That Cabinet: 1. Noted the regeneration and investment opportunity presented by the acquisition of land identified in Appendix A which could be used for employment use purposes. 2. Approved the proposed freehold acquisition of the site as outlined in Appendix A of this report pursuant to Section 227 of the Town and Country Planning Act 1990, as well as Section 120 of the Local Government Act 1972, and delegated authority to the Corporate Director of Place and Director of Finance, in consultation with the Cabinet Member for Regeneration to negotiate and agree final terms for the site’s acquisition and to enter into any necessary agreements for the purchase of the site for the Council. 3. Approved the development of the site as outlined in the report and delegated authority to the Corporate Director of Place to finalise the scheme, submit a planning application and enter into appropriate development agreements for its development in accordance with the planning permission.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
On the 25 October 2017, Council approved the Investment and Treasury Management indicators to support an investment strategy as part of the wider requirement to deliver a balanced budget. The latest Treasury Management Strategy was approved in February 2018. The October 2017 report outlined the approach for future cash investment decisions and in particular noted in section 3.10 that the investment approach would include “the need to acquire or build revenue generating assets, especially where this meets regeneration or economic need”.
A unique opportunity has come to the market for a large parcel of land in West Thurrock which is strategically located within close proximity to the M25. It is suitable for commercial use and in close proximity to Purfleet, existing industrial units will need to be relocated.
Acquisition of the site would support the wider regeneration of the area. It could also provide “lift and shift” space for businesses located in other industrial estates in Thurrock. The acquisition and subsequent industrial development of the site could result in 850 people being employed at the site, whilst generating in excess of 80 direct and indirect jobs during the construction period. This site would support the Council’s wider economic development objectives, creating new jobs and retaining businesses in Thurrock that would potentially relocate outside of the Borough.
The Council commissioned property consultancy Lambert Smith Hampton (LSH) to advise on the potential acquisition of the industrial development land. An initial report was submitted in April 2018 and the company was commissioned to undertake further due diligence, including the commissioning of preliminary architectural and cost consultancy advice. An additional consultancy, GVA, was commissioned to carry out due diligence checks on the LSH report including land value and the feasibility of the proposed scheme – these were all confirmed as being reasonable.
Discussions have progressed with the land owner and on 31 August 2018 a provisional offer was made with the request to allow the Council to enter into a 3 month exclusivity period. This exclusivity period will allow for;
the Council to carry out additional checks on the land including soil investigations allowing for a more accurate land valuation and assessment of development risks the Council to enter into pre-planning application discussions regarding the site’s future use Council to revaluate the proposed financial offer to the land owner receive the approval of Cabinet to enter into final negotiations with the land owner and make a final offer up to an authorised maximum offer as advised by LSH
1. Recommendation(s)
That Cabinet:
1.1notes the regeneration and investment opportunity presented by the acquisition of land identified in Appendix A which could be used for employment use purposes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.