RESOLVED That Cabinet: 1. Note the General Fund capital programme was projected to have available resources of £16.902 million as at 31 March 2017, with this funding carried forward to 2017/18 to fund schemes currently in progress or under development. 2. Note the Housing Revenue Account capital programme was currently forecasting an overspend of £0.502 million, but work was being undertaken to eliminate this by the 31st March 2017. Reason for Decision - as stated in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Cabinet last considered the 2016/17 Capital Programme at its meeting on 7 September 2016 (General Fund and Housing Revenue Account).
Since the last reported position, additional funding has been added to the programme and budgets have been profiled to realign them with expected spend.
This report reflects these changes and sets out the latest forecasted outturn position.
1. Recommendation(s)
That Cabinet:
1.1Note the General Fund capital programme is projected to have available resources of £16.902m as at 31 March 2017, with this funding carried forward to 2017/18 to fund schemes currently in progress or under development;
1.2Note the Housing Revenue Account capital programme is currently forecasting an overspend of £0.502m, but work is being undertaken to eliminate this by the 31st March 2017.
2. Introduction and Background
2.1This report provides an update to Cabinet on the financial position of the capital programme and highlights significant variances. It is the second monitoring report for 2016/17 and is based on expenditure to the end of month 6 (the period 1st April 2016 to 30th September 2016) and projected expenditure for the remainder of the year. 2.2 Capital schemes and resources are identified in two specific categories:
Mainstream schemes – capital expenditure funded through prudential (unsupported) borrowing, by the use of capital receipts, from the capital contribution from revenue budget or earmarked capital reserves.
Specific schemes – capital expenditure funded through external funding sources, for example, government grants and Section 106 monies, ring fenced for specific projects.
3 General Fund Schemes
3.1The current position for General Fund schemes in 2016/17 are summarised in Table 1 below.
Table 1: Capital Programme – Projected Outturn as at Month 6 Latest Projected Variance Agreed Outturn against Budget at budget 31/03/2017 £’000’s £’000’s £’000’s Expenditure: Children’s Service1 17,646 10,039 (7,607) Adult, Housing & Health 4,982 4,982 0 Environment and Place 40,211 33,528 (6,683) Finance and IT 1,372 792 (580) HR, OD & Transformation 5,238 3,206 (2,032)
Total Expenditure 69,449 52,547 (16,902)
Resources: Prudential Borrowing (37,857) (27,913) 9,944 Capital Receipts (1,828) (1,828) 0 Reserves (178) (236) (58) Government & Other Grants (27,011) (20,043) 6,968 Developers Contributions (S106) (2,575) (2,527) 48
Total Resources (69,449) (52,547) 16,902
Forecast Overspend in Resources 0 0 0
3.2Table 1 illustrates a projected outturn at the end of the financial year of £52.547m, which is £16.902m less than the latest agreed budget for the year. This forecast variance is further analysed in Table 2 below.
1 The schools capital budget is designed around academic years and officers are confident that this
will be defrayed in full within the current academic year Table 2: – Analysis of forecast variance Re-profiling Capital Completed Forecast of schemes Projects variance expenditure requiring against at additional budget at Month 6 funding Month 6
Expenditure: £’000 £’000 £’000 £’000 Children’s Service (7,501) 0 (106) (7,607) Adult, Housing & 0 0 0 0 Health Environment and (6,781) 366 (268) (6,683) Place Finance and IT (580) 0 0 (580) HR, OD & (2,032) 0 0 (2,032) Transformation
Total (16,894) 366 (374) (16,902)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.