Overview & Scrutiny Panel, Tuesday 3 February 2026 at 7.00pm

26/012 - Thanet Regeneration Programme - procurement decision

Decided Scrutiny 2 papers

AI summaryThanet scrutiny panel endorsed switching the Walpole Bay Beach Facilities works contract procurement from the London Construction Programme DPS to an open tender via the Kent Business Portal, sending the £805k scheme to Cabinet for approval.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecided
MoneyUp to £68k shortfall possible
What happens nextCabinet to decideCabinet authorisation needed to change procurement route
Who it affectsWalpole Bay, Cliftonville WestBeach facilities project in Margate, funded externally

What was decided

The Overview and Scrutiny Panel endorsed the recommendation to Cabinet to change the procurement route for the Walpole Beach Facilities works contract. Report P12, P13

The change moves the works contract from the London Construction Programme Dynamic Purchasing System to an Open Tender process via the Kent Business Portal. Report P13, P16, P31

Why

The project has changed in scale and scope, alongside changes to freedoms and flexibilities under the new Local Regeneration Programme and feedback from local contractors. Report P15, P30

After trialling the London Construction Programme Dynamic Purchasing System, the council no longer considers it the most appropriate route for this scheme. Report P16, P31

What happens next

Cabinet to authorise the change in procurement route, as the July 2024 Cabinet decision that approved the original route requires a new Cabinet decision to change it. Report P13, P46

The council aims to procure the works early 2026 to meet the project programme and external funding deadlines, using a JCT Intermediate Building Contract. Report P28

The Section 151 Officer will continue to scrutinise and approve regular monitoring returns to DLUHC, covering actual and forecast spend alongside delivery metrics. Report P42

The money

  • £1,083,300 Pre-tender approved budget for Walpole Beach Facilities works contract Report P25
  • £805,464 Project estimate for the works contract Report P25
  • £68k Additional budget that may be required to let the contract if estimated costs do not come down Report P41
  • £100k Budget held within the Access Walpole scheme that can fund the forecast gap Report P41
  • £346k Spent or committed on scheme preparatory works to the end of December 2026 Report P42

Options considered

  • Chosen: Approve the recommendation: authorise the change in procurement route for the works contract. Panel endorsed this to Cabinet following review of project risks, scale, scope and local contractor feedback Report P33
  • Rejected: Do nothing: continue on the basis of the planned procurement route (London Construction Programme DPS). Not recommended; the council no longer considers the previously proposed route most appropriate for the scheme Report P34, P31

Implications

  • Financial: Up to £68k of additional budget may be required to let the contract, with £100k available in the Access Walpole scheme as cover; £346k already spent or committed on preparatory works would need to be charged to revenue if the scheme does not proceed, affecting the council's already depleted reserves. Report P41, P42
  • Legal: The revised procurement process must comply with the Procurement Act 2023 and the council's Contract Procedure Rules; further advice will be sought from the in-house legal team on the final contract award. Report P19, P47, P49
  • Climate: Climate change and biodiversity has been a key consideration through design and planning; tenderer quality questions on positive climate change measures will be weighted in contractor selection. Report P54, P55
  • Risk: Each project has its own Risk Register; key risks are escalated to the Corporate Risk Register and reported to MHCLG through regular monitoring. Report P52
  • Other: Scheme is expected to have a positive impact on perceptions of safety in the immediate vicinity of the promenade in Cliftonville. Report P59

Who and where

  • Existing and new users of Walpole Bay in Cliftonville West, Margate Report P8, P27
  • Local construction market and contractors able to bid via the Kent Business Portal Report P13, P17, P30
  • Government funders (DLUHC/MHCLG) receiving monitoring and evaluation returns Report P42, P43

Timeline

  • 21 September 2023: Cabinet considered Simplification Pathfinder Pilot Report P61
  • December 2025: Planning approval received for the new beachfront facilities Report P28
  • Early 2026: Council aims to procure the works to meet project programme and external funding deadlines Report P28
  • 3 February 2026: Overview and Scrutiny Panel considered and endorsed the recommendation to Cabinet Report P2

Plain English for the jargon

  • DPS (Dynamic Purchasing System): An electronic procurement system for buying works, goods or services, used here as the original proposed route via the London Construction Programme.
  • Open Tender: A transparent, competitive procurement method governed by Contract Standing Orders where any interested supplier can submit a bid.
  • JCT Intermediate Building Contract: A mid-level construction contract for projects needing detailed provisions but lacking complex services, between Minor Works and Standard Contracts.
  • CSOs (Contract Standing Orders): The council's internal rules governing how contracts must be procured and awarded.
  • Section 151 Officer: The council officer with statutory responsibility for financial administration.
  • DLUHC / MHCLG: Government departments overseeing regeneration funding and monitoring.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item226

Resolved

RESOLVED to endorse the recommendation to Cabinet.
Word for word from the decision Thanet published for this meeting. Source: democracy.thanet.gov.uk

Follow this further

Built from Thanet's papers

What the report saysPro

Report to Overview & Scrutiny Panel

​(26/012) - Thanet Regeneration Programme -​ ​Procurement decision​

​Overview and Scrutiny Panel​ ​3 February 2026​

​By​ ​ ouise​ ​Askew,​ ​Head​ ​of​ ​Regeneration​ ​and​ L ​Growth​

​Cabinet​​Portfolio​​Member​ ​Cllr​ ​Ruth​ ​Duckworth,​ ​Cabinet​ ​Member​ ​for​ ​ egeneration and Property​ R

​Key Decision​ ​Yes​

​Decision classification​ ​Unrestricted​

​Call in status​ ​Yes​

​Ward:​ ​Cliftonville West​

​Purpose of the Report​

​ his​ ​report​ ​seeks​ ​authority​ ​to​ ​change​ ​the​ ​previously​​agreed​​procurement​​route​ T ​for​​the​​works​​contract​​for​​the​​Walpole​​Beach​​Facilities​​(formerly​​Pavilion)​​project​ ​within the Thanet Regeneration Programme for delivery.​

​Recommendation(s):​

​ hat​ ​the​ ​Overview​ ​and​ ​Scrutiny​ ​Panel​ ​review​ ​this​ ​report​ ​and​ ​comment​ ​on​ ​the​ T ​proposed recommendation to Cabinet, as follows:​

​ abinet​ ​is​ ​asked​ ​to​ ​authorise​ ​the​ ​change​ ​in​ ​procurement​ ​route​ ​for​ ​Thanet​ C ​Regeneration​​Programme​​project,​​the​​Walpole​​Beach​​Facilities​​(formerly​​Pavilion)​ ​works​ ​contract.​ ​This​ ​involves​ ​changing​ ​from​ ​the​ ​planned​ ​procurement​ ​route,​ ​which​ ​was​ ​to​ ​use​ ​the​ ​London​ ​Construction​ ​Programme​ ​Dynamic​ ​Purchasing​ ​System, to an Open Tender process via the Kent Business Portal.​

​1.​ ​Summary of Reasons​

​1.1​ ​This​ ​paper​ ​recommends​ ​the​ ​revised​ ​procurement​ ​route​ ​for​ ​one​ ​of​ ​the​ ​ orks contracts to ensure delivery of the capital regeneration programme.​ w ​1.2​ ​ he​​project​​has​​changed​​in​​scale​​and​​scope​​and​​this,​​alongside​​changes​​to​ T ​freedoms​ ​and​ ​flexibilities​ ​under​ ​the​ ​new​ ​Local​ ​Regeneration​ ​Programme,​ ​and​ ​feedback​ ​from​ ​local​ ​contractors​ ​has​ ​meant​ ​that​ ​the​ ​procurement​ ​strategy​ ​for​ ​this​ ​project​ ​has​ ​been​ ​revisited​ ​to​ ​consider​ ​project​ ​risks​ ​and​ ​opportunities at this time.​

​2.3​ ​ aving​ ​trialled​ ​the​ ​London​ ​Construction​ ​Programme​ ​Dynamic​ ​Purchasing​ H ​System​ ​(DPS),​ ​the​ ​council​ ​no​ ​longer​ ​considers​ ​the​ ​previously​ ​proposed​ ​procurement​ ​route​ ​to​ ​be​ ​the​ ​most​ ​appropriate​ ​for​ ​this​ ​scheme​ ​and​ ​is​ ​therefore​ ​seeking​ ​approval​ ​to​ ​move​ ​from​ ​using​ ​the​ ​London​ ​Construction​ ​Programme, DPS to an Open Tender process via the Kent Business Portal.​

​2.4​ ​ n​​Open​​Tender​​process,​​governed​​by​​Contract​​Standing​​Orders​​(CSOs),​​is​ A ​a​​transparent,​​and​​competitive​​procurement​​method​​where​​any​​interested​ ​supplier can submit a bid​​.​

​2.5​ ​ or​ ​the​ ​reasons​​set​​out​​above​​the​​council​​no​​longer​​considers​​the​​London​ F ​Construction​ ​Programme,​ ​Dynamic​ ​Purchasing​ ​System​ ​to​ ​be​ ​the​ ​most​ ​appropriate​ ​procurement​ ​route​ ​for​ ​this​ ​scheme.​ ​The​ ​appropriateness​ ​of​ ​making​​this​​change​​had​​been​​fully​​discussed​​and​​agreed​​with​​the​​council’s​ ​Procurement team and in consultation with Legal Services.​

​2.6​ ​ he​​contract​​will​​be​​procured​​in​​line​​with​​the​​council’s​​Corporate​​Procedure​ T ​Rules​ ​and​ ​will​ ​be​ ​compliant​ ​with​ ​the​ ​relevant​ ​procurement​ ​legislation​ ​(Procurement Act 2023 & related regulations).​

​2.​ ​Background​

​2.1​ I​ n​​July​​2024​​Cabinet​​approved​​the​​procurement​​and​​award​​of​​contracts​​for​ ​a​ ​number​ ​of​ ​projects​ ​in​ ​the​ ​Simplification​ ​Pathfinder​ ​Pilot​ ​programme​ ​(subsequently​ ​consolidated​ ​into​ ​one​ ​simplified​ ​fund​ ​called​ ​the​ ​Local​ ​Regeneration Fund).​

​2.2​ ​ he​ ​report​ ​presented​ ​to​ ​Cabinet​ ​outlined​ ​planned​​procurement​​routes​​for​ T ​each​ ​of​ ​the​ ​projects​ ​and​ ​each​ ​procurement​ ​route​ ​was​ ​selected​ ​based​ ​on​ ​individual project risks and opportunities at the time.​

​2.3​ ​ he​​report​​included​​the​​Walpole​​Beach​​Facilities​​(formerly​​Pavilion)​​-​​works​ T ​contract:​

​Project​ ​ re-Tender​ P ​ pproved​ A ​ rocurement​ P ​Estimate​ ​Budget​ ​Route​

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
26/012: Thanet Regeneration Programme: procurement decisionDecisions 165 KB DownloadRead as text
PDF
20260103 EIA Thanet Regeneration Programme: Procurement decision: Google DocsAppendix A 141 KB Download

At this meeting

Whole meeting

Who was there

10 of 20 attended
PF
Councillor Phil FellowsChair, expected
PF
Councillor Phil FellowsChair, present
DG
Councillor David GreenVice-Chair, absent
TA
Councillor Tricia AustinCommittee Member, present
JB
Councillor Joanne BrightCommittee Member, present
LB
Councillor Leo BritcherCommittee Member, present
HC
Councillor Helen CrittendenCommittee Member, apologies
AC
Councillor Alan CurrieCommittee Member, apologies
JD
Councillor John DavisCommittee Member, present
RF
Councillor Roopa FarookiCommittee Member, present
PM
Councillor Paul MooreCommittee Member, present
KP
Councillor Katie PopeCommittee Member, present

All 20 on the meeting page

On this subject at Thanet

Search all
  1. 26/012 - Thanet Regeneration Programme - procurement decisionThis decision
  2. 26/015 - Thanet Regeneration Programme - updateAgreed
  3. Thanet Regeneration Programme - Theatre Royal Project DecisionsApproved

More from Thanet Overview & Scrutiny Panel

All decisions
MeetingDecisionOutcome
18 Aug 2026 26/045 - Corporate Plan 2024-28, mid-term progress reviewIt was agreed that specific job target queries would be passed back to relevant heads of service, and members noted t... Agreed Open
18 Aug 2026 Quarter 4 Corporate Performance ReportRESOLVED to note the report. Noted Open
18 Aug 2026 25/014 - Health in All PoliciesRESOLVED to endorse the recommendations to Cabinet: To approve the adoption and implementation of the Health in All P... Approved Open
18 Aug 2026 Forward Plan and Exempt Cabinet Report listRESOLVED to note the Forward Plan and Exempt Cabinet Report List. Noted Open
3 Feb 2026 26/008 - Draft 2026/27 HRA BudgetRESOLVED to endorse the recommendations as outlined in the report to Council as follows: The HRA budget for 2026/27 w... Approved Open