That Cabinet: 1. Approve the re-procurement of two contract packages for the delivery of major works as set out in the report 2. Approve the re-procurement of one contractor to provide strategic support and cost management of the Housing Capital Programme as set out in the report 3. Approve delegated authority for award of the above contracts to the Corporate Director of Adults, Housing and Health in consultation with the Portfolio Holder for Housing. Reason for Decision – as stated in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Appendix 3a PROCUREMENT STAGE 1 – APPROVAL TO PROCEED TO TENDER This form must be completed for all procurements above the tender threshold (£75,000 - Services and Supplies and £500,000 – Works)
If contract value is over Cabinet approval threshold (£750,000) this form shall be attached with the request to tender report to Cabinet. This form will be “Open” for Publication.
Section A: ABOUT THIS PROCUREMENT
Title Transforming Homes Refurbishment Works 2018-21 Directorate Adults, Health and Housing Procurement PS/2017/524 Transforming Homes Refurbishments 2018-21 Reference Number Contract Cost £30M (Maximum Spend) Budget code(s) HR Introduction and This is a re-procurement for the refurbishment element of the Background Transforming Homes Programme currently underway. The current programme is delivered by 2 contractors, Keepmoat and Wates and it is proposed that the Council reprocure 2 again, to ensure competitiveness on price and quality, and that back up is in place in case of significant failure in one Proposed Contract 2 Years plus 1 Term Political Sensitivity None – the programme has been approved at Cabinet and this proposal has been through Housing Scrutiny Committee in February 2017.
Procurement Governance Forms – Stage 1: Approval to Proceed vNov 15 Section B: COMMISSIONING REPORT Business Case The Housing Capital Programme provides a comprehensive internal and external refurbishment programme through Transforming Homes which commenced in 2013 and is currently part-way through its fourth year. The original programme timeframe aimed to upgrade all major internal facilities and carry out any required external works in 5 years to 2018/19, thereby raising all domestic Council assets to the new Thurrock standard. The programme brings significant improvements to the long term viability of the council housing assets and to the living conditions for our residents. It also ensures the Council fulfils its duty to provide warm homes with modern facilities.
This procurement enables the programme to continue through the next three years. Key Deliverables High quality refurbishments within Thurrock Housing portfolio to (Draft Specification) above Decent Homes Standards Cost effective use of the HRA Social Value Outcomes Contractor N/A Employment Status (use self-assessment tool: https://www.gov.uk/guidanc e/check-employment- status-for-tax or contact Procurement for further guidance) Quality v Price 60:40 Quality:Price evaluation Social Value The Transforming Homes Programme has an excellent record of delivery against Social Value targets and this will continue with the new procurement. Current / Previous PS/2013/575d Refurbishment Works Contract details
FINANCIAL IMPLICATIONS Current / Previous Spend over Years 3-5 of the contract has been £XX. Contract Cost Cost Breakdown of Estimated 16/17 17/18 18/19 Later Total Breakdown Cost £000’s £000’s £000’s £000’s £000’s Total Spend £ £ £ £ £ Confirm Revenue Budget £ £ £ £ £ Funding Capital Budget £ £ £ £ £ Breakdown Identified Other (HRA) £ £ £8-10M £16-20M Up to £30M Other (Please State) £ £ £ £ £ Total Funding £ £ £10M £20M £30M Budget Code(s) H2000/H2200 Unsupported N/A borrowing?
Procurement Governance Forms – Stage 1: Approval to Proceed vNov 15 Other None Financial Implications
PROCUREMENT ROUTE ABOVE TENDER THRESHOLD (Choose 1(of A, B, C or D) only)
A. COMPETITIVE PROCUREMENT (complete B if a Framework) Procurement N/A Route
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.