RESOLVED that Cabinet: 1. Noted the work completed to date and to support the development of a new building for the Aveley Community Hub; 2. Agree to the Council procuring a building contractor for the scheme and to delegate authority for appointment to the Corporate Director of Place in consultation with the Portfolio Holder for Regeneration, Highways and Transportation subject to budget provision. Reason for Decision – as stated in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Previously, Cabinet considered a report on the Thurrock Library Service. The report outlined that the Council was working closely with Aveley Village Community Forum (AVCF) to progress plans for a new community building which would contain a library within a new community hub. Cabinet approved the approach outlined in the report, including the proposals for the Aveley scheme.
Planning permission was approved 24th November 2016. Bennesse (UK) Ltd were appointed to work with the steering group to conduct a further review of the business plan for operation of the new building to check that is viable and that it meets community needs. The business plan demonstrates viability and the next sages will be to review and complete technical design and to procure and appoint a building contractor to commence the construction of the new community centre. The business plan will continue to evolve to take account of changes to design and to ensure viability.
This report updates Cabinet on the project, seeks support for the business plan and requests Cabinet approval to procure a building contractor for the scheme.
1. Recommendation(s)
1.1Note the work completed to date and to support the development of a new building for the Aveley Community Hub;
1.2Agree to the Council procuring a building contractor for the scheme and to delegate authority for appointment to the Corporate Director of Place in consultation with the Portfolio Holder for Regeneration, Highways and Transportation subject to budget provision. 2. Introduction and Background
2.1The Community Hubs programme aims to build and develop strong and sustainable partnerships between the voluntary sector and local communities in order to better meet the needs of local residents. The programme is overseen by the Community Hubs Strategic Board and a tailored approach to the development of hubs in each locality has been taken depending on existing arrangements, local groups and the dynamics of each situation.
2.2In Aveley the development of the hub has been led by the Aveley Village Community Forum (AVCF) who have a long held aspiration to develop an intergenerational centre in Aveley. Approximately £1M of Section 106 (Developer’s Contribution) is available to support the development of a new build facility and this, coupled with the aspirations of the AVCF and the conclusions of public consultations in the area combine to form the rationale for the identification of Aveley as the first purpose build hub facility.
2.3The development of proposals has been informed by extensive consultation. The most recent community engagement survey was conducted in December 2015 by ngage. Besides an overwhelming demand for health and GP services the report highlighted demand for a number of services that could be delivered from a community hub:
(57%) – GP Services (35%) – Health Services. (15%) – New joint adult social care, health and housing team which will work within the community to improve services before people hit severe problems. (15%) – Housing and library services changed to provide a modern approach. (15%) – Benefits advice (8%) – Youth and children activities (5%) – Community activities such as Arts and Crafts, Bingo, lunch clubs all ages, drop in for chats and more computer access
2.4The overwhelming majority (71%) supported the suggestion that the car park and part of the recreation ground should be the location for a new hub building to deliver these services.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.