That the Planning, Transport, Regeneration Overview and Scrutiny Committee note the progress made with the proposals for the Aveley Community Hub and review and comment on: 1. a) the business plan for the Aveley Community Hub; b) the proposals for the building; c) the proposal to combine phases of the build programme to develop the whole hub using a combination of S106 funds held by the Council and additional capital funding from the Community Hubs capital programme; 2. To support a report to Cabinet seeking approval to procure a building contractor.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Planning, Transport, Regeneration Overview and Scrutiny Committee
Executive summary
In March 2015 Cabinet considered a report on the Thurrock Library Service. The report outlined that the Council was working closely with Aveley Village Community Forum (AVCF) to progress plans for a new community building which would contain a library within a new Community Hub. Cabinet approved the approach outlined in the report, including the proposals for the Aveley scheme.
Since March 2015 good progress has been made, including the appointment of a professional team of architects and surveyors to work with the Council and AVCF to develop a design for the new building. The design process concluded with the planning application being submitted and approved 24th November 2016. Following approval of the planning application Bennesse (UK) Ltd were appointed to work with the steering group to conduct a further review of the business plan for operation of the new building to check that it is viable and that it meets community needs. The business plan is now complete and the next stages will be to complete technical design and to procure and appoint a building contractor to commence the construction of the new community centre.
This report updates the Committee on the project, seeks views on the new building and the business plan and support for request to Cabinet for approval to procure a building contractor for the scheme.
1. Recommendation(s) To note progress made with the proposals for the Aveley Community Hub and to review and comment on:
1.1a) the business plan for the Aveley Community Hub; b) the proposals for the building; c) the proposal to combine phases of the build programme to develop the whole hub using a combination of S106 funds held by the Council and additional capital funding from the Community Hubs capital programme;
1.2To support a report to Cabinet seeking approval to procure a building contractor.
2. Introduction and Background
2.1The Community Hubs programme aims to build and develop strong and sustainable partnerships between the voluntary sector and local communities in order to better meet the needs of local residents. The programme is overseen by the Community Hubs Strategic Board and a tailored approach to the development of hubs in each locality has been taken depending on existing arrangements, local groups and the dynamics of each situation.
2.2In Aveley the development of the hub has been led by the Aveley Village Community Forum (AVCF) who have a long held aspiration to develop an intergenerational centre in Aveley. Approximately £1M of Section 106 (Developer’s Contribution) is available to support the development of a new build facility and this, coupled with the aspirations of the AVCF and the conclusions of public consultations in the area combine to form the rationale for the identification of Aveley as the first purpose build hub facility.
2.3The development of proposals has been informed by extensive public consultation. The most recent community engagement survey was conducted in January 2015 by ngage. Beside an overwhelming demand for health and GP services the report highlighted demand for a number of services that could be delivered from a community hub:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Transport, Regeneration Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.