2018/19 Capital Monitoring Report - Quarter 3

Noted Executive 3 papers

Cabinet noted this item on Wednesday 13 March 2019. Below is the council's own wording, with the papers it was decided on.

Item121

Resolved

That Cabinet: 1. Noted the General Fund capital programme is projected to have available resources of £16.154m as at 31 March 2019 with this funding carried forward to 2019/20 to fund schemes currently in progress. 2. In addition, there is further £50.546m in the approved programme that is under development and/or dependent on third party actions as set out in paragraph 3.5 3. Noted the Housing Revenue Account capital programme is projected to breakeven by 31 March 2019, which will be funded from the Housing capital receipts.
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Cabinet

Executive summary

At its meeting on 28 February 2018, Council agreed the 2018/19 capital programme.

Since the 1 April 2018, additional funding has been added to the programme, funded from prudential borrowing and other grants. In addition, budget carry forwards from 2017/18 have also been added to the programme.

This report reflects these changes and sets out the latest forecasted outturn.

1. Recommendation(s)

That Cabinet:

1.1Note the General Fund capital programme is projected to have available resources of £16.154m as at 31 March 2019 with this funding carried forward to 2019/20 to fund schemes currently in progress;

1.2In addition, there is a further £50.546m in the approved programme that is under development and/or dependent on third party actions as set out in paragraph 3.5;

1.3Note the Housing Revenue Account capital programme is projected to breakeven by 31 March 2019, which will be funded from the Housing capital receipts.

2. Introduction and Background

2.1This report provides an update to Cabinet on the financial position of the capital programme and highlights significant variances. It is the third monitoring report for 2018/19 and is based on expenditure to the end of month 9 (the period 1 April 2018 to 31 December 2018) and projected expenditure for the remainder of the year.

2.2Capital schemes and resources are identified in two specific categories:

 Mainstream schemes – capital expenditure funded through prudential (unsupported) borrowing, from capital receipts, from the capital contribution from revenue budget or from earmarked capital reserves.

 Specific schemes – capital expenditure funded through external funding sources, for example, government grants and Section 106 monies which are ring fenced for specific projects.

3. General Fund Schemes

3.1The current position for General Fund schemes for 2018/19 is summarised in Table 1. Table 1: Capital Programme – Projected Outturn as at Month 9

Latest Projected Variance Agreed Outturn against Budget to budget 31/03/2019 £’000’s £’000’s £’000’s Expenditure: Children’s Service1 10,284 7,149 (3,135) Adult, Housing & Health 2,438 1,708 (730) Housing General Fund 1,448 92 (1,356) Environment and Highways 13,193 11,881 (1,312) Place 35,190 26,856 (8,334) Finance and IT 2,552 2,552 0 HR, OD & Transformation 4,150 2,888 (1,262) Customer Services 40 15 (25)

Total Expenditure 69,295 53,141 (16,154)

Resources: Prudential Borrowing (24,280) (18,839) 5,441 Capital Receipts (290) (267) 23 Reserves (74) (74) 0 Revenue Contributions to Capital 0 (167) (167) Government Grants (11,207) (8,646) 2,561 Other Grants (26,845) (20,400) 6,445 Developers Contributions (S106) (6,599) (4,748) 1,851

Total Resources (69,295) (53,141) 16,154

Forecast Overspend in Resources 0 0 0

3.2Table 1 illustrates a projected outturn at the end of the financial year of £53.141m, which is £16.154m less than the latest agreed budget for the year. This forecast variance is further analysed in Table 2 below.

1 The schools capital budget is designed around academic years and officers are confident that this

will be defrayed in full within the current academic year Table 2: – Analysis of forecast variance

Re-profiling Capital Completed Forecast of schemes Projects variance expenditure requiring against at additional budget at Month 9 funding Month 9

Expenditure: £’000 £’000 £’000 £’000 Children’s Service (3,135) 0 0 (3,135) Adult, Housing & (730) 0 0 (730) Health Housing General (1,356) 0 0 (1,356) Fund Environment and (1,312) 0 0 (1,312) Highways Place (8,501) 167 0 (8,334) Finance and IT 0 0 0 0 HR, OD & (1,262) 0 0 (1,262) Transformation Customer Services (25) 0 0 (25)

Total (16,321) 167 0 (16,154)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2018/19 Capital Monitoring Report: Quarter 3: Appendix 1Appendix 196 KB Download
PDF
2018/19 Capital Monitoring Report: Quarter 3: Appendix 2Appendix 71 KB Download
PDF
2018/19 Capital Monitoring Report: Quarter 3Report 118 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 9 attended
RG
Councillor Rob GledhillChair, present
SH
Councillor Shane HebbDeputy Chair, apologies
GC
Councillor Gary CollinsCommittee Member, present
MC
Councillor Mark CoxshallCommittee Member, apologies
JH
Councillor James HaldenCommittee Member, apologies
DH
Councillor Deborah HuelinCommittee Member, present
BJ
Councillor Barry JohnsonCommittee Member, present
SL
Councillor Susan LittleCommittee Member, present
AW
Councillor Aaron WatkinsCommittee Member, present

On this subject at Thurrock

Search all
  1. 2018/19 Capital Monitoring Report - Quarter 3This decision
  2. Revenue Capital Budget Monitoring Report Q2 2024-25Noted
  3. Q3 Monitoring Forecast Revenue and Capital Outturn 23/24Noted
  4. 2018/19 Capital Monitoring ReportNoted
  5. 2017/18 Capital Monitoring Report - Quarter 3 (Decision 0110466)Noted
  6. 2017/18 Capital Monitoring Report - Quarter 2 (Decision 0110444)Noted

More from Thurrock Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... Noted Open
16 Sep 2026 Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... Approved Open
16 Sep 2026 Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... Approved Open
16 Sep 2026 High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... Agreed Open
16 Sep 2026 Matrix Agency Worker 1 year contract extension2.1 Cabinet agreed to utilise the one-year extension option contained within the current contract and extend the exis... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies