling of Ysgol Gyfun Gŵyr.Approved
  5. Contract Award and Capital Programme Authorisation for the New Build Replacement of YGG Tirdeunaw.Approved
  6. Contract Award and Capital Programme Authorisation for New Build for YGG Tan-y-lan.Approved

More from Swansea Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... Approved Open
16 Sep 2026 Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... Approved Open
16 Sep 2026 Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... Approved Open
16 Sep 2026 Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... Noted Open
16 Sep 2026 Quarter 1 2026/27 Performance Monitoring Report.Resolved that: 1) The Council’s performance in delivering its well-being objectives during Quarter 1 of 2026/27 be no... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies