Resolved
That Cabinet: 1. Reviewed the response to the motion raised by Councillor Aker MEP and agreed that the current and planned actions set out within the report were sufficient.
Cabinet agreed this item on Wednesday 12 December 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That Cabinet: 1. Reviewed the response to the motion raised by Councillor Aker MEP and agreed that the current and planned actions set out within the report were sufficient.
At the Council meeting of 27 June 2018, Councillor Tim Aker MEP, Member for Aveley and Uplands raised a motion as follows:
“This Council calls on Cabinet to commit to looking at each private contract and assess whether, or not, it could be fulfilled locally and begin a process of bringing private contracts back in-house as soon as possible so that the Council can maximise the benefits for Thurrock rather than multi-national corporations.” Following discussion, the motion was carried by majority vote (25 to 14) and this report provides the formal response to the query. It should be noted that Members in support of the motion commented that “not all services should be in-house – but that all options should be available and be presented fairly” (Councillor Spillman) and that this review would “ensure best value was being maintained for residents and had the best interest for local businesses and the environment” (Councillor Kent). As Portfolio Holder, Councillor Hebb concurred with Councillor Kent and confirmed that steps had been taken to ensure that all Council services were commissioned in a way that established best quality and value for Thurrock.
National (and EU) legislation controls how the public sector procures goods, works and services in the provision of their statutory responsibilities. Within these boundaries, officers carry out rigorous options appraisals to determine the best course of action, including whether services should be delivered in-house or through a third party (outsourced), and in what arrangement or package – which then influences the size of contract and suitability for smaller or larger organisations.
Overall, it is felt that the balance of in-house v. outsourced is right, with currently 60% (of the number of) services delivered by Thurrock Council, 24% by local businesses or small organisations and only 16% by larger national companies. Perhaps understandably, the 16% is concentrated on high risk, high value services however, such as housing developments, housing repairs, large engineering projects and dispersed social services such as placements for looked after children and adult social care.
This report provides a detailed response and demonstrates the current balance of services; how Thurrock is working to support local businesses and the voluntary sector to improve their access to contracts; and the background setting out the Council’s responsibilities for procurement.
Recommendation(s)
1 Cabinet is recommended to review the response to the motion raised by Cllr Aker MEP and agree if the current and planned actions set out within the report are sufficient.
2. Introduction and Background
2.1The motion raised by Councillor Aker MEP at Council on 27 June 2018 brings about the following key questions:
1. What is the balance of in-house v. outsourced services delivered by Thurrock Council? 2. Are larger organisations getting too much benefit from the Council’s spending power? 3. Could the Council do more to support local businesses and the voluntary sector?
These questions are answered in Section 4 of this report.
2.2The Public Contracts Regulations 2015 – which is the UK’s statutory interpretation of EU Procurement Rules, and the Council’s own Constitution Contract Procedure Rules (Constitution Part 9 Chapter 2) sets out clear rules and guidance for the procurement of goods, works and services. Both of these are based on an assumption of competition to deliver best value.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Review of Outsourced Service Provision (Decision 110490)Decisions | 155 KB | DownloadRead as text |
Follow Cabinet at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... | Noted | Open |
| 16 Sep 2026 | Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... | Approved | Open |
| 16 Sep 2026 | Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... | Approved | Open |
| 16 Sep 2026 | High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... | Agreed | Open |
| 16 Sep 2026 | Matrix Agency Worker 1 year contract extension2.1 Cabinet agreed to utilise the one-year extension option contained within the current contract and extend the exis... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.