Resolved
For information.
Governance & Audit Committee decided this item on Tuesday 18 May 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
For information.
1.1This report provides an overview of the status of Corporate risks in the Council to give assurance that key risks are being managed and risk management process is being followed.
2. Corporate Risk: Quarter 4 2020/21
2.1The following summarises the status of risks recorded in the Corporate Risk Register as at Quarter 4 2020/21 compared to Quarter 3 2020/21:
There are 5 Red status risks in the Corporate Risk Register: o Risk ID 153 – Safeguarding. o Risk ID 159 - Financial Control: MTFP aspects of Sustainable Swansea. o Risk ID 222 - Digital, data and cyber security. o Risk ID 264 – Covid-19 o Risk ID 269 - Local economy and infrastructure. All of the Corporate risks were recorded as having been reviewed at least once during Quarter 4. A new Corporate Risk was added to the risk register during Q4 – Risk ID 289 Reducing & Tackling Fraud. No Corporate risks were deactivated. No risks were escalated to the Corporate Risk register.
2.2The report at Appendix A includes the risks as at 30/04/21 recorded within the Council’s Corporate Risk Register. The reports for each risk include the following information:
Risk title and description…to summarize and describe the risk. Risk Identification (ID) number…to identify and search for the risk in the register. Risk level…Corporate level risks. Responsible Officer…the officer responsible for managing the risk. Councillor…the Councillor whose portfolio the risk relates to. Last update…when the risk was last updated in the risk register. Historical RAG…the level of risk assigned historically each month over a 12 month period (Red – High; Amber – Medium; Green – Low). Current Control Measures…live actions assigned to control or mitigate the level of risk. Last update…the date of the last time the Control Measure was updated in the risk register. Risk response…how the risk is controlled. Projected Completion…the date the Control Measure is expected to be implemented. Closed Control Measures…Control Measures that have been finalised, e.g. because they have been implemented. Closure date…date that Control Measures were closed. Historical impact…monthly assessment on the level of impact (1 = low; 5 = very high) should the risk come into effect. The graph shows the historical level of impact assigned each month over a 12 month period. Historical likelihood…monthly assessment on how likely the risk is to come into effect (1 = low; 5 = very high). The graph shows the historical level of likelihood assigned each month over a 12 month period.
3.0Risk Workshop – Control Measures
3.1The draft Annual Governance Statement for 2020/21 sets out that the quality of risk information within the risk register needs to be improved. A workshop on Risk Control Measures will be held with Leadership Team on 25th May 2021.
4.0Future Reporting
4.1The Chair has requested that Directors attend each quarter on a rotational basis and provide the Governance & Audit Committee with presentations regarding the internal control environment, including risk management; this report providing a Corporate Risk overview will coincide with Director’s attendance each quarter. 5.0 Integrated Assessment Implications
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
08 (2 of 2): Appendix A_Corporate risks @ 30.04 (snapshot)Appendix | 190 KB | Download |
PDF |
Corporate Risk Overview 2020/21: Quarter 4. (For Information) (Richard Rowlands)Report | 342 KB | DownloadRead as text |
Follow Governance & Audit Committee at Swansea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | Disclosures of Personal and Prejudicial Interests.Councillors M White & P Bentu declared personal interests in item 9. | Decided | Open |
| 2 Sep 2026 | Minutes.Approved. | Approved | Open |
| 2 Sep 2026 | Internal Audit Monitoring Report – Q1 2026/27.Noted. | Noted | Open |
| 2 Sep 2026 | Governance & Audit Committee - Self-Assessment of Good Practice 2025-2026.Withdrawn. | Decided | Open |
| 2 Sep 2026 | Successful and Sustainable Swansea Corporate Transformation Plan Annual Report 2025-26.For information. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.