Thanet Regeneration Programme - Theatre Royal Project Decisions
ApprovedScrutiny4 papers
AI summaryThanet Overview and Scrutiny Panel has endorsed proposals to reallocate £1,000,000 of Margate Town Deal funds to the Theatre Royal project, start procurement of capital works contractors, and delegate authority to secure a leasehold operator.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedPanel backed all four parts of the proposal
Money£1,000,000 reallocationFrom Active Movement and Connections contingency to Theatre Royal
What happens nextCabinet to make final decisionsDecisions also noted in Panel endorsement
Who it affectsMargate Central wardTheatre Royal and 19 Hawley Square
What was decided
Endorsed the reallocation of £1,000,000 of Active Movement and Connections Margate project funds to the Theatre Royal, taking the total project budget to £6,000,000. Report P11, P15
Endorsed starting procurement of contractor(s) for the Theatre Royal capital works via a single-stage traditional JCT route on the Kent Business Portal. Report P12, P49
Endorsed delegating authority to the Head of Property, with the Cabinet Member for Regeneration and Property, to enter into lease arrangements with a future independent operator for the Theatre Royal and 19 Hawley Square, and noted the RIBA Stage One masterplan and phase one scheme to reopen the theatre. Report P13, P14, P56
Why
The original £2,200,000 Margate Town Deal allocation for a creative production cluster could not attract additional external grants, with £10.5m of bids unsuccessful. Earlier, £2,800,000 was reallocated from the Active Movement and Connections intervention in August 2024. Report P15, P19, P20
The May 2024 plan for the council to lead a new operating trust is no longer financially viable after the Cultural Development Fund bid, which included £395,000 of revenue for two years of staffing, was unsuccessful. A lease to a third-party operator is now the recommended route, with legal advice from Sharpe Pritchard supporting it. Report P17, P22, P53, P54
The Theatre Royal is the UK's second oldest working theatre, on the Theatres at Risk Register since 2018, and requires urgent work to safeguard the Grade II* listed building, which was valued at nil in 2019. Report P24, P25
What happens next
Listed Building Consent and planning applications are scheduled for February 2026, with procurement of contractors and RIBA Stage Three design work progressing in parallel. Report P16, P30, P49
Officers will market the operator opportunity competitively, with the council expressing a preference for a charitable governance structure, while the Section 151 Officer continues quarterly monitoring returns to MHCLG. Report P56, P73, P75
Fundraising for the unfunded Phase Two (19 Hawley Square) and Phase Three decarbonisation will begin in 2026, in partnership with the new operator and with the National Lottery Heritage Fund and Arts Council. Report P37, P58
The money
£1,000,000 Reallocation from Active Movement and Connections contingency to Theatre Royal Report P11, P15
£2,200,000 Initial Margate Town Deal allocation for a creative production cluster Report P15, P19
£2,800,000 Previously reallocated from Active Movement and Connections on 22 August 2024 Report P15, P20
£6,000,000 Total project budget after this reallocation, including revenue element Report P15, P76
£4.1m Estimated RIBA Stage One construction value for the phase one theatre reopening Report P21, P44
£4.4m Phase one capital works budget including fees, inflation, overheads and 20% QS retained contingency Report P21, P49
£7.2m Cost of the full masterplan across both Theatre Royal and 19 Hawley Square Report P21, P44
£395,000 Lost revenue funding for two years of staffing and operational costs in unsuccessful Cultural Development Fund bid Report P17, P22
£4,477,174.17 Procurement threshold under the Act as of Oct 2025, exclusive of VAT Report P49
£10.5m Total value of unsuccessful external funding applications Report P19, P58
£5,000,000 Original Local Regeneration Fund allocation (£4,800,000 capital budget) to the project Report P76
£459,375 Projected additional annual gross income from phase one operational changes Report P25, P48
£300,000 Projected gross annual income from 19 Hawley Square at 60% capacity Report P25
£218,750 Projected additional annual box office income from expanded capacity and 250 shows Report P45
£175,000 Projected annual internal bar spend across stalls and circle bars Report P47
£65,625 Projected annual income from the public piazza and seasonal front of house space Report P47
£3.1m Remaining masterplan funds still to be secured for 19 Hawley Square Report P58
£350,000 2019 valuation of 19 Hawley Square, with condition noted to have deteriorated since Report P60
Options considered
Rejected: Do nothing and reallocate the funding elsewhere or return it to central government. Would leave the Grade II* listed theatre at further risk and keep it on the Theatres at Risk Register Report P61, P66
Chosen: Approve the four recommendations (reallocation, procurement, delegation, note RIBA Stage 1). Only viable option given time and financial constraints; essential to use Margate Town Deal funding and safeguard the theatre Report P62, P63, P64, P65, P66
Implications
Financial: Project must be fully funded from external grant allocations; the council has no scope or agreement to invest its own funds, and no current revenue budget to support ongoing theatre operations. Report P72, P78
Financial: External funding rises from £5,000,000 (£4,800,000 capital) to £6,000,000 (£5,800,000 capital) after this reallocation. Report P76
Legal: A lease exceeding seven years is a disposal at undervalue; Cabinet must be satisfied the General Disposal Consent Order 2003 conditions (undervalue under £2 million and promotion of economic, social or environmental well-being) are met. Report P82, P83, P84, P85
Legal: Any selected operator, charitable or commercial, must be independent of the council; the council may need to 'opt to tax' to protect its partial exemption VAT status. Report P53, P77
Equalities: An equalities screening found no direct equalities considerations and a full EQIA was not required; the project is expected to benefit local residents including those with protected characteristics through training and employment. Report P123, P124
Climate: Design supports the council's 2030 net zero goal through air source heat pumps, insulation, triple glazing, LED lighting, and restoration rather than demolition; minimum 5% of tender quality score is allocated to environmental sustainability. Report P33, P119, P120
Risk: Key risks include failure to secure a suitable operator, operator business plan underperformance, and capital cost increases; mitigations include a 20% QS retained contingency, robust value engineering, early contractor engagement, and a master plan with fixed budgets. Report P97, P99, P100, P107, P110, P111, P114, P117
Staffing: Theatre Royal is to be operated by an independent third party rather than directly by the council, removing the need for the council to fund or run theatre operations directly. Report P17, P22, P51
Other: Restoration of the three heritage buildings in Hawley Square conservation area is a key strategy for tackling anti-social behaviour, vandalism and graffiti on these semi-derelict council-owned properties. Report P126
Who and where
Residents and visitors in Margate Central ward, including theatregoers, tourists and the local community Report P7, P39
Theatre Royal and 19 Hawley Square as heritage assets, currently on the Theatres at Risk Register Report P24
Local creative and cultural sector, including production companies and operators Report P89, P108
Potential future operator of the Theatre Royal and 19 Hawley Square Report P13, P53
Public engagement participants (over 50,000 online engagements since March 2023, plus 175 attendees at a December 2023 event and 200 survey responses) Report P26, P27
Timeline
21 September 2023: Cabinet decision: Simplification Pathfinder Pilot Report P127
December 2023: Officers issued a Prior Information Notice and ran a public event and survey on the theatre proposals Report P26, P53
January 2024: Early market engagement with 16 operators; eight early expressions of interest Report P22, P53
February 2024: Independent options appraisal and business case prepared Report P52
30 May 2024: Cabinet decided the council would lead a new operating trust (now superseded) Report P22, P52, P127
22 August 2024: Cabinet reallocated £2,800,000 from Active Movement and Connections to Theatre Royal Report P15, P20, P127
28 February 2025: Cabinet decision: Margate Regeneration Programme Report P127
July 2025: Architect and design team appointment completed; design at RIBA Stage One Report P16
May and July 2025: Independent legal advice from Sharpe Pritchard obtained on operator route Report P53, P129
December 2025: EID assessment completed Report P129
December 2025: Public engagement exercise to begin on publication of the Cabinet paper Report P69
15 January 2026: Overview and Scrutiny Panel endorses recommendations to Cabinet Report P2
February 2026: Listed Building Consent and planning applications scheduled for submission Report P16, P30, P69
2026: Remedial works to safeguard 19 Hawley Square, including pigeon clearance, to be carried out Report P59
2026: Fundraising to begin for Phase Two and Three of the masterplan Report P58
2027: Target date to reopen the Theatre Royal under the phase one scheme Report P16
Plain English for the jargon
RIBA Stage One: The first stage of the Royal Institute of British Architects' work stages, covering preparation and brief, including initial design concepts and a cost plan.
Margate Town Deal: A central government Town Deal fund allocated to Margate, from which the Theatre Royal and other regeneration projects are funded.
Active Movement and Connections: A former Margate regeneration intervention on active travel and connectivity, scaled down in 2024 with funds reallocated to the Theatre Royal.
Listed Building Consent (LBC): Planning permission required for works to a listed building, applied for alongside planning permission in this project.
JCT Standard Building Contract With Quantities: A standard form of building contract issued by the Joint Contracts Tribunal, used here for the single-stage traditional procurement route.
General Disposal Consent Order 2003: Government order providing blanket consent for local authority disposals of land at undervalue up to £2 million where this secures promotion or improvement of the area's well-being.
QS (Quantity Surveyor): A construction cost professional who prepares cost plans, estimates and risk/contingency figures for building projects.
Local Government Reorganisation (LGR): The planned restructuring of local government in Kent, under which Thanet District Council will be merged into a new unitary authority.
Section 151 Officer: The local authority officer with statutory responsibility for the proper administration of the council's financial affairs.
MHCLG: Ministry of Housing, Communities and Local Government, the government department to which the council reports on Town Deal programme delivery.
EID: Equality Impact Decision, the council's screening or assessment of equalities implications of a decision.
Opt to tax: An election by a landlord to charge VAT on the rental of a property, used here to protect the council's VAT partial exemption position.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item207
Resolved
RESOLVED to endorse the recommendation as outlined in the report: To approve the reallocation of active movement and connections Margate project funds of £1,000k to the Theatre Royal project; To approve the procurement of contractors for capital works to the Theatre Royal; To delegate to the Head of Property, in consultation with the Cabinet Member for Regeneration and Property, the authority to enter into legal arrangements with an operator to run and manage the theatre and 19 Hawley Square; To note the RIBA Stage 1 plans.
Word for word from the decision Thanet published for this meeting.Source: democracy.thanet.gov.uk
3. DelegatetotheHeadofPropertyinconsultationwiththeCabinetMember for Regeneration and Property, to enter into legal arrangements with an operator, to run and manage the Theatre Royal and 19 Hawley Square.
25/014 - Health in All PoliciesRESOLVED to endorse the recommendations to Cabinet: To approve the adoption and implementation of the Health in All P...
26/008 - Draft 2026/27 HRA BudgetRESOLVED to endorse the recommendations as outlined in the report to Council as follows: The HRA budget for 2026/27 w...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.