Newton Abbot - 25/00345/MAJ - Langford Bridge

Approved Planning 1 paper

AI summaryTeignbridge Planning Committee approved reserved matters for the primary infrastructure of the Langford Bridge development in Newton Abbot, including a spine road, drainage basin and landscaping, subject to four conditions.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedApproval with four planning conditions and an informative
MoneyNot stated
What happens nextOutline conditions to be dischargedSeveral conditions must be cleared before works start
Who it affectsLangford Bridge site, Newton AbbotSouth side of Newton Abbot, 2km from town centre

What was decided

Reserved matters for the infrastructure phase (appearance, landscaping, layout and scale) were approved, subject to four conditions covering approved plans, landscaping implementation, replacement planting and surface water drainage, plus an additional informative that future related development should minimise reliance on on-street parking. Report P1, P2, P5, P11, P14

The final wording of the additional informative is to be agreed by the Head of Development Management in consultation with Councillors Bullivant and MacGregor.

The conditions attached to the outline permission and obligations in the S106 legal agreement dated 17th July 2020 remain applicable. Report P17

Why

Officers concluded the submission accords with the outline part of the hybrid permission, satisfying the relevant land use and ecological mitigation parameter plans and the approved Masterplan and Design Code. Report 6.1, 6.6, 6.12, 6.18

Natural England raised no objections and ecological consultants Burton Reid Associates confirmed the proposals will not adversely affect the integrity of the South Hams Special Area of Conservation, including for greater horseshoe bats. Report 6.9, 7.6, 7.8, P153, P156

The Lead Local Flood Authority, the County Highway Authority and the Environment Agency raised no objections subject to detailed drainage design and a flood risk activity permit informative. Report 6.36, 6.19, P149, P151, P152, P155

What happens next

Several outline conditions (12 Surface Water Drainage, 13 Trees, 14 Biodiversity, 17 CEMP Biodiversity, 18 LEMP, 20 Contamination, 21 CEMP Construction, 23 Foul Water) must be discharged before the infrastructure phase commences, and condition 16 (lighting) before any external lighting is installed. Report P20, P21, P22

Full details of the sizes, locations, specifications and maintenance strategy for tree pits and the rainwater garden on drawing PERSW24830-11B 2of2 must be submitted to and approved in writing by the Local Planning Authority, in consultation with the Lead Local Flood Authority and Devon County Council Highway Authority. Report P6, 6.40

The detailed design of the surface water drainage system will be required under a separate application to discharge condition 12, including long-term management of the attenuation basin before commencement. Report 6.36, 6.37

Options considered

  • Chosen: Grant reserved matters subject to conditions and an informative. Submission accords with outline permission parameter plans, no objections from statutory consultees including on bats, drainage and highways, and a new access onto the Wolborough Link Road reduces construction and residential vehicle conflict. Report P1, 6.6, 6.19, 7.8, 8.1
  • Rejected: Refuse reserved matters Report P1

Implications

  • Legal: Obligations secured under the S106 legal agreement dated 17th July 2020 continue to apply, and conditions on the outline permission remain in force. Report P17
  • Legal: As Competent Authority, Teignbridge District Council adopted the conclusion dated 31st July 2025 of Burton Reid Associates that there will be no effect on the integrity of the South Hams Special Area of Conservation. Report 7.8, P153
  • Environment and climate: The application is exempt from the mandatory Biodiversity Net Gain requirement because the outline permission predates its introduction, and the carbon reduction condition does not apply because no buildings are proposed. Report 6.11, 7.3, 14.2
  • Environment and climate: Sensitive lighting design is required to protect greater horseshoe bat commuting corridors and dark areas, secured by the condition 16 discharge requirement before any external lighting is installed. Report 7.4, 7.5, P22
  • Risk: Detailed surface water drainage design, including for the proposed attenuation basin, must be approved before commencement, with the basin maintained to prevent blockages and flooding of future residential property, play areas and highway infrastructure. Report P15, P16, 6.36, 6.37
  • Other: An informative advises the applicant that works near a main river may require a Flood Risk Activity Permit from the Environment Agency under the Environmental Permitting (England and Wales) Regulations 2016. Report P18, P19, P149

Who and where

  • Future residents and users of the Langford Bridge development, including up to 450 dwellings, a local centre and employment uses Report 3.2, 8.1
  • Buckland Athletic Football Club, whose pitches and buildings adjoin the infrastructure phase Report 4.2
  • Devon County Council as Highway Authority for adoption of the new spine road Report 6.19, P155
  • Residents of Newton Abbot, particularly along Kingskerswell Road and the wider highway network Report 4.1, 7.13

Timeline

  • 17th July 2020: S106 legal agreement securing planning obligations signed Report P17
  • 24th July 2020: Hybrid planning permission 19/00238/MAJ approved for the wider Langford Bridge development Report P38
  • 11th April 2025: Application 25/00345/MAJ consulted on with Abbotskerswell Parish Council and Newton Abbot Town Council Report 9.3, 9.5
  • 22nd January 2026: Planning Committee site inspection held, with queries from Members on drainage, land excavation and pavement parking Report 7.11, 7.12, 7.22
  • 17th February 2026: Planning Committee resolved to grant reserved matters subject to conditions and an informative

Plain English for the jargon

  • Reserved matters: Aspects of a planning application (access, appearance, landscaping, layout, scale) not decided at outline stage and submitted later for approval
  • Hybrid permission: A planning application combining full permission for part of a site with outline permission for the rest
  • SuDS: Sustainable Drainage Systems, features such as attenuation basins, swales and rainwater gardens that manage surface water run-off
  • LLFA: Lead Local Flood Authority, here Devon County Council, responsible for surface water drainage matters
  • LEMP: Landscape and Ecology Implementation and Management Plan
  • HRA: Habitats Regulations Assessment, assessing effects on protected sites such as the South Hams SAC
  • SAC: Special Area of Conservation, a European designated site of nature conservation importance
  • BNG: Biodiversity Net Gain, a requirement for development to deliver a measurable increase in biodiversity
  • CIL: Community Infrastructure Levy, a charge on new development to fund infrastructure
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item138b

Resolved

RESOLVED RESERVED MATTERS BE GRANTED, subject to the following conditions and an additional INFORMATIVE which will advise that future developments related to the hereby approved road should be designed to minimise the reliance upon on street parking. The final wording to be agreed by the Head of Development Management in consultation with Councillors Bullivant and MacGregor. 1. Development in accordance with approved plans 1. Development in accordance with approved plans Date Received Drawing/Reference Number Description 26 Feb 2025 WOLB2/3-1300 REV P1 Site Location Plan 07 Apr 2025 ES23.051 PH4-02.03 REV P1 Primary Infrastructure Highway Sections 19 Aug 2025 ES23.051 03.50 REV P1 Drainage Outfall Plan 03 Nov 2025 ES23.051 SK-03.20 REV P3 Site-Wide Drainage Strategy - Catchment Areas 03 Nov 2025 ES23.051 30.04 REV T1 Adoptable Highway Construction Details - Sheet 4 03 Nov 2025 ES23,051 REV A SuDS Maintenance Plan 26 Nov 2025 PERSW24830-12B SUDs Proposals 01 Dec 2025 ES23.051 PL-RMA-02.01 REV P3 Spine Road General Arrangement Plan 01 Dec 2025 ES23.051 PL-RMA-03.00 REV P8 Drainage Strategy Sketch Overall Sheet 01 Dec 2025 ES23.051 PL-RMA-03.01 REV P9 Drainage Strategy Sketch Inset Sheet 01 Dec 2025 ES23.051 PL-RMA-10.02 REV P2 Spine Road Surfacing Plan Sheet 2 01 Dec 2025 ES23.051 PL-RMA-20.01 REV P2 Highway Visibility Plan Sheet 1 01 Dec 2025 ES23.051 PL-RMA-20.02 REV P2 Highway Visibility Plan Sheet 2 01 Dec 2025 ES23.051 PL-RMA-07.02 REV P3 Vehicle Tracking Plan - Refuse 01 Dec 2025 ES23.051 PL-RMA-08.00 REV P3 Impermeable Area Plan 01 Dec 2025 ES23.051 PL-RMA-09.00 REV P3 Overland Flow Flood Exceedance 01 Dec 2025 ES23.051 PL-RMA-10.01 REV P3 Spine Road Surfacing Plan Sheet 1 01 Dec 2025 ES23.051 PL-RMA-07.01 REV P3 Vehicle Tracking Plan - Fire 30 Jan 2026 PERSW24830-11B 2OF2 G.I. Proposals 30 Jan 2026 PERSW24830-11B 1OF2 G.I. Proposals REASON: To ensure compliance with the approved drawings. 2. Landscaping implementation Notwithstanding the hard and soft landscaping details shown on Green Infrastructure and SuDS proposals drawings numbered PERSW24830-11B 1of 2, PERSW24830-11B 2 of 2, and PERSW24830-12B, full details of the sizes, locations, specifications and maintenance strategy for the tree pits and rainwater garden annotated on PERSW24830-11B 2of2 shall be submitted to and approved in writing by the Local Planning Authority in consultation with the Lead Local Flood Authority and Devon County Council Highway Authority. In all other respects, the approved hard and soft landscaping scheme shall be carried out strictly in accordance with the approved details submitted on the approved Green Infrastructure and SuDS proposals drawings numbered PERSW24830-11B 1of2, PERSW24830-11B 2of2, and PERSW24830-12B. All approved hard and soft landscaping, including the SuDS and Green Infrastructure proposals, shall be completed and thereafter managed and maintained in accordance with a timetable of implementation previously approved in writing by the Local Planning Authority. Thereafter, following substantial completion of the development hereby permitted, all soft landscape works shall be protected, managed and maintained in accordance with the approved details and to a standard in accordance with the relevant recommendations of British standard 4428 1989 Code of Practise for general landscape operations. ...
Word for word from the decision Teignbridge published for this meeting. Source: democracy.teignbridge.gov.uk

Follow this further

Built from Teignbridge's papers

What the report saysPro

Report to Planning Committee

Recommendation

RESERVED MATTERS BE GRANTED, subject to the following conditions:

1. Development in accordance with approved plans

Date Drawing/Reference Number Description Received 26 Feb 2025 WOLB2/3-1300 REV P1 Site Location Plan 07 Apr 2025 ES23.051 PH4-02.03 REV P1 Primary Infrastructure Highway Sections 19 Aug 2025 ES23.051 03.50 REV P1 Drainage Outfall Plan Site-Wide Drainage Strategy - Catchment 03 Nov 2025 ES23.051 SK-03.20 REV P3 Areas Adoptable Highway Construction Details - 03 Nov 2025 ES23.051 30.04 REV T1 Sheet 4 03 Nov 2025 ES23,051 REV A SuDS Maintenance Plan 26 Nov 2025 PERSW24830-12B SUDs Proposals ES23.051 PL-RMA-02.01 REV 01 Dec 2025 Spine Road General Arrangement Plan P3 ES23.051 PL-RMA-03.00 REV 01 Dec 2025 Drainage Strategy Sketch Overall Sheet P8 ES23.051 PL-RMA-03.01 REV 01 Dec 2025 Drainage Strategy Sketch Inset Sheet P9 ES23.051 PL-RMA-10.02 REV 01 Dec 2025 Spine Road Surfacing Plan Sheet 2 P2 ES23.051 PL-RMA-20.01 REV 01 Dec 2025 Highway Visibility Plan Sheet 1 P2 ES23.051 PL-RMA-20.02 REV 01 Dec 2025 Highway Visibility Plan Sheet 2 P2 ES23.051 PL-RMA-07.02 REV 01 Dec 2025 Vehicle Tracking Plan - Refuse P3 ES23.051 PL-RMA-08.00 REV 01 Dec 2025 Impermeable Area Plan P3 ES23.051 PL-RMA-09.00 REV 01 Dec 2025 Overland Flow Flood Exceedance P3 ES23.051 PL-RMA-10.01 REV 01 Dec 2025 Spine Road Surfacing Plan Sheet 1 P3 ES23.051 PL-RMA-07.01 REV 01 Dec 2025 Vehicle Tracking Plan - Fire P3 30 Jan 2026 PERSW24830-11B 2OF2 G.I. Proposals 30 Jan 2026 PERSW24830-11B 1OF2 G.I. Proposals

REASON: To ensure compliance with the approved drawings.

2. Landscaping implementation

Notwithstanding the hard and soft landscaping details shown on Green Infrastructure and SuDS proposals drawings numbered PERSW24830-11B 1of 2, PERSW24830-11B 2 of 2, and PERSW24830-12B, full details of the sizes, locations, specifications and maintenance strategy for the tree pits and rainwater garden annotated on PERSW24830-11B 2of2 shall be submitted to and approved in writing by the Local Planning Authority in consultation with the Lead Local Flood Authority and Devon County Council Highway Authority.

In all other respects, the approved hard and soft landscaping scheme shall be carried out strictly in accordance with the approved details submitted on the approved Green Infrastructure and SuDS proposals drawings numbered PERSW24830-11B 1of2, PERSW24830-11B 2of2, and PERSW24830-12B.

All approved hard and soft landscaping, including the SuDS and Green Infrastructure proposals, shall be completed and thereafter managed and maintained in accordance with a timetable of implementation previously approved in writing by the Local Planning Authority.

Thereafter, following substantial completion of the development hereby permitted, all soft landscape works shall be protected, managed and maintained in accordance with the approved details and to a standard in accordance with the relevant recommendations of British standard 4428 1989 Code of Practise for general landscape operations. Soft landscape maintenance details shall include the frequency of site visits and timings of general operations such as plant inspections, weed control, watering, fertiliser application, mulching and grass cutting.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Newton Abbot: 25/00345/MAJ: Langford BridgeReport 2.5 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 24 attended
TC
Trish CornsOfficer, in attendance
SS
Councillor Suzanne SandersChair, present
DC
Councillor David CoxVice-Chair, present
JB
Councillor Janet BradfordCommittee Member, present
PB
Councillor Phil BullivantCommittee Member, present
AH
Councillor Alex HallCommittee Member, present
SH
Councillor Stephen HornerCommittee Member, present
JN
Councillor John NutleyCommittee Member, present
PP
Councillor Paul ParkerCommittee Member, apologies
DP
Councillor David PalethorpeCommittee Member, present
KS
Councillor Kevin SmithCommittee Member, present
PW
Councillor Peter WilliamsCommittee Member, apologies

All 24 on the meeting page

On this subject at Teignbridge

Search all
  1. Newton Abbot - 25/00345/MAJ - Langford BridgeThis decision
  2. 22/01597/FUL - Alexandra Cinema, Newton AbbotApproved
  3. 22/01598/LBC - Alexandra Cinema, Newton AbbotApproved
  4. 22/01597/FUL - Alexandra Cinema, Newton AbbotDeferred
  5. 22/01598/LBC - Alexandra Cinema, Newton AbbotDeferred
  6. 22/02069/MAJ - Wolborough Barton, Newton AbbotApproved

More from Teignbridge Planning Committee

All decisions
MeetingDecisionOutcome
22 Sep 2026 MinutesThe of the meeting held on 21 July 2026 were approved as a correct record and signed by the Chair. Approved Open
22 Sep 2026 ASHBURTON - 25/01752/FUL - Land at GoodstoneRESOLVED Planning permission be approved subject to the following conditions: 1. The development hereby permitted sha... Approved Open
22 Sep 2026 BICKINGTON - 26/00876/MAJ - Land at Chipley MillRESOLVED a) The application be referred to the Secretary of State in accordance with the Town and Country Planning (C... Approved Open
21 Jul 2026 Kerswell-with-Combe - 25/01844/MAJ - Land at East of Buckland Road25/01844/MAJ - Land to the East of Buckland Road Newton Abbot Outline application for up to 50 dwellings, public open... Approved Open
12 May 2026 Woodland - 26/00353/HOU - Sunset Cottage House CrossRESOLVED Planning Permission be granted subject to the following conditions: 1. The development hereby permitted shal... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies