That Cabinet agrees: 1. That it be noted the General Fund Capital Programme is projected to have unused resources of £9.591m as at 31 March 2015 although these will be carried forward to 2015/16 to fund schemes currently being developed or work in progress. 2. That the virement between the Civic Offices refurbishment programme and IT Connects, totalling £1.0m, be approved, which will realign project budgets with projected costs. 3. That a further budget allocation of £1.5m to the PRU development at the Jack Lobley site be approved, which will fund design works and additional construction costs. 4. That it be noted the Housing Revenue Account Capital Programme is projected to have unused resources of £2.050m as at 31 March 2015 although this will be carried forward to 2015/16 to fund schemes currently being developed or work in progress. Reason for Decision - as stated in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Cabinet last considered the 2014/15 Capital Programme at its meeting on 17 December 2014 (General Fund and Housing Revenue Account).
Since the last reported position, additional funding has been added to the programme, funded from prudential borrowing and other grants. In addition, a number of budgets within the Children’s directorate have been re-profiled to re-align budgets with expected spend.
This report pulls all of the changes together and sets out the latest forecasted outturn position.
Capital budgets cannot contribute to the General Fund revenue position although officers ensure that all appropriate capitalisations occur.
1. Recommendation(s)
That Cabinet agrees:
1.1To note that the General Fund Capital Programme is projected to have unused resources of £9.591m as at 31 March 2015 although these will be carried forward to 2015/16 to fund schemes currently being developed or work in progress;
1.2To approve the virement between the Civic Offices refurbishment programme and IT Connects, totalling £1.0m, which will realign project budgets with projected costs; 1.3 To approve a further budget allocation of £1.5m to the PRU development at the Jack Lobley site, which will fund design works and additional construction costs;
1.4To note that the Housing Revenue Account Capital Programme is projected to have unused resources of £2.050m as at 31 March 2015 although this will be carried forward to 2015/16 to fund schemes currently being developed or work in progress.
2. Introduction and Background
2.1This report provides an update to Cabinet on the financial position of the Capital programme and highlights significant variances. It is the second monitoring report for 2014/15 and is based on expenditure at month 9 (April to December) and projected expenditure for the remainder of the year.
2.2Capital schemes and resources are distinguished over two specific categories:
Mainstream Schemes – Capital expenditure that is funded by supported or unsupported (prudential) borrowing, by capital receipts, from the Revenue Budget or from earmarked reserves.
Specific Schemes – Capital expenditure that is funded by external funding sources, for example, Government Grants and Section 106 monies that can only be spent on specific projects.
3. General Fund Schemes
3.1Appendix 1 sets out the Capital Programme at Month 9 showing the movement since the last reported position and the resources that are available to finance the programme.
3.2The current position for General Fund Schemes for 2014/15 is summarised in Table 1 and analysed in further detail within Appendix 2. Table 1: Capital Programme – Projected Outturn Latest Projected Variance Agreed Outturn against Budget budget
Month 9 Month 9 Expenditure: £000’s £000’s £000’s Children’s Service (Note: the schools capital budget is designed around academic years 18,093 16,174 (1,919) and officers are confident that this will be defrayed in full within the current academic year). Adult Social Care 168 114 (54) Environment 2,242 895 (1,347) Planning and Transportation 5,840 5,374 (466) Housing General Fund 2,265 1,656 (609) Commercial Services 476 231 (245) Transformation 4,772 6,261 1,489 Chief Executive Delivery Unit 11,164 4,724 (6,440)
Total Expenditure (see appendix 2) 45,020 35,429 (9,591)
Resources: Mainstream (21,737) (14,916) 6,929 Specific (23,283) (20,513) 2,662
Total Resources (45,020) (35,429) 9,591
Forecast Deficit in Resources 0 0 0
3.3Table 1 is showing that the projected outturn for the year is £35.429m which is £9.591m less than the latest agreed budget for the year. 3.4 The forecast variance is further analysis in Table 2
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.