2017/18 Capital Monitoring Report - Quarter 2 (Decision 0110444)

Noted Executive 1 paper

Cabinet noted this item on Wednesday 13 December 2017. Below is the council's own wording, with the papers it was decided on.

Item67

Resolved

RESOLVED that Cabinet: 1. Noted the General Fund capital programme is projected to have available resources of £6.467m as at 31 March 2018 with this funding carried forward to 2018/19 to fund schemes currently in progress; 2. Noted that there is a further £114.868m in the approved programme that is under development and/or dependent on third party actions as set out in paragraph 3.7; 3. Noted that the Housing Revenue Account capital programme is projected to have available resources of £21.040m as at 31 March 2018 with this funding carried forward to 2018/19 to fund schemes currently in progress. Reason for Decision – as stated in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Cabinet

Executive summary

Cabinet last considered the 2017/18 Capital Programme at its meeting on 13 September 2017 (General Fund and Housing Revenue Account).

Since the last reported position, additional funding from prudential borrowing and other grants has been added to the programme. In addition, budgets have been profiled to realign them with expected spend.

This report reflects these changes and sets out the latest forecasted outturn.

1. Recommendation(s)

That Cabinet:

1.1Note the General Fund capital programme is projected to have available resources of £6.467m as at 31 March 2018 with this funding carried forward to 2018/19 to fund schemes currently in progress;

1.2In addition, there is a further £114.868m in the approved programme that is under development and/or dependent on third party actions as set out in paragraph 3.7;

1.3Note the Housing Revenue Account capital programme is projected to have available resources of £21.040m as at 31 March 2018 with this funding carried forward to 2018/19 to fund schemes currently in progress. 2. Introduction and Background

2.1This report provides an update to Cabinet on the financial position of the capital programme and highlights significant variances. It is the second monitoring report for 2017/18 and is based on expenditure to the end of month 6 (the period 1 April 2017 to 30 September 2017) and projected expenditure for the remainder of the year.

2.2Capital schemes and resources are identified in two specific categories:

 Mainstream schemes – capital expenditure funded through prudential (unsupported) borrowing, from capital receipts, from the capital contribution from revenue budget or from earmarked capital reserves.

 Specific schemes – capital expenditure funded through external funding sources, for example, government grants and Section 106 monies which are ring fenced for specific projects.

3. General Fund Schemes

3.1The current position for General Fund schemes for 2017/18 is summarised in Table 1.

Table 1: Capital Programme – Projected Outturn as at Month 6 Latest Projected Variance Agreed Outturn against Budget to budget 31/03/2018 £’000’s £’000’s £’000’s Expenditure: Children’s Service1 6,558 5,351 (1,207) Adult, Housing & Health 1,860 1,246 (614) Environment and Place 40,946 37,605 (3,341) Finance and IT 3,067 2,317 (750) HR, OD & Transformation 4,317 3,762 (555) Customer Services 45 45 0

Total Expenditure 56,793 50,326 (6,467)

Latest Projected Variance Agreed Outturn against Budget to budget 31/03/2018 £’000’s £’000’s £’000’s

1 The schools capital budget is designed around academic years and officers are confident that this

will be defrayed in full within the current academic year Resources: Prudential Borrowing (35,481) (31,334) 4,147 Capital Receipts (320) (283) 37 Reserves (245) (97) 148 Government Grants (9,221) (7,757) 1,464 Other Grants (8,435) (8,322) 113 Developers Contributions (S106) (3,091) (2,533) 558

Total Resources (56,793) (50,326) 6,467

Forecast Overspend in Resources 0 0 0

3.2Table 1 illustrates a projected outturn at the end of the financial year of £50.326m, which is £6.467m less than the latest agreed budget for the year. This forecast variance is further analysed in Table 2 below.

Table 2: – Analysis of forecast variance Re-profiling Capital Completed Forecast of schemes Projects variance expenditure requiring against at additional budget at Month 6 funding Month 6

Expenditure: £’000 £’000 £’000 £’000 Children’s Service (1,207) 0 0 (1,207) Adult, Housing & (614) 0 0 (614) Health Environment and (2,122) 91 (1,309) (3,341) Place Finance and IT (750) 0 0 (750) HR, OD & (555) 0 0 (555) Transformation Customer Services 0 0 0 0

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2017/18 Capital Monitoring Report: Quarter 2 (Decision 0110444)Decisions 295 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
RG
Councillor Rob GledhillChair, present
SH
Councillor Shane HebbDeputy Chair, present
MC
Councillor Mark CoxshallCommittee Member, present
JH
Councillor James HaldenCommittee Member, present
DH
Councillor Deborah HuelinCommittee Member, present
BL
Councillor Brian LittleCommittee Member, present
SL
Councillor Susan LittleCommittee Member, present
AW
Councillor Aaron WatkinsCommittee Member, present
LC
Lyn CarpenterOfficer, in attendance
SC
Steve CoxOfficer, in attendance
KM
Kenna-Victoria MartinOfficer, in attendance

On this subject at Thurrock

Search all
  1. 2017/18 Capital Monitoring Report - Quarter 2 (Decision 0110444)This decision
  2. Revenue Capital Budget Monitoring Report Q2 2024-25Noted
  3. Q3 Monitoring Forecast Revenue and Capital Outturn 23/24Noted
  4. 2018/19 Capital Monitoring Report - Quarter 3Noted
  5. 2018/19 Capital Monitoring ReportNoted
  6. 2017/18 Capital Monitoring Report - Quarter 3 (Decision 0110466)Noted

More from Thurrock Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... Noted Open
16 Sep 2026 Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... Approved Open
16 Sep 2026 Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... Approved Open
16 Sep 2026 High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... Agreed Open